Project Time Table Sample Clauses

Project Time Table. 2.2.1 Construction of the proposed works is scheduled to commence in March 2003, for completion in October 2004. The tentative implementation programme is shown in Table 2.1. Stage 1 Site establishment March 03 – April 03 (2 months) Stage 2 Demolition of existing entrance C3 structure May 03 (1 month) Stage 3 Drainage works / Utilities diversions June 03 – July 03 (2 months) Stage 4 Temporary works and road decking August 03 – January 04 (6 months) Stage 5 Excavation for subway (works underground) February 04 (1 month) Stage 6 Construction of subway (works underground) March 04 – June 04 (4 months) Stage 7 Backfill and reinstatement July 04 – October 04 (4 months)
AutoNDA by SimpleDocs
Project Time Table. In order to provide your group with meaningful projects, we request that you indicate which months of the year you intend to volunteer. You do not need to give a specific date or time and this information is not set in stone. Indicating which month you intend to volunteer will assist staff in their planning of park projects and allow for the purchase of plants and other materials in anticipation of your projects.
Project Time Table. 2.2.1 The construction of the Project is scheduled to commence in year 2016 for completion in year 2020.
Project Time Table. Construction works for the designated features are to be carried out under Works Contract No. GE/2002/17. The Contract is scheduled for tendering in September 2002 and is likely commenced in December 2002 with a duration of 24 months. The main programme constraint to the overall completion of the project is the group of 7 features at Shek Pik Reservoir, which are roadside slopes within the Lantau South Country Xxxx and the works at these features run throughout the duration of the Contract. These 7 designated features have been divided into 5 sections. The anticipated duration of each feature at Shek Pik Reservoir is about 6 months. The remainder of the programme has been built around these 7 features, taking into other constraints such as traffic management for other projects, undertaking works at fill slopes during the dry season and other project or site specific constraints. It should be noted that the 2 remaining designated features, at Keung Shan Road, have been programmed to follow on from each other, to minimise the number of xxxx closures at any one time on this road, and to minimise the quantity of such items as safety fence, which have to be imported onto Lantau, by moving these from one feature to the next. The overall programme for Contract GE2002/17 is included in Attachment D. The approximate construction periods for the activities for an individual feature are typically as follows: (1) Minor earthworks including slope trimming and shotcrete removal 1 – 2 months (2) Installing soil nails and raking drains 1 – 2 months (3) Rock Slope Stabilisation Measures 1 – 2 months (4) Drainage improvement works 0.5 – 1 month (5) Landscaping Works 0.5 – 1 month
Project Time Table. This agreement covers all activities mentioned herein and is valid beginning on the date of signing and continuing for a period of 12 months from the date of system commissioning.
Project Time Table. 2.3.1 The asbestos abatement work is scheduled to begin in October 2001 for completion in early 2002 under Infrastructure Contract 1. Figure 2.1 shows the project timetable and its relationship with other concurrent works.

Related to Project Time Table

  • Project Timeline The Project Timeline establishes a start and end date for each Phase of the Project. Developed during the Initiate & Plan Stage and revised as mutually agreed to, if needed, the timeline accounts for resource availability, business goals, size and complexity of the Project, and task duration requirements.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Flexible Work Schedule A flexible work schedule is any schedule that is not a regular, alternate, 9/80, or 4/10 work schedule and where the employee is not scheduled to work more than 40 hours in the "workweek" as defined in Subsections F. and H., below.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Work Schedule (A) Where an employee has an established schedule, a change in workdays or shifts will be posted no less than 14 calendar days in advance and will reflect at least a two workweek schedule; however, the state will make a good faith effort to reflect a one month schedule. (B) In the event of a declared emergency the notice requirement of this Section may be void. (C) The state will continue to observe the scheduling structures currently in place at each agency and agrees to bargain any change in the overall practice of how schedules are established.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Milestone Schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.

  • Preliminary Design Phase 30 percent plans) A. Proceed with Preliminary Design Phase after the completion of the Conceptual phase which includes: Acceptance by Owner of the Conceptual Report and any other Study and Report Phase deliverables; selection by Owner of a recommended solution; issuance by Owner of any instructions for use of Project Strategies, Technologies, and Techniques, or for inclusion of sustainable features in the design, and Indication by Owner of any specific modifications or changes in the scope, extent, character, or design requirements of the Project desired by Owner. 1. Prepare Preliminary Design Phase documents consisting of final design criteria, preliminary drawings, outline specifications, and written descriptions of the Project. 2. Include on plans, property lines, structure locations, ownership names and contact information. 3. In preparing the Preliminary Design Phase documents, use any specific applicable Project Strategies, Technologies, and Techniques authorized by Owner during or following the Study and Conceptual Phase, and include sustainable features, as appropriate, pursuant to Owner’s instructions. 4. Provide necessary field surveys, topographic and utility mapping for Engineer’s design purposes. Comply with the scope of work and procedure for the identification and mapping of existing utilities as defined by Section A1.03 “Utility Requirements” and Section A1.04 “Survey Services” 5. Visit the Site as needed to prepare the Preliminary Design Phase documents. 6. Advise Owner if additional reports, data, information, or services of the types described are necessary and assist Owner in obtaining such reports, data, information, or services. 7. Continue to assist Owner with Project Strategies, Technologies, and Techniques that Owner has chosen to implement. 8. Based on the information contained in the Preliminary Design Phase documents, prepare a revised opinion of probable Construction Cost, and assist Owner in tabulating the various cost categories which comprise Total Project Costs. 9. Obtain and review Owner’s instructions regarding Owner’s procurement of construction services (including instructions regarding advertisements for bids, instructions to bidders, and requests for proposals, as applicable), Owner’s construction contract practices and requirements, insurance and bonding requirements, electronic transmittals during construction, and other information necessary for the finalization of Owner’s bidding-related documents (or requests for proposals or other construction procurement documents), and Construction Contract Documents. Also obtain and review copies of Owner’s design and construction standards, Owner’s standard forms, general conditions, supplementary conditions, text, and related documents or content for Engineer to include in the draft bidding-related documents (or requests for proposals or other construction procurement documents), and in the draft Construction Contract Documents, when applicable. 10. Development communication plan for project: considering the use of door hangers, letters, public meetings, changeable message boards. 11. Furnish 6 review copies of the Preliminary Design Phase documents, opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables to Owner by established due date, and review them with Owner. Owner shall submit to Engineer any comments regarding the furnished items. 12. Revise the Preliminary Design Phase documents, opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables in response to Owner’s comments, as appropriate, and furnish to Owner 6 copies of the revised Preliminary Design Phase documents, revised opinion of probable Construction Cost, and any other deliverables by the specified due date. 13. Engineer’s services under the Preliminary Design Phase will be considered complete on the date when Engineer has delivered to Owner the revised Preliminary Design Phase documents, revised opinion of probable Construction Cost, and any other Preliminary Design Phase deliverables.

  • Project Cost An updated cost spreadsheet reflecting the current forecasted cost vs. the latest approved budget vs. the baseline budget should be included in this section. One way to track project cost is to show: (1) Baseline Budget, (2) Latest Approved Budget, (3) Current Forecasted Cost Estimate, (4) Expenditures or Commitments to Date, and (5) Variance between Current Forecasted Cost and Latest Approved Budget. Line items should include all significant cost centers, such as prior costs, right-of-way, preliminary engineering, environmental mitigation, general engineering consultant, section design contracts, construction administration, utilities, construction packages, force accounts/task orders, wrap-up insurance, construction contingencies, management contingencies, and other contingencies. The line items can be broken-up in enough detail such that specific areas of cost change can be sufficiently tracked and future improvements made to the overall cost estimating methodology. A Program Total line should be included at the bottom of the spreadsheet. Narratives, tables, and/or graphs should accompany the updated cost spreadsheet, basically detailing the current cost status, reasons for cost deviations, impacts of cost overruns, and efforts to mitigate cost overruns. The following information should be provided:

  • Contract Times The number of days or the dates stated in the Agreement to: (i) achieve Substantial Completion; and (ii) complete the Work so that it is ready for final payment as evidenced by Architect's or Owner’s representative’s written recommendation of final payment.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!