Quarterly Progress Report Clause Samples

The Quarterly Progress Report clause requires a party, typically a contractor or service provider, to submit regular updates on the status of work or project milestones every three months. These reports usually include information such as completed tasks, encountered challenges, and projections for upcoming quarters, ensuring that all stakeholders are kept informed of progress. By mandating periodic reporting, this clause promotes transparency, enables early identification of issues, and helps ensure that the project stays on track.
POPULAR SAMPLE Copied 1 times
Quarterly Progress Report. This report shall cover each three-month period of the contract and shall be submitted within 30 days of the end of each three-month period. Each report shall show the progress of all program services in a form and manner prescribed by the County.
Quarterly Progress Report. The Concessionaire shall prepare and submit report in each quarter on the progress of construction (the “Quarterly Progress Report”) to the Concessioning Authority. The first report shall cover the period up to the end of the calendar month in which the Compliance Date occurred. Reports shall be submitted quarterly thereafter, each within 7 (seven) days of the last day of the period to which it relates. Reporting shall continue until the Concessionaire has completed all the Works, services, facilities and the Construction Completion Certificate is issued. Each report shall include:-
Quarterly Progress Report. Beginning at the end of the first Fiscal Year quarter after the Effective Date, and no later than 45 days after the end of each Fiscal Year quarter, each Party will prepare a Quarterly Progress Report and provide that report to the SOC and the other Party. The Parties will prepare the Quarterly Report using a template they jointly create and approve that will include information on progress toward established KPIs, a copy of the Annual Spending Plan, an updated list of Programs and Service Providers receiving Funding in the reported quarter, copies of Reconciliation Submittals exchanged in the reported quarter, and any material changes in programming or strategy from those set out in the Annual Program Plan. For reports created before the template is available, the information to be included in the reports will be as agreed to by the Parties.
Quarterly Progress Report. 1.30.1 During Implementation Phase, the Lessee shall, not later than 7 (seven) days from the close of each quarter, furnish to DOT and any other official or agency designated by DOT for the purpose of monitoring - a report on the progress of the Implementation Works and shall promptly give such other relevant information as may be required by DOT or any other official or agency designated by DOT for purpose of monitoring.
Quarterly Progress Report. The quarterly progress report shall track the Recipient’s progress towards goals and identify specific strategies in response to challenges. The Quarterly Report shall include:
Quarterly Progress Report. The Concessionaire shall prepare and submit report in each quarter on the progress of construction (the “Quarterly Progress Report”) to the Concessioning Authority. The first report shall cover the period up to the end of the calendar month in which the Compliance Date occurred. Reports shall be submitted quarterly thereafter, each within 7 (seven) days of the last day of the period to which it relates. Reporting shall continue until the Concessionaire has completed all the Works, services, facilities and the Construction Completion Certificate is issued. Each report shall include:- (i) An executive summary of activities completed and under progress; (ii) For the construction of each main item of the Project, the extent of progress as quantity and percent, the actual or expected dates of commencement, anticipated completion date of the activity; (iii) Furnishing and equipment of the Project Facility as ordered, as received, as installed, in the process of installation, testing and commissioning;
Quarterly Progress Report. CONTRACTOR shall submit Quarterlyquarterly Progress Reports 2 to ADMINISTRATOR. These reports shall be in a format provided by ADMINISTRATOR, and 3 document progress toward performanceoutcome objectives and performance measuresprocess 4 objectives, project successes, barriers to implementation, staff changes and reasons for staff changes, 5 and plans for the following quarter. 6 1. Period One reports: 7 a. Quarter 1: July 1, 20142016 through September 30, 20142016, due October 10, 8 201415, 2016; 9 b. Quarter 2: October 1, 20142016 through December 31, 20142016, due January 16, 10 201515, 2017; and 11 c. Quarter 3: January 1, 20152017 through March 31, 20152017, due April 17, 201515, 12 2017. 13 2. Period Two reports: 14 a. Quarter 1: July 1, 20152017 through September 30, 20152017, due October 16, 15 201515, 2017; 16 b. Quarter 2: October 1, 20152017 through December 31, 20152017, due January 22, 17 201615, 2017; and 18 c. Quarter 3: January 1, 20162018 through March 31, 20162018, due April 15, 20162018. 19 3. CONTRACTOR shall submit supporting documentation with each quarterly progress report 20 including, but not limited to, tracking measures, materials developed, and evaluation results.
Quarterly Progress Report. CONTRACTOR shall submit Quarterly Progress Reports to ADMINISTRATOR. These reports shall be in a format provided by ADMINISTRATOR and document progress toward Units of Service and Outcome Measures, project successes, barriers to implementation, staff changes and reasons for staff changes, and plans for the following quarter. CONTRACTOR shall submit supporting documentation with each Quarterly Progress Report including, but not limited to, tracking measures, materials developed, and Evaluation results. Quarterly Reports are due on the following dates: a. Period Four reports: Quarter 1: July 1, 2023 through September 30, 2023, due October 15, 2023; Quarter 2: October 1, 2023 through December 31, 2023, due January 15, 2024; and Quarter 3: January 1, 2024 through March 31, 2024, due April 15, 2024. b. Period Five reports: Quarter 1: July 1, 2024 through September 30, 2024, due October 15, 2024 Quarter 2: October 1, 2024 through December 31, 2024, due January 15, 2025; and Quarter 3: January 1, 2025 through March 31, 2025, due April 15, 2025.
Quarterly Progress Report. CONTRACTOR shall submit Quarterly Progress Reports to 18 ADMINISTRATOR. These reports shall be in a format provided by ADMINISTRATOR and document 19 progress toward Outcome Objectives and Process Objectives, project successes, barriers to 20 implementation, staff changes and reasons for staff changes, and plans for the following quarter.
Quarterly Progress Report. CONTRACTOR shall submit quarterly Progress Reports to