REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK Sample Clauses

REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. All work which has been rejected or condemned shall be repaired, or if it cannot be repaired satisfactorily, it shall be removed and replaced at the CONTRACTOR’S expense. Defective materials shall be immediately removed from the site of the work. Work done without line and grade having been given, work done beyond the lines or not in conformity with the grades shown on the plans or as given, save as herein provided, work done without written authority and prior agreement in writing as to process, shall be done at the CONTRACTOR’S risk and shall be considered unauthorized and at the option of the OWNER may be ordered removed at the CONTRACTOR’S expense. Upon failure of the CONTRACTOR to repair satisfactorily or to remove and replace, if so directed, rejected, unauthorized or condemned work or materials immediately after receiving notice form the OWNER, the OWNER shall, after giving written notice to the CONTRACTOR, have the authority to cause defective work to be remedied or removed and replaced, or to cause unauthorized work to be removed and to deduct the cost thereof from any monies due or to become due the CONTRACTOR. Alternatively, the OWNER may, at its option, declare the CONTRACTOR in default.
AutoNDA by SimpleDocs
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. The Contracting Agency will not pay for unauthorized or defective Work. Unauthorized or defective Work includes: Work and materials that do not conform to Contract requirements; Work done beyond the lines and grades set by the Plans or the Engineer; and extra Work and materials furnished without the Engineer’s written approval. At the Engineer’s order, the Contractor shall immediately remedy, remove, replace, or dispose of unauthorized or defective Work or materials and bear all costs of doing so.
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. (a) Rejected Work shall be removed and replaced by Contractor in an acceptable manner and no compensation will be allowed for such removal or replacement. Work done beyond the lines and grades shown on the plans or established by the City Representative, or Work done without written authority will be considered as unauthorized and not be paid for. Such Work may be ordered removed at Contractor’s expense.
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. A. All work which has been rejected or condemned shall be repaired, or if it cannot be repaired satisfactorily, it shall be removed and replaced at the CONTRACTOR’S expense. Defective materials shall be immediately removed from the site of the work. Work done without line and grade having been given, work done beyond the lines or not in conformity with the grades shown on the plans or as given, save as herein provided, work done without written authority and prior agreement in writing as to process, shall be done at the CONTRACTOR’S risk and shall be considered unauthorized and at the option of the OWNER may be ordered removed at the CONTRACTOR’S expense.
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. (October 1, 2005 APWA GSP) Supplement this section with the following: If the Contractor fails to remedy defective or unauthorized work within the time specified in a written notice from the Engineer, or fails to perform any part of the work required by the Contract Documents, the Engineer may correct and remedy such work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary. If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public. Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized work. No adjustment in contract time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Contracting Agency’s rights provided by this Section. The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the work as required.
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. (February 22, 2011 KC GSP) The following is added at the end of this section:
REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. All work, which has been rejected, shall be remedied, or removed and replaced by the Contractor in an acceptable manner and no compensation will be allowed for such removal or replacement. Any work done beyond the lines and grades shown on the plans or established by the Engineer, or any extra work done without written authority will be considered as unauthorized and will not be paid for. Work so done may be ordered removed at the Contractor's expense. Upon failure on the part of the Contractor to comply forthwith with any order of the Engineer made under the provisions of this article, the Engineer shall have authority to cause defective work to be removed, and to deduct the costs from any monies due or to become due the Contractor
AutoNDA by SimpleDocs

Related to REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK

  • RECTIFICATION OF DEFECTS 23.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.