Taylor Slough and The Coastal Basins Sample Clauses

Taylor Slough and The Coastal Basins. Under the Consent Decree, a single total phosphorus long-term limit of 11 ppb, to be met by December 31, 2006, was set for the two points of inflow to Taylor Slough (S332 and S175) and the inflow point to the Coastal Basins (S18C). The 11 ppb limit applies to the water year ending September 30. Beginning in August 1999, structure S332D, a new pump station constructed by the U.S. Army Corps of Engineers (USACE), began operation. The structure is adjacent to spillway S174 and pumps water from the L31N canal into the L31W canal. The S332D and S174 structures became the new inflow compliance monitoring sites for Taylor Slough on October 1, 1999, replacing S332 and S175. However, the Settlement Agreement's Technical Oversight Committee requested that data from both the old and new pairs of inflow structures to Xxxxxx Xxxxxx be presented for one year. This request was made to determine if the differences between the two data sets observed from August 1999 through March 2000 would continue throughout a complete wet season/dry season cycle and what implications this might have on future compliance with the 11 ppb limit. Total phosphorus and flow data from both sets of structures presented in prior editions of this report through December 2001 (April 2002 report) showed that, beginning October 2000, the 12-month moving total flow data for S332D/S174/S18C was consistently greater than flow at S332/S175/S18C. There was also a shift in flow-weighted mean total phosphorus concentration data whereby S332D/S174/S18C concentrations became equal to and then consistently lower than the concentrations at S332/S175/S18C. These changes reflected the switch made from S332 to S332D for water delivery to Taylor Slough between July 3 and July 5, 2000. Consequently, as of the July 2002 report, only S332D/S174/S18C data are presented, with the exception of data in Figure 5a. C-111 Project Structures and Detention Areas The USACE completed construction of the remaining C-111 structures and detention areas along the eastern boundary of the ENP in June 2002. The project was authorized by the USACE in 1995 to restore more natural hydrologic conditions in Taylor Slough and to maintain flood protection to the east of the L31N and C- 111 canals. Project facilities consist of pump stations S332B, S332C and S332D, Detention Cells 1 through 5, a Connector Cell between cells 2 and 3, a Flow Way Cell originating at Berm 3 of Cell 5, and four emergency overflow structures (Figure 5). The Flow Wa...
AutoNDA by SimpleDocs
Taylor Slough and The Coastal Basins. Under the Consent Decree, a single total phosphorus long-term limit of 11 ppb, to be met by December 31, 2006, was set for the two points of inflow to Taylor Slough (S332 and S175) and the inflow point to the Coastal Basins (S18C). The 11 ppb limit applies to the water year ending September 30. C-111 Project Structures and Detention Areas Beginning in August 1999, structure S332D, a new pump station constructed by the U.S. Army Corps of Engineers (USACE), began operation. The structure is adjacent to spillway S174 and pumps water from the L31N canal into the L31W canal. The S332D and S174 structures became the new inflow compliance monitoring sites for Taylor Slough on October 1, 1999, replacing S332 and S175. The USACE completed construction of the remaining C-111 project structures and detention areas along the eastern boundary of the ENP in June 2002. The project was authorized by the USACE in 1995 to restore more natural hydrologic conditions in Taylor Slough and to maintain flood protection to the east of the L31N and C-111 canals. Project facilities consist of pump stations S332B, S332C and S332D, Detention Cells 1 through 5, a Connector Cell between cells 2 and 3, a Flow Way Cell originating at Berm 3 of Cell 5, and four emergency overflow structures (Figure 5). The Flow Way Cell is the routine surface water discharge location to the ENP from this project. The construction of these facilities was accelerated to respond to U.S. Fish and Wildlife requirements to give immediate relief to water conditions that threaten the Cape Sable Seaside Sparrow, an endangered species. The USACE signed a Record of Decision on July 2, 2002 that authorizes the implementation of an Interim Operational Plan (IOP) to govern the operation of the new facilities. On July 31, 2002, the Florida Department of Environmental Protection (FDEP) issued Emergency Order #7 to allow the USACE to operate the new and existing facilities in accordance with the IOP. The USACE and the South Florida Water Management District (District) will monitor the implementation of the IOP under the terms and conditions of the C- 111 Project Cooperation Agreement executed in 1995. As local sponsor, the District will eventually operate and maintain the project facilities. The USACE has implemented a monitoring plan that was approved by FDEP that assesses the hydrologic, environmental, and surface and ground water quality changes that may occur as a result of the IOP. The monitoring plan treats the deten...
Taylor Slough and The Coastal Basins. Under the Consent Decree, a single total phosphorus (TP) long-term limit of 11 ppb, to be met by December 31, 2006, was set for the two points of inflow to Taylor Slough (S332 and S175) and the inflow point to the Coastal Basins (S18C). The 12-month flow-weighted mean concentrations have consistently been lower than the long-term limit of 11 ppb. C-111 Project Structures and Detention Areas Beginning in August 1999, structure S332D, a pump station constructed by the U.S. Army Corps of Engineers (USACE), began operation. The structure is adjacent to spillway S174 and pumps water from the L31N Canal into the L31W Canal. The S332D and S174 structures became the new inflow compliance monitoring sites for Taylor Slough on October 1, 1999, replacing S332 and S175. The USACE completed construction of the remaining C-111 project structures and detention areas along the eastern boundary of the ENP in June 2002. The project was authorized by the USACE in 1995 to restore more natural hydrologic conditions in Taylor Slough and to maintain flood protection to the east of the L31N and C-111 canals. Project facilities consist of pump stations S332B, S332C and S332D, detention cells, Cell 1 through Cell 5, a connector cell between Cell 2 and Cell 3, a flow way cell originating at Berm 3 of Cell 5, and four diversion structures, DS1 through DS4 (Figure 9). The flow way cell is the only location to routinely discharge surface water into the ENP from this project. The construction of these facilities was accelerated to respond to U.S. Fish and Wildlife requirements to give immediate relief to water conditions that threaten the Cape Sable Seaside Sparrow, an endangered species. The USACE signed a Record of Decision on July 2, 2002, that authorizes the implementation of an Interim Operational Plan (IOP) to govern the operation of the new facilities. Since July 31, 2002, the USACE has been operating the project under Emergency Orders issued by the Florida Department of Environmental Protection (FDEP). The USACE and the South Florida Water Management District (District) will monitor the implementation of the IOP under the terms and conditions of the C-111 Project Cooperation Agreement executed in 1995. The District, on behalf of the USACE, has implemented a monitoring plan approved by FDEP that assesses the hydrologic, environmental, and surface and ground water quality changes that may occur as a result of the IOP. The District started the routine sampling in September 2003. Th...

Related to Taylor Slough and The Coastal Basins

  • Indigenous Peoples 17. The Borrower shall, and shall cause MOT and ARS to, ensure that the Project does not cause any impact on indigenous people within the meaning of the SPS. In the event that the Project does have any such impact, the Borrower shall, and shall cause MOT and ARS to, take all steps required to ensure that the Project complies with the applicable laws and any other applicable regulations of the Borrower and the SPS.

  • Washtenaw Community College Eastern Michigan University Xxxxxx Xxxxxxxxxx College of Engineering & Technology Student Services BE 214 xxx_xxxxxxxx@xxxxx.xxx; 734.487.8659 734.973.3398

  • xxx/OpenGovernment/LobbingAtOrangeCounty aspx A lobbying blackout period shall commence upon issuance of the solicitation until the Board selects the Contractor. For procurements that do not require Board approval, the blackout period commences upon solicitation issuance and concludes upon contract award. The County may void any contract where the County Mayor, one or more County Commissioners, or a County staff person has been lobbied in violation of the black-out period restrictions of Ordinance No. 2002-15. • Orange County Protest Procedures xxxx://xxx.xxxxxxxxxxxxxx.xxx/VendorServices/XxxxxxXxxxxxxXxxxxxxxxx.xx px Failure to file a protest with the Manager, Procurement Division by 5:00 PM on the fifth full business day after posting, shall constitute a waiver of bid protest proceedings.

  • Entities that Boycott Energy Companies In accordance with Senate Bill 13, Acts 2021, 87th Leg., R.S., pursuant to Section 2274.002 (eff. Sept. 1, 2023, Section 2276.002, pursuant to House Bill 4595, Acts 2023, 88th Leg., R.S.) of the Texas Government Code (relating to prohibition on contracts with companies boycotting certain energy companies), Contractor represents and warrants that: (1) it does not, and will not for the duration of the Contract, boycott energy companies or (2) the verification required by Section 2274.002 (eff. Sept. 1, 2023, Section 2276.002, pursuant to House Bill 4595, Acts 2023, 88th Leg., R.S.) of the Texas Government Code does not apply to the Contract. If circumstances relevant to this provision change during the course of the Contract, Contractor shall promptly notify System Agency.

  • Tropical Hardwood and Virgin Redwood Ban Pursuant to San Francisco Environment Code Section 804(b), the City urges Contractor not to import, purchase, obtain, or use for any purpose, any tropical hardwood, tropical hardwood wood product, virgin redwood or virgin redwood wood product.

  • Role of the Central Parties and Crown a) The central parties shall each have the following rights:

Time is Money Join Law Insider Premium to draft better contracts faster.