Time Control. 30 Program 30.1 Within the time stated in the Special Conditions of Contract, the Contractor shall submit to the Project Manager for approval a Program showing the general methods, arrangements, order, and timing for all the activities in the Works. 30.2
Time Control. 14. 30.1 The Contractor shall Submit a Program for the Works within Seven (7) days of delivery of the Letter of Acceptance.
Time Control. GCC 26.1 The Contractor shall submit a revised Program including Environmental Management Plan for the Works (in such form and detail as the engineer shall reasonably prescribe) within 14 days of delivery of the Letter of Acceptance. GCC 26.3 The period between Program updates is 7 days. The amount to be withheld for late submission of an updated Program is Rs 500000/-.
Time Control. Programme 30.1 Within the time stated in the Contract Data Sheet, the Contractor shall submit to the Project Manager for approval a Programme showing the general methods, arrangements, order, and timing for all the activities in the Works. An update of the Program shall be a Program showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work, including any changes to the sequence of the activities. 30.3 The Contractor shall submit to the Project Manager for approval an updated Program at intervals no longer than the period stated in the Contract Data Sheet. If the Contractor does not submit an updated Program within this period, the Project Manager may withhold the amount stated in the Contract Data Sheet from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Program has been submitted. 30.4 The Project Manager’s approval of the Program shall not alter the Contractor’s obligations. The Contractor may revise the Program and submit it to the Project Manager again at any time. A revised Program shall show the effect of Variations and Compensation Events
Time Control. 27.1. Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a Programme showing the general methods, arrangements, order, timing for all the activates in the Works along with monthly cash flow forecast.
Time Control. 27. Programme
Time Control. 25.1 The Adjudicator should be in position before “notice to proceed with work” is issued to the contractor and an agreement should be signed with the Adjudicator jointly by Employer/Contractor in the form attached – Appendix 3
Time Control. 26.1 Within the time stated in the PCC, after the date of the Letter of Acceptance, the Contractor shall submit to the Project Manager for approval a revised Program (revising the program given along with the bid) including Environmental Management Plan showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecasts.
Time Control. GCC 34.1 The Contractor shall submit for approval a Program for the Works within [number] days from the date of the Letter of Acceptance. GCC 34.3 The period between Program updates is [insert number] days. The amount to be withheld for late submission of an updated Program is [insert amount].
Time Control. In order to be compliant with article 34 of the Spanish Worker’s Statute, the control of the working hours of the EMPLOYEE will be carried out through the following means: -Through an online timesheet.