Examples of Statement of Dispute in a sentence
Such Statement of Dispute shall include adequate supporting data to substantiate the disputed Claim.
Adequate supporting data to a Statement of Dispute submitted by the Program Manager involving the Program Manager’s compensation shall include a detailed cost breakdown and supporting cost data in such form and including such detailed information and other supporting data as required to demonstrate the grounds for, and precise amount of, the Claim.
Failure by the Program Manager to timely submit its Statement of Dispute shall result in the decision by the District on the Claim becoming final and binding.
Paragraphs 9.b and 18 from the 2007 Statement of Dispute Resolution in Appendix L: Paragraph 9.b states, “The Parties agree to the following process concerning waste removal.
Designated representatives of the District and the Architect shall meet as soon as possible (but not later than forty-five (45) calendar days after the Statement of Dispute is given) in a good faith effort to negotiate a resolution to the Claim.
The Program Manager’s Statement of Dispute shall state with specificity the events or circumstances giving rise to the Claim, the dates of their occurrence and the asserted effect, if any, on the compensation due or time of performance obligations of the Program Manager under this Agreement.
The Parties agree to include liquid waste milestones, which will supersede all current milestones in FFA Appendix L, except for paragraphs 9.b and 18 from the 2007 Statement of Dispute Resolution in Appendix L, incorporated into this Agreement.
Such Statement of Dispute shall include adequate supporting data.
Designated representatives of the District and the Program Manager shall meet as soon as possible (but not later than forty-five (45) Days after receipt of the Statement of Dispute) in a good faith effort to negotiate a resolution to the Claim.
The Program Manager’s Statement of Dispute shall be signed by a responsible managing officer and shall state with specificity the events or circumstances giving rise to the Claim, the dates of their occurrence and the asserted effect, if any, on the compensation due or time of performance obligations of the Program Manager under this Agreement.