Commencement of Commercial Production Sample Clauses

Commencement of Commercial Production. Commencement of Commercial Production shall occur upon the completion of all major construction and development work, including but not limited to, conversion of the pilot mill to a full-scale milling facility, receipt of all necessary production and operating permits from local, state and federal regulatory agencies and the beginning of reasonably satisfactory operation of mine and mill facilities in the course of substantial mining operations resulting in the production and sale of marketable concentrates, other than for metallurgical testing and trial marketing purposes, as evidenced by a resolution of the Company as manager and operator of the Ashdown Mine pursuant to the Ashdown Joint Venture Agreement.
AutoNDA by SimpleDocs
Commencement of Commercial Production. Within thirty (30) days after the Date of Commencement of Commercial Production, the Contractor shall notify the Secretary, Director and Regional Director of such commencement.
Commencement of Commercial Production. If a retention period applies, the exploitation phase shall commence once is made the declaration of Commercial Discovery.
Commencement of Commercial Production. Commercial Operations The Company will promptly notify the Exchange the commencement of commercial/production or the commencement of commercial operations of any unit/division where revenue from the unit/division for a full year of production or operations is estimated to be not less than ten per cent of the revenues of the Company for the year. (4) Developments with respect to pricing/realisation arising out of change in the regulatory framework. The Company will promptly inform the Exchange of the developments with respect to pricing of or in realisation on its goods or services (which are subject to price or distribution control/restriction by the Government or other statutory authorities, whether by way of quota, fixed rate of return, or otherwise) arising out of modification or change in Government’s or other authority’s policies provided the change can reasonable be expected to have a material impact on its present or future operations or its profitability. (5) Litigation/dispute with a material impact The Company will promptly after the event inform the Exchange of the developments with respect to any dispute in conciliation proceedings, litigation, assessment, adjudication or arbitration to which it is a party or the outcome of which can reasonably be expected to have a material impact on its present or future operations or its profitability or financials. (6) Revision in Ratings The Company will promptly notify the Exchange, the details of any rating or revision in rating assigned to any debt or equity instrument of the Company or to any fixed deposit programme or to any scheme or proposal of the Company involving mobilisation of funds whether in India or abroad provided the rating so Page 20 of 62 assigned has been quoted, referred to, reported, relied upon or otherwise used by or on behalf of the Company. (7) Any other information having bearing on the operation/performance of the company as well as price sensitive information, which includes but not restricted to; i) Issue of any class of securities.ii) Acquisition, merger, de-merger, amalgamation, restructuring, scheme of arrangement, spin off or selling divisions of the company, etc.
Commencement of Commercial Production 

Related to Commencement of Commercial Production

  • TIME OF COMMENCEMENT AND COMPLETION 2.1 The Contractor shall commence the Work upon the date established in the Notice to Proceed. 2.2 The Contractor shall achieve Final Completion, as defined in Section 105.01, Contract Time, Notice of Contract Execution and Notice to Proceed of the Loudoun County Revisions to the 0000 XXXX Xxxx & Bridge Specifications, Division I - General Provisions, within one hundred and eighty (180) calendar days from the date specified in the Notice to Proceed. This time period shall be designated the Contract Time. The Notice to proceed will be issued approximately than thirty (30) days after the execution of this agreement. The Contractor agrees that the time for completion of the Work as described in the Contract Documents shall govern unless specifically amended in writing by the County, and that no claims for early completion are allowed to be presented by the Contractor to the County. 2.3 The County specifies that time is of the essence under this Contract. Time being of the essence, it is essential to the County that Contract work will be completed within the Contract Time. The County and the Contractor agree that damages for failure to complete the work within the Contract Time are not susceptible to exact determination but that $600 per day is in proportion to the actual loss that the County would suffer from such delay. Therefore, the Contractor will pay the County on demand $600 per day for each and every day beyond the one hundred and eighty (180) calendar days, or modified date of completion, that the County determines that work is not complete, as damages caused by such delay and not as a penalty. The County shall be entitled to offset liquidated damages against any sum owed by the County to the Contractor under this Contract. 2.4 The amount of liquidated damages set forth in Articles 2.3 above shall be assessed cumulatively. This provision for liquidated damages does not bar County's right to enforce other rights and remedies against Contractor, which are otherwise legally enforceable, including but not limited to, specific performance or injunctive relief. 2.5 The Contractor hereby waives any defense as to the validity of any liquidated damages stated in this Agreement as they may appear on grounds that such liquidated damages are void as penalties or are not reasonably related to actual damages.

  • Pre-Commencement Phase Services The services required to be provided by the Contractor for the Pre- Commencement Phase of the Project in accordance with the Contract Documents.

  • Project Commencement The Grantee shall begin the grant-funded project <<on or before insert date>> <<within 90 days of the original start date of the grant term or grant execution date, whichever is later,>>, unless otherwise approved by System Agency. If project commencement is delayed, the Grantee must submit in writing to the assigned contract manager, the steps taken to initiate the project, the reasons for the delay, and the expected start date. System Agency may require Grantee to take immediate remedial or corrective action in response to any delay.

  • Service Commencement Date The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.

  • Construction Commencement The Connecting Transmission Owner shall commence construction of the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied: 5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; 5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades; 5.6.3 The Connecting Transmission Owner has received written authorization to proceed with construction from the Developer by the date specified in Appendix B hereto; and 5.6.4 The Developer has provided security to the Connecting Transmission Owner in accordance with Article 11.5 by the dates specified in Appendix B hereto.

  • Commencement and Completion The Work shall commence on _______________, 20__ and shall be complete in accordance with this Agreement without delay on ______________, 20__. The term “day”, used throughout this Agreement, refers to calendar days. Contractor shall not be entitled to any additional compensation for any Permitted Delays. If this Agreement is not signed and returned to the Owner before any work commences, this Agreement will be considered as accepted as presented to the Contractor.

  • Improvement Plan A detailed, written plan collaboratively developed between the teacher and evaluator, utilized when a teacher receives an Evaluation Rating of ineffective. The approved form for the Improvement Plan is attached to this agreement as Appendix .

  • Development Phase contractual phase initiated with the approval of ANP for the Development Plan and which is extended during the Production Phase while investments in xxxxx, equipment, and facilities for the Production of Oil and Gas according to the Best Practices of the Oil Industry are required.

  • Commencement of Development 5.3.1 In the event that development on the Lands has not commenced within five (5) years from the date of registration of this Agreement at the Registry of Deeds or Land Registry Office, as indicated herein, the Agreement shall have no further force or effect and henceforth the development of the Lands shall conform with the provisions of the Land Use By-law. For the purpose of this section, commencement of development shall mean issuance of a Mobile Home Park Construction Permit. 5.3.2 For the purpose of this section, Council may consider granting an extension of the commencement of development time period through a resolution under Section 4.1 of this Agreement, if the Municipality receives a written request from the Developer at least sixty (60) calendar days prior to the expiry of the commencement of development time period.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: § 3.2 The Contract Time shall be measured from the date of commencement of the Work.