CONCEALED OR UNKNOWN SITE CONDITIONS Sample Clauses

CONCEALED OR UNKNOWN SITE CONDITIONS. If the conditions at the site are (a) subsurface or other physical conditions which are materially different from those indicated in the Contract Documents, or (b) unusual or unknown physical conditions which are materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, then prompt notice shall be given to all affected parties before the conditions are disturbed, but in no event later than seven (7) days after discovery. If appropriate, an equitable adjustment to the Contract Price and Contract Time shall be made by Change Document. If agreement cannot be reached by the parties, the party seeking an adjustment in the Contract Price or Contract Time may assert a Claim in accordance with the Contract Documents.
AutoNDA by SimpleDocs
CONCEALED OR UNKNOWN SITE CONDITIONS. If the conditions at the site are (a) subsurface or other physical conditions which are materially different from those indicated in the Contract Documents, or (b) unusual or unknown physical conditions which are materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, then prompt notice shall be given to all affected parties before the conditions are disturbed, but in no event later than seven (7) days after discovery. If appropriate, an equitable adjustment to the Contract Price and Contract Time shall be made by Change Document. If agreement cannot be reached by the parties, the party seeking an adjustment in the Contract Price or AGC DOCUMENT NO. 200 STANDARD FORM OF AGREEMENT AND GENERAL CONDITIONS BETWEEN OWNER AND CONTRACTOR (Where the Contract Price is a Lump Sum) 1997, The Associated General Contractors of America Contract Time may assert a Claim in accordance with the Contract Documents.
CONCEALED OR UNKNOWN SITE CONDITIONS. If a condition encountered at the Worksite is (a) a subsurface or other physical condition materially different from those indicated in the Contract Documents, or (b) an unusual and unknown physical condition materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, Private Entity shall stop affected Work after the concealed or unknown condition is first observed and give prompt written notice of the condition to Owner. Owner shall investigate and then issue an Construction Change Directive specifying the extent to which Owner agrees that a concealed or unknown condition exists and directing how Private Entity is to proceed. Any change in the GMP, estimated Cost of the Work, Private Entity’s Fee, and the dates of Substantial and Final Completion as a result of the condition, including any dispute about its existence or nature, shall be determined as provided in this article. For purposes of this Section a condition is “unknown” if the Private Entity had no actual knowledge of the condition and reasonably would not have had such knowledge had it performed its duties under Section 2.6 with reasonable diligence.
CONCEALED OR UNKNOWN SITE CONDITIONS. If the conditions encountered at the Worksite are (a) subsurface or other physical conditions materially different from those indicated in the Contract Documents, or (b) unusual and unknown physical conditions materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, the Constructor shall stop affected Work after the condition is first observed and give prompt written notice of the condition to the Owner. The Constructor shall not be required to perform any Work relating to the unknown condition without the written mutual agreement of the Parties. Any change in the Contract Time as a result of the unknown condition shall be determined as provided in ARTICLE 8. Constructor shall be paid for its costs and Constructor’s Fee incurred as a result of any Worksite conditions.
CONCEALED OR UNKNOWN SITE CONDITIONS. If the conditions at the Worksite are (a) subsurface or other physical conditions which are materially different from those indicated in the Contract Documents or (b) unusual or unknown physical conditions which are materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, the Design-Builder shall stop Work and give immediate written notice of the condition to the Owner and the Design-Builder. The Design-Builder shall not be required to perform any work relating to the unknown condition without the written mutual agreement of the Parties. Any change in the Contract Price or the Contract Time as a result of the unknown condition shall be determined as provided in Article 8. The Design-Builder shall provide the Owner with written notice of any claim as a result of unknown conditions within the time period set forth in Paragraph 8.6. Provided, however, that the Design-Builder shall not be entitled to a change in the Contract Price or the Contract Time where the condition should have been discovered through reasonable due diligence and care in examining the Worksite or in performing the Work.
CONCEALED OR UNKNOWN SITE CONDITIONS. If a condition encountered at the Worksite is (a) a subsurface or other physical condition materially different from those indicated in the Contract Documents, or (b) an unusual and unknown physical condition materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, Design-Builder shall stop affected Work after the concealed or unknown condition is first observed and give prompt written notice of the condition to Owner. Owner shall investigate and then issue an Interim Directive specifying the extent to which Owner agrees that a concealed or unknown condition exists and directing how Design-Builder is to proceed. Design-Builder shall not be required to perform any Work relating to the unknown condition without the written mutual agreement of the Parties. Any change in the GMP, estimated Cost of the Work, Design-Builder’s Fee, and the dates of Substantial and Final Completion as a result of the condition, including any dispute about its existence or nature, shall be determined as provided in this article.
CONCEALED OR UNKNOWN SITE CONDITIONS. If a condition encountered at the Worksite is (a) a subsurface or other physical condition materially different from those indicated in the Contract Documents, or (b) an unusual and unknown physical condition materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, Construction Manager shall stop affected Work after the condition is first observed and give prompt written notice of the condition to Owner and Design Professional. Owner shall investigate and then issue an Interim Directive specifying the extent to which Owner agrees that a concealed or unknown condition exists and directing how Construction Manager is to proceed. Construction Manager shall not be required to perform any Work relating to the condition without the written mutual agreement of the Parties. Any change in the GMP, estimated Cost of the Work, Construction Manager's Fee, Date of Substantial Completion or Date of Final Completion, and, if appropriate, the Compensation for Preconstruction Services as a result of the condition, including any dispute about its existence or nature shall be determined as provided in ARTICLE 9.
AutoNDA by SimpleDocs
CONCEALED OR UNKNOWN SITE CONDITIONS. If the conditions encountered at the Worksite are (a) subsurface or other physical conditions materially different from those indicated in the Contract Documents, or (b) unusual and unknown physical conditions materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, the Construction Manager shall stop affected Work after the condition is first observed and give prompt written notice of the condition to the Owner and the Design Professional. The Construction Manager shall not be required to perform any Work relating to the unknown condition without the written mutual agreement of the Parties. Any change in the GMP, estimated Cost of the Work, Construction Managers Fee, Date of Substantial Completion or Date of Final Completion, as a result of the unknown condition shall be determined as provided in Article 10.
CONCEALED OR UNKNOWN SITE CONDITIONS. If a condition encountered at the Worksite are (a) subsurface or other physical conditions materially different from those indicated in the Contract Documents, or (b) unusual and unknown physical conditions materially different from conditions ordinarily encountered and generally recognized as inherent in Work provided for in the Contract Documents, Design-Builder shall stop affected Work after the concealed or unknown condition is first observed and give prompt written notice of the condition to Owner. Owner shall investigate and then issue an Interim Directive specifying the extent to which Owner agrees that a concealed or unknown condition exists and directing how Design-Builder is to proceed. Design-Builder shall not be required to perform any Work relating to the unknown condition without the written mutual agreement of the Parties. Any change in the Contract Price or Contract Time as a result of the condition, including any dispute about its existence or nature, shall be determined as provided in this ARTICLE 8.

Related to CONCEALED OR UNKNOWN SITE CONDITIONS

  • Concealed or Unknown Conditions If the Contractor encounters conditions at the site that are (1) subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, that differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, the Contractor shall promptly provide notice to the Owner and the Architect before conditions are disturbed and in no event later than twenty-one (21) calendar days after first observance of the conditions. The Owner will promptly investigate such conditions and, if the Owner determines that they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will authorize an equitable adjustment in the Contract Sum or Contract Time, or both. If the Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Owner shall promptly notify the Contractor in writing, stating the reasons. If the Contractor disputes the Owner’s determination, the Contractor party may assert a Claim as provided in Article 15.

  • Site Conditions A. Existing Site Conditions: Information with respect to the site of the Work given in drawings or specifications has been obtained by County's representatives and is believed to be reasonably correct, but the County does not warrant either the completeness or accuracy of such information, and it is the responsibility of the Contractor to verify all such information.

  • Hazardous Conditions Whenever the Contractor’s operations create a condition hazardous to traffic or to the public, the Contractor shall provide flagmen and furnish, erect and maintain control devices as are necessary to prevent accidents or damage or injury to the public at Contractor’s expense and without cost to the County. The Contractor shall comply with County directives regarding potential hazards. Emergency lights and traffic cones must also be readily available at all times and must be used in any hazardous condition. Emergency traffic cones must be placed in front of and behind vehicles to warn oncoming traffic. Signs, lights, flags, and other warning and safety devices shall conform to the requirements set forth in Chapter 5 of the current traffic manual, Traffic Control for Construction and Maintenance Work Zones, published by the state of California Department of Transportation. The Contractor shall take proper safety and health precautions to protect the Work, the workers, the public, and the property of others. The Contractor shall also be responsible for all materials delivered and Work performed until completion and acceptance of the entire construction Work, except for any completed unit of construction thereof which theretofore may have been accepted.

  • CONCEALED CONDITIONS 12.2.1 Should concealed conditions encountered in the performance of the Work below the surface of the ground, or should concealed or unknown conditions in an existing structure be at variance with the conditions indicated by the Contract Documents or should unknown physical conditions below the surface of the ground or should concealed or unknown conditions in an existing structure of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract, be encountered, the Contract Sum shall be equitably adjusted by Change Order upon claim by either

  • Differing Site Conditions (a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site(s), of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract. (b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. Work shall not proceed at the affected site, except at the Contractor’s risk, until the Contracting Officer has provided written instructions to the Contractor. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, the Contractor shall file a claim in writing to the PHA within ten days after receipt of such instructions and, in any event, before proceeding with the work. An equitable adjustment in the contract price, the delivery schedule, or both shall be made under this clause and the contract modified in writing accordingly. (c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer. (d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

  • Unsafe Conditions In accordance with 29 CFR § 1977, occasions might arise when an employee is confronted with a choice between not performing assigned tasks or subjecting himself/herself to serious injury or death arising from a hazardous condition at the workplace. If the employee, with no reasonable alternative, refuses in good faith to expose himself/herself to the dangerous condition, he/she would be protected against subsequent discrimination. The condition causing the employee's apprehension of death or injury must be of such a nature that a reasonable person, under the circumstances then confronting the employee, would conclude that there is a real danger of death or serious injury and that there is insufficient time, due to the urgency of the situation, to eliminate the danger by resorting to regular statutory enforcement channels. In addition, in such circumstances, the employee, where possible, must also have sought from his Employer, and been unable to obtain, a correction of the dangerous condition.

  • HAZARDOUS SUBSTANCE CONDITIONS If a Hazardous Substance Condition occurs, unless Lessee is legally responsible therefor (in which case Lessee shall make the investigation and remediation thereof required by Applicable Requirements and this Lease shall continue in full force and effect, but subject to Lessor's rights under Paragraph 6.2(c) and Paragraph 13), Lessor may at Lessor's option either (i) investigate and remediate such Hazardous Substance Condition, if required, as soon as reasonably possible at Lessor's expense, in which event this Lease shall continue in full force and effect, or (ii) if the estimated cost to investigate and remediate such condition exceeds twelve (12) times the then monthly Base Rent or $100,000 whichever is greater, give written notice to Lessee within thirty (30) days after receipt by Lessor of knowledge of the occurrence of such Hazardous Substance Condition of Lessor's desire to terminate this Lease as of the date sixty (60) days following the date of such notice. In the event Lessor elects to give such notice of Lessor's intention to terminate this Lease, Lessee shall have the right within ten (10) days after the receipt of such notice to give written notice to Lessor of Lessee's commitment to pay for the excess costs of (a) investigation and remediation of such Hazardous Substance Condition to the extent required by Applicable Requirements, over (b) an amount equal to twelve (12) times the then monthly Base Rent or $100,000, whichever is greater. Lessee shall provide Lessor with the funds required of Lessee or satisfactory assurance thereof within thirty (30) days following said commitment by Lessee. In such event this Lease shall continue in full force and effect, and Lessor shall proceed to make such investigation and remediation as soon as reasonably possible after the required funds are available. If Lessee does not give such notice and provide the required funds or assurance thereof within the time period specified above, this Lease shall terminate as of the date specified in Lessor's notice of termination.

  • Subsurface Conditions Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the Contractor shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

  • Safe Conditions Whenever an employee reports a condition which the employee feels represents a violation of safety or health rules and regulations or which is an unreasonable hazard to persons or property, such conditions shall be promptly investigated. The appropriate administrator shall reply to the concern, in writing, if the employee's concern is communicated in writing.

  • SUSPENSIVE CONDITIONS 2.1 This entire AGREEMENT is subject to the registration of transfer of ownership of the PROPERTY to the EMPLOYER. In the event that the PROPERTY is not transferred within 6 (six) months from date of signing of this Agreement by the CONTRACTOR, the CONTRACTOR reserves the right to: 2.1.1 increase the CONTRACT SUM, based on the current prices for the building materials, and the CONTRACTOR shall notify the EMPLOYER in writing of such increased cost and the EMPLOYER may then, at his/her option, cancel this agreement by providing written notice of cancellation to the CONTRACTOR within 5 (five) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost. Should written notice of cancellation not be forthcoming within the aforesaid period, the CONTRACTOR and the EMPLOYER shall proceed with the AGREEMENT at the increased CONTRACT SUM and the EMPLOYER shall be obliged to pay the increase in the CONTRACT SUM to the CONTRACTOR within 21 (twenty one) DAYS of receiving written notice from the CONTRACTOR in respect of the increased cost; or 2.1.2 cancel this AGREEMENT and the parties shall have no claim of whatsoever nature against each other. 2.2 This AGREEMENT is subject further to the EMPLOYER being offered a loan to be secured by a mortgage bond over the PROPERTY and improvements in the amount reflected in Schedule B or such lesser amount as the EMPLOYER may accept, within 30 (thirty) DAYS of the date of the CONTRACTOR’s signature of this AGREEMENT, which period may be extended in the CONTRACTOR’s sole discretion. Should no amount be inserted in the relevant field in the Schedule B, then the suspensive condition contained in this clause will not apply. In the event that the suspensive condition contained in this clause is not fulfilled, this AGREEMENT will lapse and the parties shall have no claim of whatsoever nature against each other.