Construction Progress Update Sample Clauses
The Construction Progress Update clause requires the contractor or responsible party to provide regular reports on the status of construction activities. Typically, this involves submitting written updates at specified intervals, detailing completed work, current progress, and any delays or issues encountered. By mandating these updates, the clause ensures that all stakeholders remain informed about the project's timeline and can address potential problems proactively, thereby promoting transparency and effective project management.
POPULAR SAMPLE Copied 4 times
Construction Progress Update. Each monthly and biweekly update shall reflect actual conditions of Project progress as of the date of the update. The update shall reflect the actual progress of construction, identify developing delays, regardless of their cause, and reflect the Construction Manager's best projection of the actual date by which Substantial Completion and Final Completion of the Project will be achieved. Via a narrative statement (not merely a critical path method schedule), the Construction Manager shall identify the causes of any potential delay and state what, in the Construction Manager's judgment, must be done to avoid or reduce that delay. The Construction Manager shall point out, in its narrative, changes that have occurred since the last update, including those related to major changes in the scope of work, activities modified since the last update, revised projections of durations, progress and completion, revisions to the schedule logic or assumptions, and other relevant changes. Any significant variance from the previous schedule or update shall also be identified in a narrative, together with the reasons for the variance and its impact on Project completion. All schedule reports and updates shall be in a native Primavera 6 format or the latest version thereof and reasonably acceptable to the Department. The Department may make reasonable requests during the Project for changes to the format or for further
Construction Progress Update. Each monthly update shall contain a narrative description of the Project progress and a critical path method schedule in Primavera format, including any plans to correct defective or deficient work or for time lost due to delays.
Construction Progress Update. The Design-Builder shall provide written reports to the Department, on the progress of the entire Work at least monthly from Preconstruction NTP until Final Completion of the Project. The monthly report shall include: (i) an updated schedule analysis, including any plans to correct defective or deficient work or recover delays; (ii) an updated cost report; (iii) a monthly review of cash flow; (iv) a quality control report; and (v) progress photos. Each monthly update shall contain a narrative description of the Project progress and a critical path method schedule in Primavera format, including any plans to correct defective or deficient work or for time lost due to delays.