Cost Loading Sample Clauses

Cost Loading. The cost estimate/budget to perform the Individual Activity of work. The total cost loading of all Individual Activities shall equal the Total Base Bid/Contract Price.
AutoNDA by SimpleDocs
Cost Loading. The Proposed Target Schedule and the Target Schedule must be provided in hard copy and editable electronic format.
Cost Loading. The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by Architect.
Cost Loading. The Commission reserves the right to require a resource-loaded schedule within the timeframe designated by the Commission. The Proposed Target Schedule and the Target Schedule must be provided in hard copy and editable electronic format.
Cost Loading. The allocation of the schedule of values for the completion of an activity as scheduled. The sum of costs for all activities must not exceed that portion of the GMP attributable to Construction Phase Compensation, unless otherwise approved by Architect and Owner.
Cost Loading. The Project Schedules shall be cost loaded. Cost loading of the CPM schedule shall be effected by representing the Payment Milestones in the schedule. Each of the Payment Milestones shall be logically tied to the activities which must be completed as a pre-requisite to the Payment Milestone being considered complete. Each Payment Milestone will be cost loaded with the approved corresponding Payment Milestone amount. The Payment Milestone cost will be further broken down into components using the cost code to reflect the appropriate Authority provided WBS codes. Change Orders will be represented in the schedule with new activities and the associated cost of the Change Order with new Payment Milestones if applicable.
Cost Loading. The Design-Builder shall cost load each activity in the Baseline Schedule for which the Design-Builder expects to receive payment. The Baseline Schedule shall be reasonably cost loaded to allow for an accurate determination of progress of the activity based on earnings. The Baseline Schedule shall be cost loaded in accordance with the following: .1 If the “Resource” feature is used to cost-load the Baseline Schedule, the Design- Builder shall define and assign a project-specific resource to applicable activities. The Resource ID shall be unique and prefixed by the Contract number. (e.g. C00012345DB10.00100$).
AutoNDA by SimpleDocs
Cost Loading. Contractor shall allocate the total Contract Amount to lowest level of the activities scheduled in the Baseline Schedule such that each activity has a value which accurately shows the amount payable to Contractor for such activity. The overhead and indirect costs shall be distributed to all the activities and added to each activity as a percentage. The identified percentage for overhead and other indirect costs shall be the same for all activities within each bid classification and shall not be changed without the authority prior written approval, which may be withheld at the authority sole discretion. For Work, which is the subject of a Change Order, the schedule shall show the identified percentages set forth in the approved Change Order. The sum of the prices of all activities in the Baseline Schedule shall be equal the total Contract Amount. Once the Baseline Schedule has been approved, no changes to any allocated amount will be initiated without the Authority’s approval.

Related to Cost Loading

  • TOOL STORAGE 1. A company shall provide on all construction jobs in towns and cities, and elsewhere where reasonably necessary and practicable (or if requested buy the employee), a suitable and secure waterproof lock-up solely for the purpose of storing employees’ tools, and on multi-storey and major projects the company shall provide, where possible, a suitable lock-up for employees’ tools within a reasonable distance of the work area of large groups of employees.