Cost Responsibility and Billing. PGE shall charge for, and the Applicant will be responsible for, the timely payment of the cost of any application fee and the costs of such facilities, equipment, modifications, upgrades and additional review, as may be allowed by the Rules.
Cost Responsibility and Billing. The Applicant is responsible for the application fee and for such facilities, equipment, modifications, and upgrades identified under the process prescribed in the Commission’s rules, ARSD chapter 20:10:36.
Cost Responsibility and Billing a. PUD shall charge for, and the Customer will be responsible for, the timely payment of the cost of any application fee and the costs of such facilities, equipment, modifications, upgrades and additional review, as may be necessary.
Cost Responsibility and Billing. The Applicant is responsible for the application fee and for such facilities, equipment, modifications, and upgrades.
Cost Responsibility and Billing. As provided in the CSP Interconnection Procedures, the Applicant is responsible for the cost of all facilities, equipment, modifications and upgrades needed to facilitate the interconnection of the Community Solar Project to the Public Utility’s Distribution System.
Cost Responsibility and Billing. The Interconnection Customer is responsible for the cost of all facilities, equipment, modifications and upgrades needed to facilitate the interconnection of the Community Solar Project to the Public Utility’s T&D System..
Cost Responsibility and Billing. 4.1 Application Fee Customer-Generator shall bear the cost of any Application fee provided for in the Rule and Pacific Power’s Oregon Electric Service Schedule 135 or its successor tariff(s). Customer-Generator shall remit payment with the Application as calculated in Appendix C, the Application, Section 2.C.
Cost Responsibility and Billing. BLEC shall charge for, and the Applicant will be responsible for, the timely payment of the cost of any application fee and the costs of such facilities, equipment, modifications, upgrades, and additional review, as may be allowed by the Rules.
Cost Responsibility and Billing. The Interconnection Customer is responsible for the cost of all facilities, equipment, modifications and upgrades needed to facilitate the interconnection of the Small Generator Facility to the Public Utility’s T&D System..
Cost Responsibility and Billing