NOTICE OF POTENTIAL DELAY Sample Clauses

NOTICE OF POTENTIAL DELAY. Contractor shall strictly comply with the delivery requirements of this Contract. Whenever the Contractor has knowledge of any actual or potential delay or threatened delay in the timely performance of this Contract, the Contractor shall immediately give notice thereof, confirmed in writing, including all relevant information with respect thereto, to Sandia. NI14-ORDER OF PRECEDENCE & LANGUAGE Any inconsistencies shall be resolved in accordance with the following descending order of precedence: (1) Section I; (2) SF 6432-NI, Section II. The English language version of this Contract shall be controlling. All deliverables under this Contract shall use and/or be in the English language. NI15 - PAYMENT Contractor agrees to provide invoices within 60 days of completion of work and hereby waives any amounts that are not invoiced within 60 days of the completion of work on the contract. Unless otherwise provided, terms of payment shall be net 30 days from the latter of (1) receipt of Contractor's proper invoice, if required, or (2) delivery of Items/completion of work. Invoices or vouchers requesting payment for item(s) of Government Property as defined in DEAR 970.5204-21 Property, shall be separately listed on such invoices or vouchers. Any offered discount shall be taken if payment is made within the discount period that the Contractor indicates. Payments may be made either by check or electronic funds transfer, at the option of Sandia. Payment shall be deemed to have been made as of the date of mailing or the date on which an electronic funds transfer was made.
AutoNDA by SimpleDocs
NOTICE OF POTENTIAL DELAY. Contractor shall strictly comply with the delivery requirements of this contract. Whenever the Contractor has knowledge of any actual or potential delay or threatened delay in the timely performance of this contract, the Contractor shall immediately give notice thereof, confirmed in writing, including all relevant information with respect thereto, to the SCR. CR16 - ORDER OF PRECEDENCE Any inconsistencies shall be resolved in accordance with the following descending order of precedence: (1) Section I; (2) SF 6432-CR, Section II, (3) other incorporated documents. 6 CR17 - PAYMENT (a) Payments on Account of Allowable Costs
NOTICE OF POTENTIAL DELAY. Program Manager shall submit written notice to Owner’s Project Manager advising of the risk of any potential delay, stating in detail any and all actions reasonably required of Owner to appropriately mitigate or avoid the risk of delay, within seven (7) days after Program Manager knew or, in the exercise of reasonable diligence, should have known of the potential delay. The foregoing notwithstanding, Program Manager shall not be entitled to an equitable adjustment to the Program Master Schedule if the potential delay actually results in a delay unless the resulting delay would not have occurred but for Owner’s failure to take reasonable and appropriate action as described in such notice to prevent such resulting delay.
NOTICE OF POTENTIAL DELAY. Contractor shall strictly comply with the delivery requirements of this Contract. Whenever the Contractor has knowledge of any actual or potential delay or threatened delay in the timely performance of this Contract, the Contractor shall immediately give notice thereof, confirmed in writing, including all relevant information with respect thereto, to Sandia. NI13-ORDER OF PRECEDENCE & LANGUAGE Any inconsistencies shall be resolved in accordance with the following descending order of precedence: (1) Section I; (2) SF 6432-NI, Section II. The English language version of this Contract shall be controlling. All deliverables under this Contract shall use and/or be in the English language.
NOTICE OF POTENTIAL DELAY. Whenever CONTRACTOR has knowledge of any actual or potential delay or threatened delay in the timely performance of this Contract, the CONTRACTOR shall immediately give notice thereof, confirmed in writing, including all relevant information with respect thereto, to SMS. The CONTRACTOR agrees to insert the substance of this provision, including this sentence, in any Subcontract hereunder, except that each such Subcontract shall require the Subcontractor to notify his next higher tier Contractor of all relevant information with respect to such delays. Such notice is for informational purposes only and shall not be construed to relieve the CONTRACTOR of CONTRACTOR’S obligation to comply with the Contract delivery requirements.
NOTICE OF POTENTIAL DELAY. Contractor shall strictly comply with the delivery requirements of this Contract. Whenever the Contractor has knowledge of any actual or potential delay or threatened delay in the timely performance of this Contract, the Contractor shall immediately give notice thereof, confirmed in writing, including all relevant information with respect thereto, to Sandia. LA13-ORDER OF PRECEDENCE & LANGUAGE Any inconsistencies shall be resolved in accordance with the following descending order of precedence: (1) Section I; (2) SF 6432-LA, Section II. The English language version of this Contract shall be controlling. All deliverables under this Contract shall use and/or be in the English language. LA14 - PAYMENT Contractor agrees to provide invoices within 60 days of completion of work and hereby waives any amounts that are not invoiced within 60 days of the completion of work on the contract. Unless otherwise provided, terms of payment shall be net 30 days from the latter of (1) receipt of Contractor's proper invoice, if required, or (2) delivery of Items/completion of work. Invoices or vouchers requesting payment for item(s) of Government Property as defined in DEAR 970.5204-21 Property, shall be separately listed on such invoices or vouchers. Any offered discount shall be taken if payment is made within the discount period that the Contractor indicates. Payments may be made either by check or electronic funds transfer, at the option of Sandia. Payment shall be deemed to have been made as of the date of mailing or the date on which an electronic funds transfer was made. LA15 - SUBCONTRACTS If Seller subcontracts under this Contract, Seller shall incorporate into the subcontract all of the requirements set forth in this Contract to any and all such subcontractors. LA16 - PRICING OF CONTRACT AND SUBCONTRACT MODIFICATIONS The cost principles and procedures set forth in FAR Part 31 as modified by DEAR Part 931 shall be used to price contract and subcontract modifications, if any, whenever cost analysis is performed to negotiate the price of any such modification LA17 -PROPERTY This clause is applicable if this contract provides (i) that Sandia will furnish Government- owned property to the Contractor (hereinafter referred to as "Sandia-Furnished U.S. Government Property") or (ii) that the Contractor will acquire property.

Related to NOTICE OF POTENTIAL DELAY

  • Notice of Potential Claims The Contractor shall not be entitled to additional compensation or to extension of time for (1) any act or failure to act by the County Project Manager or the County, or (2) the happening of any event or occurrence, unless the Contractor has given the County a written Notice of Potential Claim within ten (10) days of the commencement of the act, failure, or event giving rise to the claim, and before final payment by the County. The written Notice of Potential Claim shall set forth the reasons for which the Contractor believes additional compensation or extension of time is due, the nature of the cost involved, and insofar as possible, the amount of the potential claim. Contractor shall keep full and complete daily records of the work performed, labor and material used, and all costs and additional time claimed to be additional.

  • NOTICE OF DELAYS Except as otherwise provided under this Contract, when either party has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this Contract, that party shall, within one (1) business day, give notice thereof, including all relevant information with respect thereto, to the other party.

  • Notice of Testing The Contractor shall give the ODR and the A/E timely notice of its readiness and the date arranged so the ODR and A/E may observe such inspection, testing or approval.

  • Notice of Lay-off All regular employees shall be given in writing the following notice of lay-off or salary in lieu of notice:

  • Notice of Delay 12.1. When anything delays or threatens to delay the timely performance of the Purchase Order, Supplier must immediately provide written notice to Buyer in writing of all relevant information, including but not limited to the reasons for the potential delay and Supplier’s short-term and long-term mitigation actions.

  • SUSPENSION & TERMINATION FOR DEFAULT Enterprise Services may suspend Contractor’s operations under this Master Contract immediately by written cure notice of any default. Suspension shall continue until the default is remedied to Enterprise Services’ reasonable satisfaction; Provided, however, that, if after thirty (30) days from such a suspension notice, Contractor remains in default, Enterprise Services may terminate Contractor’s rights under this Master Contract. All of Contractor’s obligations to Enterprise Services and Purchasers survive termination of Contractor’s rights under this Master Contract, until such obligations have been fulfilled.

  • Notice of Layoffs The County shall give reasonable notice to the Association before effecting any layoffs which materially affect employees represented under this Memorandum of Understanding. Upon receiving such notice, the Association may meet and confer regarding the effect of the layoff.

  • Termination Notice for Force Majeure Event If a Force Majeure Event subsists for a period of 180 (one hundred and eighty) days or more within a continuous period of 365 (three hundred and sixty five) days, either Party may in its discretion terminate this Agreement by issuing a Termination Notice to the other Party without being liable in any manner whatsoever, save as provided in this Article 34, and upon issue of such Termination Notice, this Agreement shall, notwithstanding anything to the contrary contained herein, stand terminated forthwith; provided that before issuing such Termination Notice, the Party intending to issue the Termination Notice shall inform the other Party of such intention and grant 15 (fifteen) days time to make a representation, and may after the expiry of such 15 (fifteen) days period, whether or not it is in receipt of such representation, in its sole discretion issue the Termination Notice.

  • NOTICE OF LABOR DISPUTES (a) If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this Contract, the Contractor immediately shall give notice, including all relevant information, to the Authority.

  • Notice of Layoff The Employer shall make every reasonable effort under the circumstances to provide affected employees with at least fourteen (14) calendar days’ notice prior to the contemplated effective date of a layoff.