PROVISION FOR INSPECTION Sample Clauses

PROVISION FOR INSPECTION. The Subcontractor shall notify the Contractor when portions of the Subcontractor's Work are ready for inspection. The Subcontractor shall at all times furnish the Contractor and its representatives adequate facilities for inspecting materials at the site or any place where materials under this Agreement may be in the course of preparation. process. manufacture or treatment. The Subcontractor shall furnish to the Contractor. in such detail and as often as required. full reports of the progress of the Subcontractor's work irrespective of the location of such work.
AutoNDA by SimpleDocs
PROVISION FOR INSPECTION. The Contractor shall notify the CZS when portions of the Contractor’s Work are ready for inspection. The Contractor shall at all times furnish the CZS and its representatives adequate facilities for inspecting materials at the site or any place where materials under this Agreement may be in the course of preparation, process, manufacture, storage or treatment. The Contractor shall furnish to the CZS in such detail, and as often as required, full reports of the progress of the Contractor’s Work.
PROVISION FOR INSPECTION. Subcontractor shall furnish to Prime Contractor and Owner and their representatives ample facilities at all times for inspecting materials at the site of construction, at the shops, or any place where materials under the Subcontract may be in the course of preparation, process, manufacture or treatment. Subcontractor shall further furnish to Prime Contractor, as often as required by Prime Contractor, full reports of the progress of the work at any place where materials under the Subcontract may be in the course of preparation or manufacture, said reports to show the progress of such preparation and manufacture in such details as may be required by Prime Contractor, including any plans, drawings, or diagrams in the course of preparation. Prime Contractor and/or Owner may have a full or part time quality control individual or inspector on the site or may conduct inspections of all or any part of the work at various times. Any such person or inspection shall not relieve or diminish in any way Subcontractor’s responsibility for ensuring that its portion of the work is in full and complete compliance with the Contract Documents and approved by Prime Contractor and Owner. Subcontractor cannot defend against poor, improper, substandard, incorrect, or non-complying work or materials by arguing that said work or materials were inspected and/or approved by Owner, Architect, or Prime Contractor.
PROVISION FOR INSPECTION. The Subcontractor shall notify Maintco Corp. when portions of the Subcontractor's Work are ready for inspection. The Subcontractor shall at all times furnish Maintco Corp. the Client, and their representatives adequate means and facilities for inspecting the Work, including materials at the site or any place where materials under this Agreement may be in the course of preparation, process, manufacture or treatment.
PROVISION FOR INSPECTION. SUBCONTRACTOR shall furnish to CONTRACTOR and its representatives ample facilities at all times for inspecting materials at the site of construction, at the shops, or any place where materials under this Agreement may be in course of preparation, process, manufacture or treatment. SUBCONTRACTOR shall further furnish to CONTRACTOR as often as required, full reports of the progress of the work at any place where materials under this Agreement may be in the course of preparation or manufacture; the reports shall show the progress of such preparation and manufacture in such details as may be required by CONTRACTOR, including any plans, drawings or diagrams made in course of preparation. The making or failure to make any inspection of or payment for or acceptance of the materials shall not impair CONTRACTOR’S right to later reject non-conforming materials, or to avail itself of any other remedy which CONTRACTOR may be entitled, notwithstanding CONTRACTOR’S knowledge of the nonconformity, its substantiality, or the ease of its discovery. SUBCONTRACTOR shall be liable for all inspection, reshipment and return costs on non-conforming materials. SUBCONTRACTOR shall not replace returned materials unless so directed by CONTRACTOR in writing. CONTRACTOR shall retain all rights granted herein notwithstanding the provisions of Paragraph N of this Agreement.

Related to PROVISION FOR INSPECTION

  • DOCUMENTS FOR INSPECTION sufficient copies of all documents required to be available for inspection as provided in the Base Prospectus or Drawdown Prospectus (as the case may be) or, in relation to any Notes, the Conditions; and

  • Registers Open for Inspection The registers referred to in Section 2.8(1) shall be open at all reasonable times during business hours on a Business Day for inspection by the Company or any Warrantholder. The Warrant Agent shall, from time to time when requested to do so in writing by the Company, furnish the Company with a list of the names and addresses of holders of Warrants entered in the register of holders kept by the Warrant Agent and showing the number of Warrants held by each such holder.

  • COPIES OF DOCUMENTS AVAILABLE FOR INSPECTION Each Paying Agent shall hold available for inspection at its specified office during normal business hours copies of all documents required to be so available by the Conditions of any Notes. For these purposes, the Issuer shall provide the Paying Agents with sufficient copies of each of the relevant documents.

  • DOCUMENTS AVAILABLE FOR INSPECTION Each of the Paying Agents and the Registrar shall make available for inspection during normal business hours at its Specified Office such documents as may be specified as so available at the specified office of such agent in the Base Prospectus or Drawdown Prospectus (as the case may be) or, in relation to any Notes, the Conditions, or as may be required by any listing authority, stock exchange and/or quotation system by which any Notes may from time to time be admitted to listing, trading and/or quotation.

  • Request for Information (RFI) means a written request by Contractor directed to A/E or ODR for a clarification of the information provided in the Contract Documents or for direction concerning information necessary to perform the Work that may be omitted from the Contract Documents.

  • Inspection and Testing Each Constructing Entity shall cause inspection and testing of the Interconnection Facilities that it constructs in accordance with the provisions of this section. The Construction Parties acknowledge and agree that inspection and testing of facilities may be undertaken as facilities are completed and need not await completion of all of the facilities that a Constructing Entity is building.

  • Office of Inspector General Investigative Findings Expert Review In accordance with Senate Bill 799, Acts 2021, 87th Leg., R.S., if Texas Government Code, Section 531.102(m-1)(2) is applicable to this Contract, Contractor affirms that it possesses the necessary occupational licenses and experience.

  • Requests for Information (RFI) In the event the Contract Documents are not complete, definite, and clear, the Contractor shall request the Design Professional in writing for additional instructions and shall furnish the Owner a copy of the RFI. With reasonable promptness but not more than five days thereafter, the Design Professional shall furnish complete, definite, and clear instructions in writing, or by means of drawings, or both. In the event such additional instructions are given orally for expediency, they shall be confirmed in writing or by drawings or both within five days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. The Work shall be executed in conformity with the aforesaid instructions. The Design Professional shall furnish the Owner a copy of all additional instructions issued to the Contractor. If, because of events beyond its reasonable control, the Design Professional is not able to meet the specified time period, then it is entitled to ask for additional time from the Owner.

  • Requests for Information The Grantee shall fully and promptly comply with all reporting requirements and requests for information issued by the Department or its authorized designee. The Grantee shall provide such information in the format requested by the Department. The Grantee shall ensure that its staff, interns, volunteers, and subcontractors comply in a timely and complete manner with all the Department’s requests for information. The Grantee shall comply in a timely manner with requests by the Department or its authorized designee for financial information, records, and documents related to evaluating costs of programs and ser vices provided by the Grantee’s probation department. The Grantee shall timely submit any files or records of the Grantee’s juvenile probation department, or any facility or program operated by or under the authority of the Grantee, requested by the Department or its authorized designee as a part of the monitoring, auditing, or investigatory process.

  • Inspection and Tests 3.8.1 The Procuring entity or its representative shall have the right to inspect and/or to test the goods to confirm their conformity to the Contract specifications. The Procuring entity shall notify the tenderer in writing in a timely manner, of the identity of any representatives retained for these purposes. 3.8.2 The inspections and tests may be conducted in the premises of the tenderer or its subcontractor(s), at point of delivery, and/or at the Goods’ final destination If conducted on the premises of the tenderer or its subcontractor(s), all reasonable facilities and assistance, including access to drawings and production data, shall be furnished to the inspectors at no charge to the Procuring entity. 3.8.3 Should any inspected or tested goods fail to conform to the Specifications, the Procuring entity may reject the equipment, and the tenderer shall either replace the rejected equipment or make alterations necessary to make specification requirements free of costs to the Procuring entity. 3.8.4 The Procuring entity’s right to inspect, test and where necessary, reject the goods after the Goods’ arrival shall in no way be limited or waived by reason of the equipment having previously been inspected, tested and passed by the Procuring entity or its representative prior to the equipment delivery. 3.8.5 Nothing in paragraph 3.8 shall in any way release the tenderer from any warranty or other obligations under this Contract.