Requests for Information (RFI) Sample Clauses

Requests for Information (RFI). In the event the Contract Documents are not complete, definite, and clear, the Contractor shall request the Design Professional in writing for additional instructions and shall furnish the Owner a copy of the RFI. With reasonable promptness but not more than five days thereafter, the Design Professional shall furnish complete, definite, and clear instructions in writing, or by means of drawings, or both. In the event such additional instructions are given orally for expediency, they shall be confirmed in writing or by drawings or both within five days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. The Work shall be executed in conformity with the aforesaid instructions. The Design Professional shall furnish the Owner a copy of all additional instructions issued to the Contractor. If, because of events beyond its reasonable control, the Design Professional is not able to meet the specified time period, then it is entitled to ask for additional time from the Owner.
AutoNDA by SimpleDocs
Requests for Information (RFI). The Design Professional shall review and respond to RFI's with reasonable promptness but nor more than five business days from receipt of any RFI. The Design Professional shall prepare any responses to reasonable requests from the Contractor for additional information about the Contact Documents. The Design Professional shall prescribe the format for such requests and shall instruct and assist the Contractor in adhering to this format.
Requests for Information (RFI). 2.211 The Design Professional will review and respond with reasonable promptness normally five (5) business days from receipt to properly prepare any reasonable requests from the CM/GC for additional information about the Contact Documents. The Design Professional shall prescribe the format for such requests and shall instruct and assist the CM/GC in adhering to this format. (See, however, Article 2.2.8
Requests for Information (RFI). The Design Builder will review and respond with reasonable promptness but not more than five (5) business days from receipt to properly prepare any reasonable requests from the Design-Builder for additional information about the Contact Documents.
Requests for Information (RFI). In the event the Construction Documents are not complete, definite, and clear to skilled tradesmen in the construction professions, or appear to have conflicting information, the CM/GC shall request the Design Professional in writing for additional instructions and shall furnish the Owner or Program Manager a copy of the RFI. With reasonable promptness but not more than five days thereafter, the Design Professional shall furnish complete, definite, and clear instructions in writing, or by means of drawings, or both. In the event such additional instructions are given orally for expediency, they shall be confirmed in writing or by drawings or both within five days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. The Work shall be executed in conformity with the aforesaid instructions. The Design Professional shall furnish the Owner a copy of all additional instructions issued to the CM/GC. If, because of events beyond its reasonable control, the Design Professional is not able to meet the specified time period, then it is entitled to ask for additional time from the Owner. Effect of Addenda, Bulletins, and Change Orders. No special implication, interpretation, construction, connotation, denotation, import, or meaning shall be assigned to any provision of the Contract Documents because of changes created by the issuance of any (1) Addendum, (2) Bulletin, or (3) Change Order other than the precise meaning that the Contract Documents would have had if the provision thus created had read originally as it reads subsequent to the (1) Addendum,
Requests for Information (RFI). In the event the Construction Documents are not complete, definite, and clear to skilled tradesmen in the construction professions, or appear to have conflicting information, the CMR shall request the Design Professional in writing for additional instructions and shall furnish the Board or Program Manager a copy of the RFI. With reasonable promptness but not more than five days thereafter, the Design Professional shall furnish complete, definite, and clear instructions in writing, or by means of drawings, or both. In the event such additional instructions are given orally for expediency, they shall be confirmed in writing or by drawings or both within five days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. The Work shall be executed in conformity with the aforesaid instructions. The Design Professional shall furnish the Board a copy of all additional instructions issued to the CMR. If, because of events beyond its reasonable control, the Design Professional is not able to meet the specified time period, then it is entitled to ask for additional time from the Board.
Requests for Information (RFI). In the event the Construction Documents are not complete, definite, and clear to CM/GC, or appear to have conflicting information, CM/GC shall issue in writing an RFI to Design Professional with a copy to Owner. Design Professional shall furnish complete, definite, and clear instructions in response to the RFI in writing, or by issuing drawings, or both. In the event instructions are given orally for expediency, they shall be confirmed in writing or by drawings within five (5) days following the oral instructions. Any such additional instructions shall be consistent with the Contract Documents and reasonably inferable therefrom. CM/GC shall maintain a log of RFIs and the responses received from Design Professional.
AutoNDA by SimpleDocs
Requests for Information (RFI). If included in the scope of services, XXXXXXX will provide, with reasonable promptness, written responses to requests from any contractor for clarification, interpretation or information on the requirements of the Contract Documents. If Contractor’s RFI’s are, in XXXXXXX’x professional opinion, for information readily apparent from reasonable observation of field conditions or review of the Contract Documents, or are reasonably inferable therefrom, XXXXXXX shall be entitled to compensation for Additional Services for XXXXXXX’x time in responding to such requests. CLIENT may wish to make the Contractor responsible to the CLIENT for all such charges for additional services as described in this article.
Requests for Information (RFI). 6.1 The CM will be responsible for developing and implementing an RFI form for use on the project utilizing Primavera Contract Manager software. 6.2 The CM will be responsible for logging and reviewing all RFIs prior to submission to the OWNER and the Project Designer. The CM is to insure that the RFIs submitted are appropriate and not frivolous. 6.3 The CM shall be responsible for tracking and monitoring all RFIs throughout the Construction Phase in a timely manner until they are processed by the Project Designer and/or the OWNER. 6.4 The CM shall include RFIs as an agenda topic at all OWNER meetings and advise the OWNER immediately of any delays in their process. All responses to the RFIs that have an added cost impact shall also be discussed with the OWNER.
Requests for Information (RFI). (a) Contractor shall submit a written request, sequentially numbered, to HFC, Architect or Consultant seeking verification that Contractor’s proposed solution to the issue or matter that is the subject of the RFI is an acceptable solution. Upon receipt, HFC, Architect or Consultant may either accept Contractor’s proposed solution or propose an alternative solution. HFC shall be entitled to deduct from the Contract Amount amounts paid to Architect or Consultant for Architect or Consultant to evaluate and respond to Contractor’s RFI’s, where such information was available to Contractor from a careful study and comparison of the Contract Documents, field conditions, other HFC provided information, Contractor prepared coordination drawings, and/or prior Project correspondence or documentation.