Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plant. Such analysis shall be performed by IID at its sole expense. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] II, Transmission Service and in any subsequent Plant Amendments.
7.2 Unless otherwise agreed to by Producer's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries for Producer or Producer's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] II, Transmission Service and in any subsequent Plant Amendments.
7.3 If either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination.
7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Transmission Losses. 8 8 CHARGES..........................................................................
Transmission Losses. 2.83% or as revised in accordance with Section 7.
Transmission Losses. Whenever the Office of the Interconnection has in place appropriate computer hardware, software, and other necessary resources to account for marginal losses in the dispatch of energy and the calculation of Locational Marginal Prices, loss accounting shall be determined on that basis, and the provisions of this Section shall be revised accordingly. Until such time, the following accounting provisions for losses shall apply.
Transmission Losses. (i) Responsibility for Transmission Losses Transmission Customer shall be responsible for Transmission Losses over the Maritime Link for deliveries of Energy pursuant to Point-to-Point Transmission Service reservations under this Agreement.
(ii) Transmission Loss Factors The applicable Transmission Loss Factor for the Maritime Link shall be established in accordance with Schedule 1.
(iii) Testing and Adjustments Transmission Provider shall test the Maritime Link on a monthly basis to confirm the Transmission Loss Factor based on the most recent 12 month average Transmission Loss Factor. Following each test, the Transmission Loss Factor shall be adjusted to the tested level and applied during the following month. There shall be no retroactive adjustments.
Transmission Losses. (a) Whenever the Office of the Interconnection has in place appropriate computer hardware, software, and other necessary resources to account for marginal losses in the dispatch of energy and the calculation of Locational Marginal Prices, loss accounting shall be determined on that basis, and the provisions of this Section shall be revised accordingly. Until such time, the following accounting provisions for losses shall apply.
(b) Each Internal Market Buyer that is a Load Serving Entity or purchasing on behalf of a Load Serving Entity shall be credited in an amount equal to its pro rata share of the hourly total amounts collected from Transmission Customers either as charges for transmission losses in the PJM Control Area as specified in Section 3.4.2 or for transmission losses supplied in kind in accordance with Section 3.4.2(c) based on the Locational Marginal Price at the interface where such losses were delivered. This credit shall be determined by the ratio of the Internal Market Buyer's total hourly load, divided by the total hourly load in the PJM Control Area.
(c) PJM Control Area 500 kV losses shall be allocated to each Electric Distributor that reports hourly net energy flows from metered tie lines in proportion to its hourly load in the PJM Control Area.
Transmission Losses. (a) Whenever the Office of the Interconnection has in place appropriate computer hardware, software, and other necessary resources to account for marginal losses in the dispatch of energy and the calculation of Locational Marginal Prices, loss accounting shall be determined on that basis, and the provisions of this Section shall be revised accordingly. Until such time, the following accounting provisions for losses shall apply.
(b) Transmission Customers other than entities that are also Internal Market Buyers shall be charged for transmission losses in an amount equal to the product of (i) the Transmission Customer's megawatt-hours of deliveries using Point-to-Point Transmission Service, times (ii) the appropriate loss factor for deliveries using Point-to-Point Transmission Service, times (iii) the weighted average Locational Marginal Price for all load busses in the PJM Control Area. The foregoing average hourly loss factor shall be: (i) determined by the Office of the Interconnection from time to time as conditions affecting losses shall warrant; and (ii) calculated separately for on-peak and off-peak hours on the basis of the average ratio of losses to load served in each such period.
(c) A Transmission Customer may elect to pay for losses in kind, rounded off to the nearest whole megawatt, rather than as specified above if its total deliveries in an hour using Point-to-Point Transmission Service are greater than 200 megawatts. If it so elects, the Transmission Customer's specified source for the energy to be delivered using Point-to-Point Transmission Service may be scheduled to supply to the PJM Control Area boundary an amount of energy equal to the delivery schedule plus the amount of losses determined by applying the appropriate hourly loss factor as specified above to the delivered amount.
Transmission Losses. Tucson shall supply and be responsible for transmission losses to the Delivery Points. Tucson shall supply Capacity Losses and Energy Losses to compensate for transmission losses from the Delivery Points to the Metering Points as specifically required by arrangements between NTUA and third-party transmission owners. B. WHOLESALE MARKET PURCHASES - NEW INDUSTRIAL LOAD NTUA shall have the right to seek alternate suppliers for New Industrial Load.
Transmission Losses. 4.13.1 Transmission losses from the Interconnection Point onwards would be borne by the Procurer(s), and power lost on account of transmission loss would be to the account of the Procurer(s).