Customization Milestones Chart definition
Examples of Customization Milestones Chart in a sentence
Included on the Customization Milestones Chart shall be the date by which the contractual definition of the Aircraft must be finalized and all relevant SCNs executed (the “Contractual Definition Freeze” or “CDF”), in order to assure delivery of the Aircraft in the Scheduled Delivery Month.
Within a reasonable period, [*] following signature of the Agreement, the Seller shall provide the Buyer with a Customization Milestones Chart.
Within *** following signature of the Agreement, the Seller shall provide the Buyer with a Customization Milestones Chart setting the minimum lead times prior to the Scheduled Delivery Month of the Aircraft, when an SCN must be executed in order to integrate into the Specification any items requested by the Buyer from the catalogues of Specification change options made available by the Seller (the “Customization Milestone Chart”).
Within two months following signature of the Agreement, the Seller will provide the Buyer with a Customization Milestones Chart setting out how far in advance of the Scheduled Delivery Month of the Aircraft an SCN must be executed in order to integrate into the Specification any items requested by the Buyer from the Specification Changes Catalogues made available by the Seller (the “Customization Milestone Chart”).
The Customization Milestones Chart shall in particular define the date(s) by which the contractual definition of the Aircraft must be finalized and all SCNs need to have been executed by the Buyer (the “Contractual Definition Freeze” or “CDF”) in order to enable their incorporation into the manufacturing of the Aircraft and Delivery of the Aircraft in the Scheduled Delivery Month.
Attached in Appendix 1 to this Clause 2 is a Customization Milestones Chart reflecting, in terms of minimum lead times prior to the delivery of the Aircraft, the dates when a mutual agreement must be reached (execution of a SCN) to integrate the Buyer’s specific features into the industrial process.
Within a reasonable period following signature of the Agreement, the Seller will provide the Buyer with a Customization Milestones Chart setting out how far in advance of the Scheduled Delivery Month of the Aircraft an SCN must be executed in order to integrate into the Specification any items requested by the Buyer from the Specification Changes Catalogues made available by the Seller (the "Customization Milestone Chart").
Buyer Furnished Equipment (BFE) - as defined in Clause 18.1.1 Certificate of Acceptance - as defined in Clause 8.3. Commitment Fee - the commitment fee amount described in Clause 5.3. Contractual Definition Freeze or CDF – as defined in 2.4.2 Customization Milestones Chart – as defined in 2.4.1 CT1706024 – Amended and Restated A350-900 Purchase Agreement – execution version AIRBUS S.A.S. & UNITED AIRLINES, INC.
Within a reasonable period after signature of this Agreement, the Seller will provide the Buyers with a chart called the "Customization Milestones Chart," defining the lead times before Delivery needed for agreeing on items requested by the Buyers from the Standard Specifications and Configuration Guides CD-ROM.
At a suitable time prior to CDF, to be defined in each Aircraft Customization Milestones Chart,, the Seller will organize a Technical Coordination Meeting (“TCM”) between the Buyer, the Seller and ACS Suppliers for Major ACS in order to reach the final detailed definition of the cabin.