As-Built Records. The Contractor shall prepare, and keep up-to-date, a complete set of as built records of the execution of the Works, showing the exact as built locations, sizes and details on the Works as executed with cross references to all relevant specifications and data sheets. These records shall be kept on the Site and shall be used exclusively for the purpose of this Sub-Clause 10.
As-Built Records. At the end of the project, the Contractor will submit to the City a certified as built site survey showing coordinates and elevations of the completed work.
As-Built Records. Maintain/develop at the project site one set of full-size contract drawings and specifications marked to show any deviations which have been made from the Contract Task Order drawings or specifications including buried or concealed structures and utility features revealed during the course of site work. Record the horizontal and vertical location of buried utilities that differ from the contract drawings. The drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, deliver the marked set of prints to the Contracting Officer or designated representative.
As-Built Records. The Project QC Manager is required to review the as-built records to ensure that as-built records are kept current on a daily basis and marked to show deviations that have been made from the contract drawings. The Project QC Manager shall initial each deviation or revision. Upon completion of work, the Project QC Manger shall submit a certificate attesting to the accuracy of the as-build records prior to submission to the Contracting Officer or COR.
As-Built Records. A. The Contractor shall keep at the site of work an accurately marked record set of drawings and specifications as the job progresses, with all changes or deviations from the original Contract Documents recorded thereon for work under the Contract. Ensure entries are complete and accurate, enabling future reference by Owner.
B. Accurate measurements referenced to two “permanent” structures shall be recorded to show exact location and changes in direction of all underground services and utilities, as well as the approximate depth below finished grade. In addition, the drawings and specifications shall be marked to record all materials used where options, alternates and/or change orders were indicated, specified, or authorized.
C. The specification section shall be legibly marked and recorded at each product section, the description of actual products installed, including the following:
1. Manufacturer’s name and product model number.
2. Product substitutions or alternates utilized.
3. Changes made by addenda and modifications.
D. The record drawings and shop drawings shall be legibly marked to record actual construction, including the following:
1. Measured depths of foundation grade beams in relation to the finish floor elevations/datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to permanent surface improvements.
4. Field changes of dimension and detail.
5. Details not in original Contract Drawings.
E. Record information concurrent with construction progress and store record documents separate from documents used for construction. The record set shall be kept up to date at all times and shall be reviewed by the Owner and the Owner’s Representative at each pay request meeting. Failure to have the record set up to date shall, at the discretion of the Owner’s Representative, be reason to withhold payment in accordance with “PAYMENT AND COMPLETION” until such information is recorded.
F. The Owner will provide a CAD file, mylar or reproducible plan set for the Contractor to transfer as- built information on to.
G. Upon completion of the project and prior to final payment, the Contractor shall forward the record set of drawings (CAD file or reproducible mylars and three sets of prints) and three sets specifications showing the as-built notations to the Owner’s Representati...
As-Built Records. Company, without expense to Township, shall, upon 48 hours' notice, give Township access to all "as-built" maps, records, plans and specifications showing the Small Wireless Facilities or portions thereof in the ROW.
As-Built Records. Contractor shall maintain a current and accurate record of the work completed during the course of this contract. This may be in the form of “as-built” drawings kept by accurately marking a designated set of the contract plans with the specified information as the Work proceeds.
1. Record location of underground services and utilities as installed.
2. Record location of existing underground utilities and services that are to remain and that are encountered during the course of the work.
3. Record changes in dimension, location, grade, or detail to that shown on the plans.
4. Record changes made by change order.
5. Record details not in the original plans.
6. Provide fully completed shop drawings reflecting all revisions.
As-Built Records. Maintain/develop at the project site one set of full-size contract drawings and specifications marked to show any deviations which have been made from the CTO drawings or specifications, including buried or concealed structures and utility features revealed during the course of site work. Record the horizontal and vertical location of buried utilities that differ from the contract drawings. The drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, the Contractor will deliver the marked set of prints to the Contracting Officer or COR.
As-Built Records. The Architect shall prepare a set of reproducible record drawings showing changes in the Work made during construction of the Project. The record drawings shall be based on the Architect’s observations and records kept during the Project. In addition, the Architect shall use marked-up prints, drawings and other data furnished by the CM and its contractors to prepare the record drawings. The Owner shall require the CM to maintain a set of record drawings during the course of the Project, and deliver those record drawings to the Architect at the conclusion of the Project. Unless the Owner later agrees to some other format, the record drawings provided by the Architect shall consist of an electronic file in AutoCAD or other approved compatible software, and one full size set of reproducible three mil mylars, all fully and neatly coordinated and accurately annotated and cross-referenced to show all of the changes in the Work and to reference and reflect the marked-up drawings and records provided by the CM. The mylars shall be of such quality that clear and legible prints may be made without appreciable or objectionable loss of detail.
As-Built Records. The Contractor shall prepare, and keep up-to-date, a complete set of as built recordsof the execution of the Works, showing the exact as built locations, sizes and detailsontheWorksasexecutedwithcrossreferencestoallrelevantspecificationsanddat asheets. These records shall be kept on the Site and shall be used exclusively for thepurpose of this Sub-Clause 10.8. The Contractor shall provide 2 (two) copies of asbuiltrecordstotheAuthoritypriortothecommencementoftheTestson Completion.