Concurrent Projects Sample Clauses

Concurrent Projects. 4.1 The southern landfall reclamation of the TM-CLKL forms an integrated part of the HKBCF reclamation, and interfaces with the latter along its eastern edge. Reclamation works sequencing and programme have been planned to match those of the HKBCF in order to achieve an assumed Phase 1 commissioning date target in 2015. The HKLR is also scheduled to open in 2015 in matching the Phase 1 commissioning date of the HKBCF. This construction programme comprising the use of non-dredge methods for reclamation together with more extensive preloading surcharge would result in less water quality impacts, and can still meet the vital programming target for HKBCF. It should be noted that an alternative construction programme, adopting a series of temporary seawalls (including one at the project interface) and full-dredging around local programme critical areas, will enable Phase 1 to be completed by 2014. This 2014 programme will provide margin to enable the project to gain back delays. With respect to potential environmental impacts, these two programmes would have different levels of construction phase water quality impacts, and both have been modelled and assessed. Detailed coordination of the interfacing construction activities will be required, including construction access, layout of mitigation measures to control water quality during the construction stage, joint water quality monitoring system, and engineering and construction details at the interface.
AutoNDA by SimpleDocs
Concurrent Projects. Construction Phase 1-11
Concurrent Projects. CHFS has concurrent projects that will deliver solutions expected to integrate with the solutions developed within this project. In addition, the projects will require the sharing of limited resources, including CHFS staff. The selected Vendor for this project shall be required to collaborate and cooperate with other Vendors and CHFS, as needed, in order to develop and maintain a consolidated multi-project Work Plan. As Vendors may have varying start dates, the Work Plan shall be a living document and the selected Vendor shall be flexible and work with other Vendors and CHFS, as needed, to modify, update and maintain the consolidated Work Plan. The Integrated Project Work Plan and all updates shall be submitted to CHFS for review and comment prior to approval or acceptance.
Concurrent Projects. 2.4.1 During the period of construction for the rock cavern development, the concurrent projects with construction works in the vicinity (500m from the site of cavern construction) will include the followings: Project Item Works Components Time Line 2 Flood attenuation facilities (drainage retention tank and artificial lake, etc.) within Quarry Park area Early 2018 – end 2020 5 Road improvement works at junction of Clear Water Bay Road and On Sau Road End 2016 - mid 2020
Concurrent Projects. There are a few concurrent projects that could have significant water quality impact in the vicinity of the Project area. They are listed and further discussed below.
Concurrent Projects. The same producer may present several projects to the CPFC.
Concurrent Projects 
AutoNDA by SimpleDocs

Related to Concurrent Projects

  • Sub-projects 1. The Participating Bank shall make Sub-loans to Beneficiaries and appraise, review, approve, and supervise Sub-projects in accordance with the criteria, conditions and procedures set forth in the Operations Manual, including, inter alia, the following eligibility criteria:

  • Concurrent Delay When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, Contractor may not be entitled to a time extension for the period of concurrent delay.

  • Project Completion Part 1 – Material Completion

  • Special Projects 2:01 The parties hereto express their intent to consider amending certain provisions of this Collective Agreement, by way of an appendix, where this action appears necessary and appropriate for certain projects. The provisions must be mutually agreed upon by the parties hereto.

  • Drawings and Specifications at the Project Site The Contractor shall keep at the Site at least one copy of the Contract Documents and Change Orders, all in good order and available to the Design Professional and to his representatives.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Overall Project Schedule The Construction Progress Schedule that is approved by the Owner.

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

Time is Money Join Law Insider Premium to draft better contracts faster.