CONSTRUCTION SCHEDULE/ PROGRESS CHART Sample Clauses

CONSTRUCTION SCHEDULE/ PROGRESS CHART a. Within ten (10) working days after receiving Notice to Proceed for each phase, the Private Entity shall prepare and submit to the Owner’s Representative a complete detailed design and construction schedule in the form of a electronic file and two (2) copies of a practical progress chart. The schedule shall show the principal categories of work, corresponding with those used in the breakdown on which progress payments are based, the order in which the Private Entity proposes to carry on the Work, the date on which it will start each category of Work, and the contemplated dates for completion. The design and construction schedule must be in suitable scale to indicate graphically the total percentage of Work scheduled to be in place at any time. The Private Entity shall use a Critical Path Method (CPM) format. This schedule shall use Primavera Scheduling software (Primavera Contractor P6), with at least 100 activities including sitework, procurement, delivery, significant owner activities, and installation of construction materials and equipment. Activities shall be organized by work areas, and work breakdown structure, and shall be fully cost loaded such that the sum of all activities equals the total GMP and shall be used as the feeder report for the Schedule of Values for the purpose of determining progress payment. No activity shall have a value exceeding $40,000 dollars, or a duration longer than ten (10) working days, without prior approval of the Owner’s Representative. A critical path shall be developed based on scheduling logic that identifies all successor and predecessor activities and float. Activities of like duration, programmed for different times of the year shall be modified to account for weather that can reasonably be expected by the Private Entity as indicated in Exhibit L. Activity constraints shall be avoided. Such software and schedule shall be compatible with the Owner Representative’s computer system and scheduling software. This will allow the Owner’s Representative to efficiently process each pay application in Expedition, using the AIA G702/G703 format where the G703 back up listing will be the Schedule of Values in CSI division format as explained in Section 16.3, so that the Owner will only be paying for work actually completed by the Private Entity. At the end of each progress payment period, or at such reasonable intervals as directed by the Owner’s Representative, the Private Entity shall:
AutoNDA by SimpleDocs
CONSTRUCTION SCHEDULE/ PROGRESS CHART a. Within five (5) calendar days after receiving Notice to Proceed, the Operator shall prepare and submit to the Owner’s Representative a complete detailed Project Schedule in the form of a electronic file and six (6) copies of a practical progress chart. The schedule shall show the principal categories of work, corresponding with those used in the breakdown on which progress payments are based, the order in which the Operator proposes to carry on the work, the date on which it will start each category of work, and the contemplated dates for completion. The Project Schedule must be in suitable scale to indicate graphically the total percentage of work scheduled to be in place at any time. The Operator shall use a Critical Path Method (CPM) format. This schedule shall be in Primavera™ P3 or SureTrak™ format, or in such format as the Owner and Operator mutually agree, with at least 200 activities including sitework, procurement, delivery, and installation of construction materials and equipment. Activities shall be organized by work areas, and shall be cost loaded to facilitate approval of progress payments. A critical path shall be developed based on scheduling logic that identifies all successor and predecessor activities and float. Activity constraints shall be avoided. At the end of each progress payment period, or at such reasonable intervals as directed by the Owner’s Representative, the Operator shall:
CONSTRUCTION SCHEDULE/ PROGRESS CHART a. Within ten (10) working days after receiving Notice to Proceed for each phase, the Private Entity shall prepare and submit to the Owner’s Representative a complete detailed design and construction schedule in the form of a electronic file and six (6) copies of a practical progress chart. The schedule shall show the principal categories of work, corresponding with those used in the breakdown on which progress payments are based, the order in which the Private Entity proposes to carry on the Work, the date on which it will start each category of Work, and the contemplated dates for completion. The design and construction schedule must be in suitable scale to indicate graphically the total percentage of Work scheduled to be in place at any time. The Private Entity shall use a Critical Path Method (CPM) format. This schedule shall use Primavera Scheduling software (Primavera Contractor, P3 or P6), with at least 100 activities including sitework, procurement, delivery, significant owner activities, and installation of construction materials and equipment. Activities shall be organized by work areas, and work breakdown structure, and shall be fully cost loaded such that the sum of all activities equals the total GMP and shall be used as the feeder report for the Schedule of Values for the purpose of determining progress payment. No activity shall have a value exceeding $40,000 dollars, or a duration longer than ten
CONSTRUCTION SCHEDULE/ PROGRESS CHART a. Within fourteen (14) working days after receiving Notice to Proceed for each phase, the DB shall prepare and submit to the Owner’s Representative a complete detailed design and construction schedule in the form of an electronic file. Unless otherwise required by the Contract Documents; the schedule shall contain details appropriate for the Project, including (1) the date of commencement of the Work, interim schedule milestone dates, and the date of Substantial Completion; (2) an apportionment of the Work by construction activity; and (3) the time required for completion of each portion of the Work. The schedule shall provide for the orderly progression of the Work to the Substantial Completion date and final completion date indicated in the Contract Documents. The schedule shall be revised at appropriate intervals as required by the conditions of the Work and Project. Such software and schedule shall be compatible with the Owner Representative’s computer system and scheduling software. This will allow the Owner’s Representative to efficiently process each pay application in Expedition, using the AIA G702/G703 format where the G703 back up listing will be the Schedule of Values in CSI division format as explained in Paragraph 16.3, so that the Owner will only be paying for work actually completed by the DB.

Related to CONSTRUCTION SCHEDULE/ PROGRESS CHART

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Construction Schedules 10.1 Within seven (7) days of the University’s issuance of a purchase order, the Contractor shall submit to the Project Coordinator three (3) copies of a Construction Schedule for this Project. The Schedule shall be in bar chart form and shall include all aspects of the work, the interrelationship of the various trades and the critical path of the job. The schedule shall include a timeline for the submission, review and approval of shop drawings for critical path items and delivery and installation dates for those same critical path, or long lead time items, (such as electrical transformers and elevator). The Schedule shall coincide with the Contractor’s approved Schedule of Values. The Schedule shall indicate a completion date in advance of the date established for Substantial Completion. The Schedule shall be acceptable to the Architect/Engineer and the Project Coordinator. It shall be revised and reissued at the beginning of every month for the duration of the project. This monthly update progress Schedule shall include a summary comparison of the original schedule and the latest updated schedule (previous month) showing all activity description and dates. These comparison schedules shall be in the form of a summary bar chart, an activity listing report and actual to target comparisons. The reports may include critical activities, float time, duration of each activity, dates of each activity and the network logic (including successors and predecessors of each activity). Included with the written report and electronic copy of the schedule submission noting the above referenced requirements. Failure to provide the Architect/Engineer, or the Project Coordinator with an acceptable, revised Schedule, within seven (7) days of the receipt of a written request, may result in the withholding of the Contractor’s monthly progress payments until such a Schedule is received.

  • Implementation Schedule TIME IS OF THE ESSENCE with regard to all dates and time periods set forth and/or incorporated herein. Any material modification or deviation from an approved schedule described in this Agreement shall occur only upon approval of the City and RDA, with any such approvals required to be in writing as an amendment to this Agreement, and which approvals shall not be unreasonably withheld. City shall cooperate and act promptly with respect to any and all permits or approvals necessary for completion of the Project. Notwithstanding the above, this Agreement shall not limit the discretion of the City, or any of its duly appointed and authorized governing bodies, boards or entities, in approving or rejecting any aspect of the Project or improvements contemplated on or about the Property.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Evaluation Schedule CLIENT REFERENCES The Tenderer shall provide details of his performance on each of the previous projects listed in the “Relevant Experience” returnable schedule. “Client Reference Scorecards” will be completed by each of the respective Clients for the projects listed in the “Relevant Experience” returnable schedule. The following are to be completed by the Client and Principal Agent and is to be supported in each case by a letter of award and the works completion certificate. Both Client and Principal Agent must sign and stamp the documents, failure to obtain both signatures and stamps will result in no allocation of points. PROJECT NAME and SCOPE OF WORK: Principal agent: ................................................................................................................................. Client: .. ..............................................................................................................................................

  • Work Progress Schedule Refer to Special Conditions and Division 1 General Administration Specifications for additional schedule requirements. Unless indicated otherwise in those documents, Contractor shall submit to the ODR and the A/E its initial Work Progress Schedule for the Work in relation to the entire Project not later than twenty-one (21) days after the effective date of the Notice to Proceed. Unless otherwise indicated in the Contract Documents, the Work Progress Schedule shall be based upon a computerized Critical Path Method (CPM) with full reporting capability. This initial schedule shall indicate the dates for starting and completing the various aspects required to complete the Work, including mobilization, procurement, installation, testing, inspection, and acceptance of all the Work of the Contract. When acceptable to the Owner, the initially accepted schedule shall be the Baseline Schedule for comparison to actual conditions throughout the contract duration.

  • Construction Budget The total amount indicated by the District for the Project plus all other costs, including design, construction, administration, financing, and all other costs.

Time is Money Join Law Insider Premium to draft better contracts faster.