Contract Time / Construction Schedule Sample Clauses

Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall be [days in words] ([days in numbers]) calendar days, commencing with the date upon which the Facilities Lease and the Site Lease are fully executed and delivered to both Parties and ending with completion of the Work which will occur no later than [Date] (“Contract Time”). The Construction Schedule must be approved by the District.
AutoNDA by SimpleDocs
Contract Time / Construction Schedule. 12.2.2.1.The Construction shall be performed pursuant to the construction schedule(s), attached hereto as Exhibit F (“Construction Schedule(s)”). The time period between the Notice to Proceed and Completion shall be the total Contract time (“Contract Time”).
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project Shall be Six-Hundred and Ninety-Three (693) calendar days, commencing on June 5, 2019, and ending with completion of the Work, which will occur no later than April 28, 2021 ("Contract Time"). The Construction Schedule must be approved by the District.
Contract Time / Construction Schedule. It hereby understood and agreed that assuming the District issues a Notice to Proceed on or before June 15, 2013, District and Developer may also approve additional changes in the Construction Schedule. District shall have beneficial occupancy of all sites on or before August 1, 2013, and Project Completion shall on or before August 30, 2013. The time period between the Notice to Proceed and Completion shall be the total Contract time (“Contract Time”). The Construction shall be performed pursuant to the construction schedule, attached hereto as Exhibit F (“Construction Schedule”). The Master Construction Schedule must be approved by the District prior to execution of this Master Facilities Lease.
Contract Time / Construction Schedule. A F T The Parties intend for this Project to proceed in two phases: Phase One – Modernization; and Phase TwoNew Construction. It is hereby understood and agreed that the Contract Time for this Project shall be ( ) calendar days, commencing with the date upon which the District issues the Notice to Proceed with Construction for the first phase and ending with the date of Developer’s completion of the Work for the last phase of the Project (“Contract Time”). Contract Time for a phase will only run/accrue from the date District issues the Notice to Proceed with Construction for that phase through the date of Developer’s completion of the Work for that phase. The Construction Schedule must be approved by the District. R D
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall be Seventy-Seven (77) calendar days for construction, and be Sixty (60) calendar days for close-out, commencing with the Notice to Proceed construction phase and ending with completion of the construction work which will occur no later than [Date] and close-out [Date] (“Contract Time”). The Construction Schedule must be accepted by the District.
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall be from June 20, 2015 through September 1, 2015. (“Contract Time”) The Construction Schedule must be approved by the District.
AutoNDA by SimpleDocs
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for the Project shall be completed by November 20, 2020 (“Contract Time”). The Construction Schedule must be approved by the District.
Contract Time / Construction Schedule. It is hereby understood and agreed that the Contract Time for this Project shall continue until August 2023, commencing with the date upon which the Facilities Lease and the Site Lease are fully executed and delivered to both Parties.

Related to Contract Time / Construction Schedule

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Construction Schedules Construction Manager shall incorporate the relevant portions of the Project Schedule, into its Construction Schedules. Construction Manager shall include with its Estimated Contract Sum preliminary Construction Schedules for Owner Parties’ review. After Owner approves the Project budget, Construction Manager shall update and distribute with the Progress Report its approved Construction Schedules throughout the duration of the Work. Each such updated Construction Schedule shall conform to the Contract Documents’ requirements and shall accurately reflect progress and remaining estimated durations of applicable Work.

  • Neutral Construction Neither party hereto may rely on any drafts of this Agreement in any interpretation of the Agreement. Both parties to this Agreement have reviewed this Agreement and have participated in its drafting and, accordingly, neither party shall attempt to invoke the normal rule of construction to the effect that ambiguities are to be resolved against the drafting party in any interpretation of this Agreement.

  • Contract Construction 6.27.1 The parties acknowledge that each party and its counsel have reviewed this CONTRACT and that the normal rule of construction to the effect that any ambiguities are to be resolved against the drafting party shall not be employed in the interpretation of this CONTRACT or any amendment or exhibits hereto.

  • ADDITIONAL CONSTRUCTIONS The Promoter undertakes that it has no right to make additions or to put up additional structure(s) anywhere in the Project after the building plan has been approved by the competent authority(ies) except for as provided in the Act.

  • Project Construction The Contractor agrees to provide continuous on-site supervision on each Job Order, while progress on the project is being accomplished. The Contractor’s Project Manager will ensure:

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.