Hydro Turbine Pilot Project Sample Clauses

Hydro Turbine Pilot Project. ISSUE: San Xxxxxxx proposed to construct an in-conduit hydroelectric generating station as a pilot-project with NLine Energy, Inc. to demonstrate the viability of converting hydraulic pressure differential to clean renewable electrical energy. In its Application, San Xxxxxxx sought Commission approval of the project and authorization to file an Advice Letter to recover all reasonable, recorded costs of the pilot project, at that time estimated to total $1,813,000. San Gabriel revised this request in Supplemental Testimony following completion in August 2011 of the feasibility study performed by NLine Energy, Inc., which estimated a reduced total cost of $1,385,661. The hydroelectric station would be located at San Gabriel’s Sandhill Water Treatment Plant. Power generated at this facility would offset nearly all of the on-site power load from the Sandhill Plant, with excess energy exported to the power grid. XXX recommended that the Commission not authorize San Xxxxxxx to file an advice letter for the $1,385,661 associated with the project, based on its concerns as to the proposed size of the turbine/generator unit (162 kW) and the related assumption of 5,000 acre-feet per year (“AFY”) of purchased water from Inland Empire Utilities Agency (which would require a constant flow of 6.9 cubic feet per second (“cfs”) and a daily Sandhill Water Treatment Plant capacity usage of 4.46 MGD). In December 2011, San Gabriel received a 50-percent design report from NLine Energy, Inc. which superseded the previous feasibility study provided in San Gabriel’s Supplemental Testimony. The 50-percent design report included further design work and removed the previous assumption of 5,000 AFY of purchased water from Inland Empire Utilities Agency, and instead included a range of possible flows from approximately 2,000 to 5,000 AFY using two turbines operating part-time (6 to 9 months of the year). Upon receiving the 50-percent design report, San Xxxxxxx submitted a request for bids for a turbine/generator in-conduit hydroelectric project equipment package. The winning bid, from Canyon Hydro in Deming, Washington, included two turbines (95 kW and 215 kW) sized for instantaneous flow rates of 12 cfs combined or 4 cfs and 8 cfs independently. San Xxxxxxx provided DRA a revised cost estimate based on the 50-percent design report and a firm bid from Canyon Hydro, totaling $1,353,000, as shown in Table 2. A summary of the expected flow options with unit conversions from cfs to MGD an...
AutoNDA by SimpleDocs

Related to Hydro Turbine Pilot Project

  • PROJECT 3.01. The Recipient declares its commitment to the objectives of the Project. To this end, the Recipient shall carry out the Project in accordance with the provisions of Article IV of the General Conditions.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Generating Facility The Interconnection Customer’s device for the production of electricity identified in the Interconnection Request, but shall not include the Interconnection Customer’s Interconnection Facilities.

  • Project Engineer If the Project has been designed by the Project Engineer, the Project Engineer is to act as the Owner's representative, assumes all duties and responsibilities, and has the rights and authority assigned to Project Engineer in the Contract Documents in connection with completion of the Work all in accordance with the Contract Documents.

  • Sub-projects 1. The Participating Bank shall make Sub-loans to Beneficiaries and appraise, review, approve, and supervise Sub-projects in accordance with the criteria, conditions and procedures set forth in the Operations Manual, including, inter alia, the following eligibility criteria:

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Project Site The “Project Site” is the place where the Work is being carried on.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!