Requirements for Substantial Completion Sample Clauses

Requirements for Substantial Completion. Substantial Completion of the required Work shall occur when, in the sole determination of the Director, all of the conditions set forth below have been satisfied.
AutoNDA by SimpleDocs
Requirements for Substantial Completion. The Work (or a designated portion thereof) shall be deemed Substantially Completed on the date when all of the following events or conditions shall have occurred:
Requirements for Substantial Completion. The Design Consultant and the Authority shall determine the date that the Contractor achieves Substantial Completion for the Project. In order to achieve Substantial Completion, the Contractor must have achieved the following on the Project: (i) all essential requirements of the Contract Documents have been performed so that the purpose of the Contract Documents have been accomplished, (ii) a Temporary Certificate of Occupancy (or Temporary Certificate of Acceptance, if applicable) has been issued by the Department of Community Affairs, (iii) a Punchlist has been created by the Design Consultant and approved by the Authority, (iv) [deliberately omitted] (v) there are no material omissions or technical defects or deficiencies, identified by the Authority or the CM or Design Consultant, and (vi) the Project is one- hundred percent (100%) ready for occupancy in accordance with its intended use.
Requirements for Substantial Completion. The following are the conditions precedent for the Project to achieve Substantial Completion: the Project is Mechanically Complete; the [_________] Tests have been Successfully Run; Contractor shall have paid all Delay Liquidated Damages calculated pursuant to Section 15.1.1; Owner has received all Contractor Deliverables which are either necessary for the operation of the Project or are required to be delivered by the applicable Substantial Completion Date as set forth in the Contractor Deliverables Table;
Requirements for Substantial Completion. (i) Phase I of the Work shall be deemed Substantially Completed (“Substantial Completion”) on the date when such Work shall be sufficiently completed and all of the following shall have occurred: (a) Owner may use and occupy the Phase I area (as set forth in Exhibit “H”); (b) only minor Punch List items (as such term is defined in Section 7.02(bb) hereof), if any, remain incomplete provided they do not interfere with such use and occupancy; (c) a temporary certificate of occupancy (“TCO”) shall have been issued by the appropriate local governmental authority for the Phase I area, unless such TCO is not issued for reasons outside Construction Manger’s reasonable control; and (d) Construction Manager has performed all services and provided all documentation necessary to enable the commencement or continuationof commissioning and validation activities.
Requirements for Substantial Completion. (i) The Work shall be deemed Substantially Completed (“Substantial Completion”) on the date when such Work shall be sufficiently completed and all of the following shall have occurred: (a) Owner may use and occupy the the Work; (b) only minor Punch List items (as such term is defined in Section 7.02(bb) hereof), if any, remain incomplete provided they do not interfere with such use and occupancy; (c) a temporary certificate of occupancy (“TCO”) shall have been issued by the appropriate local governmental authority for the Work, unless such TCO is not issued for reasons outside Construction Manger’s reasonable control; and (d) Construction Manager has performed all services and provided all documentation necessary to enable the commencement or continuation of commissioning and validation activities.
Requirements for Substantial Completion. Prior to making any request for Owner’s approval of Substantial Completion, whether for the Work as a whole or for a portion or phase thereof which, the following must be completed:
AutoNDA by SimpleDocs

Related to Requirements for Substantial Completion

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Project Completion Part 1 – Material Completion

Time is Money Join Law Insider Premium to draft better contracts faster.