Schedule Slippage Sample Clauses

Schedule Slippage. The General Contractor or Prime Consultant will notify the PMT promptly of any delay in the most current approved Project schedule as a result of its Work and must submit a detailed recovery plan for the PMT to evaluate and approve.
AutoNDA by SimpleDocs
Schedule Slippage. Design Builder will notify the Program Manager in writing with a copy to District’s Authorized Representative within 3 business days of any delay in the Project Schedule as a result of its Work and must submit a detailed recovery plan to Program Manager for evaluation and District’s approval. The detailed recovery plan must be submitted within 2 business days of the notice (so within 5 business days from date of delay). All costs associated with the recovery will be the responsibility of the Design Builder unless the Design Builder is entitled to an extension of time under Section 10.5.
Schedule Slippage. If at any time Contractor fails to complete any activity by the completion date in the Approved Project Implementation Schedule, unless previously excused by the SANDAG Project Manager in writing, Contractor will be required, within seven (7) days, to submit to the Project Manager a statement as to how it plans to return to compliance. Contractor shall furnish sufficient resources to ensure the performance of the Work in accordance with the Approved Project Implementation Schedule. If Contractor falls behind in the performance of the Work as indicated in the Approved Project Implementation Schedule, Contractor shall take such steps as may be necessary to improve its progress. If Contractor fails or refuses to implement measures sufficient to bring its Work back into conformity with the current Approved Project Implementation Schedule, its right to proceed with any or all portions of the Work may be terminated under the provisions of the Agreement. However, in the event SANDAG, in its sole determination, should permit Contractor to proceed, SANDAG’s permission shall in no way operate as a waiver of its rights nor shall it deprive SANDAG of its rights under any other provisions of the Agreement. Under no circumstances is either party responsible for any delay (or resulting damages) caused solely by or arising solely from the actions of the other party, or the other party’s employees, agents, officers or subcontractors. Any review or acceptance by the Project Manager of the schedules submitted by Contractor to the Project Manager shall merely mean that, in the opinion of the Project Manager, Contractor has complied with the requirements of this section. No such review shall release or relieve Contractor from full responsibility for the accurate, complete and timely performance of the Work, including the accuracy and completeness of the schedules, or any other duty, obligation or liability imposed on it by the Agreement including the responsibility for completing the Work within the time set forth in the Agreement. The review shall also not constitute a representation by SANDAG that Contractor will be able to proceed or complete the Work in accordance with the dates contained in said schedule.‌ In addition to all other rights and remedies available to SANDAG, if Contractor fails to meet any of the Guaranteed Completion Dates in Section 25.4.1 of this Agreement, the Contractor shall be subject to Liquidated Damages as specified in Section 2.3.7 of this Agreemen...
Schedule Slippage. The Contractor and/or Architect will notify the PMT within 48 hours of any slippage in the VTS as a result of its Work and must submit a detailed recovery plan for evaluation and approval by the PMT.
Schedule Slippage. The Design-Build Entity will notify Owner within 72 hours of any slippage in the Monthly Project Schedule as a result of its Work and must submit a detailed recovery plan for evaluation and approval by Owner. All costs associated with the recovery, which shall provide for completion of the Project within the Contract Time, will be the responsibility of the Design-Build Entity unless the Design-Build Entity is entitled to an extension of time under Section 8.4

Related to Schedule Slippage

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Schedule Updates the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and Contractor agrees not to charge the County.

  • Outage Schedules The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional overtime, breaking of maintenance contracts or other costs above and beyond the cost the Developer would have incurred absent the request to reschedule maintenance, shall be in accordance with the ISO OATT. Developer will not be eligible to receive compensation, if during the twelve (12) months prior to the date of the scheduled maintenance, the Developer had modified its schedule of maintenance activities other than at the direction of the NYISO or request of the Connecting Transmission Owner.

  • SCHEDULE OF WORK FIRST PARTY’S proposed schedule for the various services required will be set forth in Exhibit A-1. In addition to services described in Section A1, the parties may from time to time agree in writing that FIRST PARTY, for additional compensation, shall perform additional services including but not limited to: • Change in the services because of changes in scope of the work. • Additional tasks not specified herein as required by the CITY. The CITY and FIRST PARTY shall agree in writing to any changes in compensation and/or changes in FIRST PARTY’s services before the commencement of any work. If FIRST PARTY deems work he/she has been directed to perform is beyond the scope of this agreement and constitutes extra work, FIRST PARTY shall immediately inform the CITY in writing of the fact. The CITY shall make a determination as to whether such work is in fact beyond the scope of this agreement and constitutes extra work. In the event that the CITY determines that such work does constitute extra work, it shall provide compensation to the FIRST PARTY in accordance with an agreed cost that is fair and equitable. This cost will be mutually agreed upon by the CITY and FIRST PARTY. A supplemental agreement providing for such compensation for extra work shall be negotiated between the CITY and the FIRST PARTY. Such

  • Schedule The Work shall be performed as expeditiously as possible in conformity with the schedule requirements contained herein and in the Statement of Work. The draft and final versions of all deliverables shall be submitted by the dates specified in the Exhibit A Schedule and Project Period noted in Item No. 7 of this Agreement. It is understood and agreed that the delivery of the draft and final versions of such deliverables by the Contractor shall occur in a timely manner and in accordance with the requirements of the Exhibit A Schedule.

  • Schedule Change When a change of work schedule is requested by an employee and approved by the Agency, all forms of penalty pay shall be waived by the employee. When a change of work schedule is requested by an employee and approved by the Agency, overtime compensation for that workday, but not for work over forty (40) hours per week, associated with the changed schedule shall be waived.

  • Schedule Changes (a) If, in the course of a posted schedule, the Employer: (i) changes Employees’ scheduled days off without giving 14 days’ notice of the change, they shall be paid 2X their Basic Rate of Pay for all hours worked on what would otherwise have been their off-duty days. (ii) changes Employees’ scheduled Shift, but not their scheduled days off, without giving 14 days’ notice of the change, they shall be paid 2X their Basic Rate of Pay for all hours worked during the first Shift of the changed schedule. (b) Employees shall be notified of such changes in their schedule and such changes shall be recorded on the Shift schedule. (c) An Employee or the Employer may, during the course of a posted schedule, ask to amend scheduled Shifts. Such Employee requests shall be granted where operationally possible without additional cost. Where mutually agreed, the requirements for 14 days’ notice of change and the resultant penalty pay as described in Article 7.04(a) shall not apply. Employees or the Employer should make such requests as far in advance as possible in order to maximize the ability to accommodate the request. Any Shift changes made by mutual agreement shall not violate the scheduling provisions of this Article.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!