Certificate of Final Completion. The form prescribed by the Authority which contains the certification of the Designer, OPM and the Owner that the Project has reached Final Completion.
Certificate of Final Completion. Upon satisfactory completion of the work outstanding on the Works, the Engineer shall within twenty eight (28) days of the expiration of the Defects Liability period issue a Certificate of Final Completion to the Contractor. The Contract shall be deemed to be completed upon issuance of such Certificate, provided that the provisions of the Contract which remain unperformed and the Settlement of Disputes provision in the Contract shall remain in force for as long as is necessary to dispose of any outstanding matters or issues between the Parties.
Certificate of Final Completion. Upon satisfactory completion of the work outstanding on the Works, the Engineer shall within twenty eight (28) days of the expiration of the Defects Liability period issue a Certificate of Final Completion to the Contractor. The Contract shall be deemed to be completed upon issuance of such Certificate, provided that the provisions of the Contract which remain unperformed and the Settlement of Disputes provision in the Contract shall remain in force for as long as is necessary to dispose of any outstanding matters or issues between the Parties. ALTERATIONS, ADDITIONS AND OMISSIONS Variations The Engineer may within his powers introduce any variations to the form, type or quality of the Works or any part thereof which he considers necessary and for that purpose or if for any other reasons it shall, in his opinion be desirable, he shall have power to order the Contractor to do and the Contractor shall do any of the following: increase or decrease the quantity of any work under the Contract; omit any such work; change the character or quality or kind of any such work; change the levels, lines, positions and dimensions of any part of the Works; execute additional work of any kind necessary for the completion of the Works, and no such variation shall in any way vitiate or invalidate the Contract.
Certificate of Final Completion. When Contractor considers that the Facility has achieved Final Completion in accordance with Section 18.1, it shall deliver to Owner a Certificate of Final Completion signed by Contractor, together with reasonable supporting documentation evidencing the satisfaction of the provisions in Section 18.1. Upon receipt of the Certificate of Final Completion from Contractor together with supporting documentation, Owner shall promptly, but in no event later than ten (10) Business Days from the date of receipt of Contractor's notice, either issue Contractor: (a) a countersignature to the Certificate of Final Completion, signed by Owner's Representative and stating that the Final Completion Date for the Facility is the date on which Contractor gave its notice to Owner under this Section 18.2; or (b) a written notice stating why Owner does not consider that Final Completion of the Facility has been achieved.
Certificate of Final Completion. See the General Conditions of Wake County's Standard Construction Agreement with contractors.
Certificate of Final Completion. (a) After expiry of the Defects Correction Period, and provided the Alliance Manager is not aware of any outstanding Defects, the Alliance Manager will submit a draft Certificate of Final Completion to the ALT for its approval.
(b) If the ALT approves the draft Certificate of Final Completion, the Alliance Manager will sign and date the certificate and issue it to the Participants.
(c) If the ALT does not consider the Alliance Works to have reached Final Completion or considers that there is some other obligation under this Agreement which has not been performed or observed:
(i) the ALT will inform the Alliance Manager as to what the ALT considers to be outstanding to achieve Final Completion or to perform or observe the relevant obligation under this Agreement; and
(ii) the Alliance Manager will promptly inform the Participants that Completion has not been achieved and any details of the outstanding work or the failure to perform or observe some other obligation under this Agreement.
(d) Once the Alliance Manager is satisfied that the outstanding work or obligation has been completed, performed or observed in accordance with this Agreement, the Alliance Manager will again initiate the approval process under this clause 6.6.
(e) The Certificate of Final Completion must also refer to the date which the ALT determines is the Date of Final Completion.
Certificate of Final Completion. (a) After expiry of the Defects Notification Period, and provided the Alliance Manager is not aware of any outstanding Defects, the Alliance Manager will submit a Certificate of Final Completion to the ALT for its approval.
(b) If the ALT agrees that Final Completion has been achieved, the ALT will complete Part 2 of the Certificate of Final Completion and submit it to the Principal's Representative for approval.
(c) If the Principal's Representative agrees that Final Completion has been achieved, the Principal's Representative will complete Part 3 of the Certificate of Final Completion and indicate the Date of Final Completion.
(d) If the ALT or the Principal's Representative does not consider the Alliance Works to have reached Final Completion or considers that there is some other obligation under this Agreement which is required to be performed to reach Final Completion which has not been performed or observed:
(i) the ALT or the Principal's Representative (as applicable) will complete the relevant Part of the Certificate of Final Completion indicating what the ALT or the Principal's Representative considers to be outstanding to achieve Final Completion or to perform or observe the relevant obligation under this Agreement; and submit the Certificate of Final Completion to the Alliance Manager; and
(ii) the Alliance Manager will promptly inform the Participants that Final Completion has not been achieved and any details of the outstanding work or the failure to perform or observe the relevant obligation under this Agreement.
(e) If the ALT considers that Final Completion has been achieved but the Principal's Representative does not agree, and a NOP wishes to pursue the issue, the NOP may by written notice to the other Participants and TfNSW request that the issue be resolved in accordance with clause 18.2.
(f) Once the Alliance Manager is satisfied that the outstanding work or obligation required to be performed to reach Final Completion has been completed, performed or observed in accordance with this Agreement, the Alliance Manager will again initiate the approval process under this clause 12.4.
Certificate of Final Completion. Certificate issued by the OWNER when the Work has been completed in accordance with the Construction Contract Documents and the OWNER has received all documents and items necessary for closeout of the Work.
Certificate of Final Completion. Reference is made to that certain Engineering, Procurement & Construction Agreement dated as of ______________, 2023 by and between Owner and Contractor (the “Agreement”). Capitalized terms used, but not defined, herein shall have the meanings set forth in the Agreement.
Certificate of Final Completion. The following which may be delivered or issued after the Effective Date of the Contract and are attached hereto: All Written Amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to the General Conditions.