Commencement of the Works. Before the commencement of the WUC, the Contractor shall: provide the Principal with a copy of the Contractor’s construction programme referred to in clause 43; effect all insurances required under clauses 7. and 8. and lodge evidence of such with the Superintendent; give the Superintendent seven (7) days’ notice in writing of the proposed date of commencement of the Works; obtain approval from the Superintendent for the nominated Contractor’s Representative; and provide to the principal a geotechnical report specifying the Site’s engineering classification.
Commencement of the Works. 38.1 The Contractor shall not commence the Works prior to the issuance of the Commencement Order (“Commencement Order”).
38.2 Within sixty (60) days following the Signature Date, the Contractor shall be responsible to fulfill all the necessary conditions to obtain the Commencement Order. Any failure thereof, shall entitle NI to receive from the Contractor Liquidated Damages for delay, as detailed in Appendix B (Contractual Milestones).
38.3 The achievement of the Commencement Order shall be subject to the fulfillment of the following conditions:
Commencement of the Works. At least seven days before commencement of the works, the Developer shall notify the Section Engineer: Contract Management of Council of the commencement date. Such Notice shall be accompanied by all relevant documentation, such as but not limited to:
a) A copy of the signed Development Agreement;
b) 1 copy of the set of approved construction drawings (released for construction);
c) 1 copy of the construction contract document containing the specifications.
Commencement of the Works. The Contractor agrees to carry out the Works using a degree of skill, care and diligence reasonably expected from a Contractor carrying out similar Works. The Contractor shall perform the Works and supply the Materials as specified in the Contract Documents and agrees to comply with all reasonable instructions from the Principal. The Contractor shall provide all Materials, labour, plant, and anything else required to perform the Works.
Commencement of the Works. Subject to the receipt of all Necessary Consents, delays caused by a Relevant Event and the requirements of Schedule 4, the Developer shall use all reasonable endeavours to commence the Works on the date for commencement of the Construction Period specified in the Programme.
Commencement of the Works. (a) The Organisation must obtain the Commonwealth's approval to commence that part of the Works that relates to the construction and/or fit-out of the Works. The Commonwealth may give or withhold its approval at its discretion but will only provide such approval:
(i) after the Organisation has delivered, to the Commonwealth's satisfaction, the relevant Deliverables set out in the Deliverables and Milestones Schedule;
(ii) if it is satisfied that the Organisation has complied with the requirements set out in clause 23.10(b).
(b) Without limiting clause 23.10(a) or the Organisation's obligations under clause 23.10, the Organisation must not commence that part of the Works that relates to the construction and/or fit-out of the Works until it has:
(i) obtained written approval from the Commonwealth under clause 23.10(a) (which will not be unreasonably withheld);
(ii) obtained all relevant Approvals required under clause 3.1 that are necessary to enable the Commencement of the Works;
(iii) obtained all insurances required under clause 16.1(a);
(iv) complied with its obligations under clause 4.3(a); and
(v) provided security to the Commonwealth in accordance with clause 5.1.
(c) The Organisation must:
(i) obtain written approval from the Commonwealth under clause 23.10(a); and
(ii) commence that part of the Works that relates to the construction and/or fit-out of the Works, on or before the date specified for the Commencement of the Works in Item 5 of Schedule 1.
Commencement of the Works. (a) The Organisation must obtain the Commonwealth's approval to commence the construction of the Works. The Commonwealth may give or withhold its approval at its discretion but will only provide such approval after the Organisation has delivered, to the Commonwealth's satisfaction, the relevant Deliverables set out in the Deliverables and Milestones Schedule.
(b) Without limiting clause 4.4(a) or the Organisation's obligations under clause 4.4(c), the Organisation must not commence the Works until it has:
(i) obtained all relevant Approvals required under clause 3.4 that are necessary to enable the commencement of the Works;
(ii) obtained all insurances required under clause 21.1(a);
(iii) complied with its obligations under clause 6.3(a); and
(iv) where applicable, provided financial security to the Commonwealth in accordance with clause 6.6, and it has obtained written confirmation from the Commonwealth (which will not be unreasonably withheld) that the Commonwealth is satisfied that the Organisation has complied with the requirements set out above.
(c) The Organisation must:
(i) obtain written confirmation from the Commonwealth under clause 4.4(a) and
(ii) commence the Works, on or before the date specified for the commencement of the Works in Item 4 of Schedule 1 with time being of the essence.
Commencement of the Works. 15.1 Instruction by the ALT
Commencement of the Works. Subject to the provisions in respect of track possessions at clause 23, each Participant may only commence the Works on the Site to the extent that:
15.2.1 prior notice of such commencement has been given by the ALT to the Owner;
15.2.2 the Owner or the relevant Participant has procured insurance pursuant to clause 38 which provides cover in respect of any aspect of carrying out the Works at the Site by that Participant;