Construction Planning Meeting. 5.1.1. Within ten (10) Business Days of receipt of the Facility Study report, the Interconnection Customer shall request a Construction Planning Meeting, where failure to comply shall result in the Interconnection Request being deemed withdrawn. The Construction Planning Meeting request shall be in writing and shall include the Interconnection Customer’s reasonably requested date for completion of the construction of the Upgrades and Interconnection Facilities.
AutoNDA by SimpleDocs
Construction Planning Meeting. 5.1.1 Within ten (10) Business Days of receipt of the FacilityFacilities Study reportReport, the Interconnection Customer shall request a Construction Planning Meeting, where failure to comply shall result in the Interconnection Request being deemed withdrawn. The Construction Planning Meeting request shall be in writing and shall include the Interconnection Customer’s reasonably requested date for completion of the construction of the Upgrades and Interconnection Facilities. Author [A7] Utilities: Removed the proposed revision from CCEBA regarding Grid Enhancing Technology. The Utilities are not able to accommodate CCEBA’s proposed additions at this time. SC Generator Interconnection Procedures 27
Construction Planning Meeting 

Related to Construction Planning Meeting

  • Scoping Meeting 4.2.1 A scoping meeting will be held within ten (10) Business Days after the Interconnection Request is deemed complete, or as otherwise mutually agreed to by the Parties. The Utility and the Interconnection Customer will bring to the meeting personnel, including system engineers and other resources as may be reasonably required to accomplish the purpose of the meeting. The scoping meeting may be omitted by mutual agreement in writing.

  • Project Managers; Meetings 10.1 Promptly following the Effective Date, each Party shall designate a Project Manager responsible for coordinating the Party’s Work and shall provide the other Party with a written notice containing the name and contact information of such Project Manager (“Project Manager”). In no event shall any Project Manager be authorized to amend or modify the provisions of this Agreement. Each Party may change its Project Manager, from time to time, by written notice to the other Party.

  • Project Kick-off Meeting The Contractor shall hold a project kick-off meeting within thirty days from the contract execution date. The Contractor shall coordinate with NYSERDA's Project Manager to arrange the meeting at a mutually convenient time and place. The Contractor is encouraged to invite representatives of sub-contractors and equipment vendors. The purpose of this meeting shall be to finalize the strategies for accomplishing the objectives of this work. In a timely manner, the Contractor shall submit to NYSERDA’s Project Manager a brief report summarizing the issues discussed and decisions made, if any, during this meeting. Deliverable: A brief report regarding the project kickoff meeting.

  • Safety Meetings (iii) Accident investigation.

  • Orientation Meeting Within thirty (30) calendar days from execution of the Contract, Vendor and Order Fulfillers will be required to attend an orientation meeting to discuss the content and procedures of the Contract to include reporting requirements. DIR, at its discretion, may waive the orientation requirement for Vendors who have previously held DIR contracts. The meeting will be held in the Austin, Texas area at a date and time mutually acceptable to DIR and the Vendor or by teleconference, at DIR’s discretion. DIR shall bear no cost for the time and travel of the Vendor or Order Fulfillers for attendance at the meeting.

  • Construction Change Directive A written order prepared and issued by the District, the Construction Manager, and/or the Architect and signed by the District and the Architect, directing a change in the Work.

  • Construction Change Directives 7.3.1 A Construction Change Directive is written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum, or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusting accordingly.