Estimated Project Cost Sample Clauses

Estimated Project Cost. A reasonable estimate of the Costs of the Project is shown in Section 1, and the Project is fully funded.
AutoNDA by SimpleDocs
Estimated Project Cost. A. The Bureau of Reclamation has estimated the final cost of the Project as of March 29, 2019, based on the Consensus Design Concept, is $406 million.
Estimated Project Cost. A. As of the date of this Agreement, the estimated cost of construction and engineering services for the Improvements covered by this Agreement, exclusive of the cost of right- of-way or easement acquisition, is One Million Eight Hundred Sixty-Nine Thousand Three Hundred Eighty-Nine Dollars and Fifty Cents ($1,869,389.50).
Estimated Project Cost. Design and construction of the Baseline Project is currently estimated to cost a total of $37,180,000 (“Estimated Project Cost”). The Estimated Project Cost includes the cost the cost of design and construction itself, the cost of additional right-of-way acquisitions, professional services, and unallocated contingency. Those cost categories are set forth more fully in the XXXXX XX Xxxxx. Such figure is only an estimate. The actual cost to design and construct the Baseline Project (the “Actual Project Cost”) may turn out to be either more or less than the Estimated Project Cost.
Estimated Project Cost. (Loan Amount)
Estimated Project Cost. The Estimated Project Cost (the “Estimated Project Cost”) is Rs. 8,749 crores (Rupees Eight Thousand Seven Hundred Forty Nine Crores).
Estimated Project Cost. The parties acknowledge and agree that the County Stormwater Management Program has established an estimated total design cost of the Project of One Hundred Sixty Nine Thousand Nine Hundred Forty Five Dollars ($169,945) based upon engineering and design assumptions that the Preliminary Study may or may not confirm. The parties shall, upon the completion of the Preliminary Study, analyze and consider the proposed scope and conceptual design of the Project as set forth in the Preliminary Study. If the parties cannot agree upon the scope or conceptual design of the Project, then either party may terminate this agreement upon fifteen days notice to the other. Upon such termination, the City shall be reimbursed by the County for costs and expenses incurred in connection with the Preliminary Study subject to the limitations set forth in the Policy and Procedures and in this agreement.
AutoNDA by SimpleDocs
Estimated Project Cost. Source of Funding 1. LRIP Request: $ 1,250,000.00 2. Federal Funds: 3. State Aid Funds: 4. Local/Other Funds: $ 1,250,000.00 5. MnDOT Trunk Highway Funds: 6. Total Project Cost: $ 2,500,000.00
Estimated Project Cost. As defined in Clause 1.1.4 Experience Score As defined in Clause 3.2.6 Factory As defined in Clause 1.1.1 Financial Capacity As defined in Clause 2.2.2 (B) Government Government of India High Speed Train Set Train Set, with speed of 250 km/h or more, having 8 or more cars Jt. Bidding Agreement As defined in Clause 2.2.6 (g) Lead Member As defined in Clause 2.2.6 (c) LOA Letter of Award Locomotive As defined in Clause 1.1.1 Mechanical System Locomotive shell, bogies, suspension and transmission system Member Member of a Consortium Net Worth As defined in Clause 2.2.4(ii) PPP Public Private Partnership Price As defined in Clause 1.2.8 Project As defined in Clause 1.1.1 Propulsion System Set of traction converters, traction motors and vehicle electronics

Related to Estimated Project Cost

  • Project Costs Simultaneously with the execution of this Agreement, the Company shall disclose to the Department all of the Project Costs which the Company seeks to include for purposes of determining the limitation of the amount of the Credit pursuant to Section 5-30 of the Act and provide to the Department a Schedule of Project Costs in the form as attached hereto as Exhibit C.

Time is Money Join Law Insider Premium to draft better contracts faster.