Flight Delays Sample Clauses

Flight Delays. Where flights to and from the Project site are delayed for less than 4 hours due to inclement weather or aviation related delays, no compensation will be paid to the Employee. Where flights to the Project site are delayed for greater than 4 hours due to inclement weather or aviation related delays, the following conditions will apply:
AutoNDA by SimpleDocs
Flight Delays. JFI and its agents shall not be liable for any direct or indirect cost or damages resulting from flight cancellations or delays due to maintenance issues, crew sickness or unavailability, weather, air traffic control, acts of God, national emergencies, terrorist incidents, war or any other such cause. Refunds will not be issued for completed flights or flight segments. JFI will assist Client to secure alternate transportation if a trip cannot be completed but it shall be the Client’s responsibility to pay the cost of such alternate transportation. JFI’s liability shall in all cases be limited to amounts paid by Client for flight segments not flown, less costs incurred by JFI or its vendors.

Related to Flight Delays

  • Operation Delays STATE shall have the authority to delay or suspend the operations of PURCHASER and contractors of PURCHASER, wholly or in part, under this contract for such period or periods necessary due to fire hazard conditions, severe weather occurrence, surveying for threatened or endangered species listed under the state or federal Endangered Species Act, or any other activity STATE determines to be necessary for identification, management, or protection of a threatened or endangered species. PURCHASER agrees to cooperate with surveying efforts of STATE or its contractors. In no event shall STATE be liable for any costs incurred by PURCHASER by reason of delay or suspension under this section, including but not limited to costs of additional move-in/move-out of equipment and personnel, extra fire and equipment security, and insurance or bonding expenses.

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Unavoidable Delays Delays due to acts of God, acts of public agencies, labor disputes, strikes, fires, freight embargoes, inability (despite the exercise of due diligence) to obtain supplies, materials, fuels or permits, or other causes or contingencies (excluding financial inability) beyond the reasonable control of Landlord or Tenant, as applicable. Landlord shall use commercially reasonable efforts to provide Tenant with prompt notice of any Unavoidable Delays.

  • Payment Delay Notwithstanding any other terms of this Agreement, no payments will be made to CONTRACTOR until COUNTY is satisfied that work of such value has been rendered pursuant to this Agreement. However, COUNTY will not unreasonably withhold payment and, if a dispute exists, the withheld payment shall be proportional only to the item in dispute.

  • Unavoidable Delay When construction is impeded as a result of strikes, lockouts, acts of God or other factors beyond the control, and ability to remedy, of the Developer.

  • Concurrent Delay When the completion of the Work is simultaneously delayed by an excusable delay and a delay arising from a cause not designated as excusable, Contractor may not be entitled to a time extension for the period of concurrent delay.

  • Standard Work Week The standard work week shall be thirty-five (35) hours and is composed of five (5) consecutive standard work days.

  • Construction Period During the construction period, Redeveloper agrees to keep the construction area, including completed operations insured against loss or damage by fire, and such other risks, casualties, and hazards as are customarily covered by builders’ risk or extended coverage policies in an amount not less than the replacement value but allowing for reasonable coinsurance clauses and deductibles. In the event of any insured damage or destruction, Redeveloper agrees to use its good faith efforts to commence restoration of the Private Improvements to its prior condition within nine (9) months from the date of the damage or destruction, and shall diligently pursue the same to completion.

  • Standard Workweek Except as noted below the standard workweek for full-time employees consists of five (5) consecutive eight (8) hour days, Monday through Friday each week. Non-overtime hours and starting and quitting times for such employees shall be the same throughout the standard workweek. The standard workweek does not apply to the following:

Time is Money Join Law Insider Premium to draft better contracts faster.