Contract Schedule Development Sample Clauses

Contract Schedule DevelopmentWithin thirty (30) days after receiving the Notice to Proceed under Article 5 of the General Construction Provisions, Part I of the Project Manual, Contractor shall submit a detailed Proposed Contract Schedule presenting an orderly and realistic plan for completion of the Work, in conformance with the requirements of this specification. The Proposed Contract Schedule shall be in hard copy and electronic format. The Contract Schedule shall furnish or comply with the following requirements: (a) A time-scaled CPM type schedule. (b) No activity on the schedule shall have duration longer than twenty one (21) days, with the exception of fabrication and procurement activities, unless otherwise approved by the District Representative. Activity durations shall be the total number of actual days required to perform that activity including consideration of weather impact on completion of that activity. (c) Procurement of major equipment, through receipt and inspection at the job site, identified as a separate activity. (d) District-furnished materials and equipment if any, identified as separate activities. (e) Dependencies (or relationships) between activities. (f) Processing/approval of Submittals and shop drawings for major equipment. Activities that are dependent on Submittal acceptance and/or material delivery shall not be scheduled to start earlier than the expected acceptance or delivery dates. (g) Separate buildings and other independent project elements shall be individually identified in the network. (h) Fourteen (14) days for developing punch list(s), completion of punch list items, and final clean up for the work or any designated portion thereof. (i) Interface with the work of other contractors (or entities). The District Representative will review the Proposed Contract Schedule for conformance with the requirements of this Facilities Lease. Within seven (7) days after receipt, the District Representative will approve the Contract Schedule or will return it with comments. If the Proposed Contract Schedule is not approved, Contractor shall revise the schedule to incorporate comments and resubmit the schedule for approval within seven (7) days after receiving it. The approved schedule shall become the Contract Schedule. The Contract Schedule shall be the basis for evaluating job progress, payment requests, and time extension requests. The responsibility for developing the Contract Schedule and monitoring actual progress as compared to the schedule rests wi...
Contract Schedule Development. Within fifteen (15) days after receiving the NOTICE TO PROCEED, CONTRACTOR shall submit a detailed proposed CONTRACT SCHEDULE presenting an orderly and realistic plan for completion of the WORK, in conformance with the requirements of the CONTRACT DOCUMENTS.

Related to Contract Schedule Development

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Project Development a. Collaborate with COUNTY and project clients to identify requirements and develop a project Scope Statement. a. Develop a Work Breakdown Structure (WBS) for each project. b. Evaluate Scope Statement to develop a preliminary cost estimate and determinate whether project be vendor bid or be executed under a Job Order Contract (JOC).

  • Statement of Work The Statement of Work to which Grantee is bound is incorporated into and made a part of this Grant Agreement for all purposes and included as Attachment A.

  • Project Work Plan The Statement of Work is the formal document incorporated into the Grant. The Project Work Plan documents how the Grantee will achieve the performance measures outlined in the Grant. Changes to the Statement of Work require an amendment. Project Work Plans may be changed with written approval from PEI and the Grantee.

  • Design Development An interim step in the design process. Design Development documents consist of plans, elevations, and other drawings and outline specifications. These documents will fix and illustrate the size and character of the entire project in its essentials as to kinds of materials, type of structure, grade elevations, sidewalks, utilities, roads, parking areas, mechanical and electrical systems, and such other work as may be required.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Program Development NWESD agrees that priority in the development of new applications services by XXXXX shall be in accordance with the expressed direction of the XXXXX Board of Directors operating under their bylaws.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Sustainable Development 4.1 The Authority will review the Contractor’s Sustainable Development Policy Statement and Sustainable Development Plan submitted by the Contractor in accordance with the Schedule (Sustainable Development Requirements) and then at least annually thereafter. 4.2 Sustainable Procurement Risk Assessment Methodology (SPRAM) is a tool used by the Authority to identify and mitigate any potential risks to sustainability in contracts. The process requires that each Contract be assessed for its potential social, economic and environmental risks, throughout the various stages of its lifetime. Where risks are identified, appropriate mitigation action is required to reduce or eliminate the risk to sustainability. The Authority may at times require input from the Contractor in order to ensure that this process is given the required levels of consideration.