Final Submittals. Tenant shall submit the following to City within ninety (90) days of beneficial occupancy:
a. Certified Financials. Tenant shall submit a statement of construction costs certifying the total construction cost of any improvement in a form reasonably required by City.
Final Submittals. Tenant shall submit the following to City within ninety
a. Certified Financials. Tenant shall submit a statement of construction costs certifying the total construction cost of any improvement in a form reasonably required by City.
Final Submittals. Tenant shall submit the following to City within ninety (90) days of beneficial occupancy:
Final Submittals. A. No Contract will be finalized until all of the following have been submitted as required in Section 1100, SUBMITTALS:
1. Final shop drawings.
2. Record drawings.
3. Interface information.
4. Operation and Maintenance Manuals.
5. Equipment maintenance summaries.
6. Manufacturer's certification of proper installation.
7. Material certification for each item provided stating that it meets the requirements of the Specifications.
8. Sewer “as-builts” as specified by the Metropolitan St. Louis Sewer District (if required).
B. No Contract will be finalized until all guarantees, bonds, certifications, licenses, and affidavits required for work or equipment as specified are satisfactorily filed with the Engineer and Owner.
Final Submittals. Tenant shall submit the following to Lessor within ninety (90) days of beneficial occupancy:
a. Certified Financials. Tenant shall submit a statement of construction costs certifying the total construction cost of any improvement in a form reasonably required by Lessor.
Final Submittals. A submittal shall be considered a "Final Submittal" if the Municipality's responds in any of the following: pursuant to the above Section 23.4.1(1) "Reviewed as submitted", pursuant to the aforesaid Section 23.4.1.(e)(2), "Revise as noted - do not resubmit", subject to its revision as per any comments noted by the Municipality or if the Municipality determines, in accordance with the provisions of the aforesaid Section 23.4.1.(e)(2)(4) "Not reviewed" - not to review the Submittal.
Final Submittals. Not later than day prior to scheduled final inspection, Contractor shall provide to Project Manager:
1. Record drawing sets of all plans and shop drawings annotated for as-built conditions.
2. Manuals and shop drawings annotated for any exceptions noted and as-built conditions.
3. Specified warranties pursuant to Article IV VI Section E.
4. Any remaining documentation of certifications and testing, and resubmittal of any such prior documentation that may have been subsequently updated by the final installation work.
5. A letter from the Contractor verifying his completion of the work in accordance with specifications and requesting final inspection and acceptance by the Agency. June 17, 2020 County of Ventura Bid #6001 Page C-41 General Conditions
Final Submittals. The LAWA ACAMS O&M Provider shall furnish to LAWA the following items prior to final payment (LAWA ACAMS O&M Provider's final Application for Payment will not be processed by LAWA without receipt of closeout submittals):
a. Duly executed Affidavit of Payment of Debts and Claims.
b. Duly executed Affidavit of Release of Liens.
c. Consent of Surety to final payment.
d. Spare Parts (as applicable). Airport Technology and Business Systems - Project Management Office
Final Submittals. 1. The Contractor, prior to requesting final payment, shall obtain and submit the following items to the District Engineer for transmittal to the District:
i) Written guarantees, as required.
ii) O&M information and instructions as specified in section 01730.
iii) Completed record drawings.
iv) Certificates of inspection.
v) Correction period bonds.
vi) Written unconditional releases from all parties who are entitled to claims against the subject project, property, or improvement pursuant to the provisions of law.
vii) Equipment manufacturer's startup test reports, installation certifications affidavits, and warranties. GENERAL PROVISIONS
SECTION 1. BID REQUIREMENTS AND CONDITIONS
Final Submittals. A. The CONTRACTOR, prior to requesting final payment, shall obtain and submit the following items to the ENGINEER for transmittal to the OWNER:
1. Written guarantees, where required.
2. Technical Manuals and instructions.
3. Maintenance stock items; spare parts; special tools.
4. Completed record drawings.
5. Bonds for roofing, maintenance, etc., as required.
6. Certificates of inspection and acceptance by local governing agencies having jurisdiction.
7. Releases from all parties who are entitled to claims against the subject project, property, or improvement pursuant to the provisions of law.