Solar Power Plant Sample Clauses

Solar Power Plant. The Promoter will install an Elevated Grid Connected Solar Power Plant at roof top of the Said Complex in accordance with the provisions of MNRE Notification dated 02nd September 2016, WBERC Notification dated 22nd March 2013 and WBREDA notification dated 5th June 2012 for providing power for operating lifts, pumps and Common Areas at the Said Complex (Said Solar Power Plant).
AutoNDA by SimpleDocs
Solar Power Plant. 15.16.1 The Authority is contemplating setting up of 16 MW Solar Power Plant (“Solar Power Plant”) over the proposed cycle track through competitive bidding process. The Solar Power Plant shall be established, operated and maintained through a third-party agency. The obligation of the Concessionaire shall be to facilitate the third party towards setting up of the Solar Power Plant. 15.16.2 It is agreed by the Parties that the Concessionaire shall be utilizing the power generated from the Solar Power Plant for the purpose of the Project. It is clarified that the cost of tariff per unit to the Concessionaire shall be the same as prevailing rate of HT category as charged by the Telangana Southern Power Distribution Company Limited (“TSSPDCL”) or the actual cost of the power procurement by the Concessionaire, whichever is lower (hereinafter referred to as “Power Rate”). In the event, the cost of power supplied by the solar power plant is less than the Power Rate , Concessionaire shall pay the difference to the Authority. Further, in case the cost per unit supplied by the Solar Power Plant is more than the Power Rate , Authority shall compensate by paying the difference to the Concessionaire. 15.16.3 The Concessionaire shall submit the statement for power consumption from Solar Power Plant and details of Power Rate to the Independent Engineer with a copy to Authority on a half - yearly basis for its review. Independent Engineer shall review the Concessionaire’s claim for Additional O&M based on the books of accounts, other records etc. maintained by the Concessionaire and submit its report on the power consumption statement to both the Parties within 15 calendar days from the date receipt of such statement. Either Party shall pay to the other Party, differential power consumption cost within 30 calendar days from the date of receipt of report from the Independent Engineer. 15.16.4 The Parties understands that during the Concession Period, the Authority may establish more such power plants at the Project Site. The obligation of the Concessionaire with respect to such upcoming plant during the Concession Period shall be in accordance with Clause 15.16.1 to 15.16.3.
Solar Power Plant. Common Unit as per clause 1.3 of this schedule below.
Solar Power Plant. The Promoter shall at its sole discretion install an Elevated Grid Connected Solar Power Plant at roof top of Towers in the Said Complex for providing power for certain Common Amenities and Common Areas at the Said Complex (Said Solar Power Plant). Such Common Amenities and common areas shall be decided by the Promoter at its sole discretion under the following terms mentioned hereunder and the Allottee hereby agrees and undertakes to never raise any objection or claim towards the same: 53.1 The capacity of the Said Solar Power Plant shall be as per the sole discretion of the Promoter. 53.2 Costs of installation of the Said Solar Power Plant shall be borne and incurred by the Promoter either directly by itself or through the Association subject to the term that the subsidy, if any, sanctioned and paid by the Central or State Government either to the Promoter or the Association, the Promoter shall solely and exclusively be entitled to be paid the same. 53.3 The Promoter shall initially look after and manage the maintenance and operation of the Said Solar Power Plant to be installed on the Roof Top of the Said Complex and the same as common facilities of the Said Complex for a period of 2 (two) years from the date of completion of the Said Complex and subsequently, the Association on its formation shall look after the maintenance, management and operation thereof as a common facility. The Promoter shall never in any manner whatsoever be held liable or responsible for the operation, maintenance, safety and security of the Said Power Plant after its installation and handing over of the same to the Facility Manager/Association. 53.4 The Allottee agrees and confirms that the Promoter shall not be liable for any variation in the efficiency of the Said Solar Power Plant. 53.5 The Promoter at its sole discretion shall decide the commencement of operation of the said Solar Power Plant and the Allottee shall never raise any objection or claim towards such commencement of the said Solar Power Plant by the Promoter nor it shall hold the Promoter liable in any manner whatsoever if there is any delay in Commencement of operation of the Solar Panels.

Related to Solar Power Plant

  • Power Factor Design Criteria (Reactive Power A wind generating plant shall maintain a power factor within the range of 0.95 leading to 0.95 lagging, measured at the Point of Interconnection as defined in this LGIA, if the ISO’s System Reliability Impact Study shows that such a requirement is necessary to ensure safety or reliability. The power factor range standards can be met using, for example without limitation, power electronics designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors if agreed to by the Connecting Transmission Owner for the Transmission District to which the wind generating plant will be interconnected, or a combination of the two. The Developer shall not disable power factor equipment while the wind plant is in operation. Wind plants shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Reliability Impact Study shows this to be required for system safety or reliability.

  • Capacity Interconnection Rights Pursuant to and subject to the applicable terms of the Tariff, the Interconnection Customer shall have Capacity Interconnection Rights at the Point(s) of Interconnection specified in this Interconnection Service Agreement in the amount of 33.6

  • One-Way Interconnection Trunks 2.3.1 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Onvoy to Frontier, Onvoy, at Xxxxx’s own expense, shall: 2.3.1.1 provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA; and/or 2.3.1.2 obtain transport for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA (a) from a third party, or, (b) if Frontier offers such transport pursuant to a Frontier access Tariff, from Frontier. 2.3.2 For each Tandem or End Office One-Way Interconnection Trunk group for delivery of traffic from Onvoy to Frontier with a utilization level of less than sixty percent (60%) for final trunk groups and eighty-five percent (85%) for high usage trunk groups, unless the Parties agree otherwise, Onvoy will promptly submit ASRs to disconnect a sufficient number of Interconnection Trunks to attain a utilization level of approximately sixty percent (60%) for all final trunk groups and eighty-five percent (85%) for all high usage trunk groups. In the event Onvoy fails to submit an ASR to disconnect One-Way Interconnection Trunks as required by this Section, Frontier may disconnect the excess Interconnection Trunks or bill (and Onvoy shall pay) for the excess Interconnection Trunks at the rates set forth in the Pricing Attachment. 2.3.3 Where the Parties use One-Way Interconnection Trunks for the delivery of traffic from Frontier to Onvoy, Frontier, at Frontier’s own expense, shall provide its own facilities for delivery of the traffic to the technically feasible Point(s) of Interconnection on Frontier’s network in a LATA.

  • Power System Stabilizers The Developer shall procure, install, maintain and operate Power System Stabilizers in accordance with the requirements identified in the Interconnection Studies conducted for Developer’s Large Generating Facility. NYISO and Connecting Transmission Owner reserve the right to reasonably establish minimum acceptable settings for any installed Power System Stabilizers, subject to the design and operating limitations of the Large Generating Facility. If the Large Generating Facility’s Power System Stabilizers are removed from service or not capable of automatic operation, the Developer shall immediately notify the Connecting Transmission Owner and NYISO. The requirements of this paragraph shall not apply to wind generators.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Interconnection Facilities 4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection Facilities itemized in Attachment 2 of this Agreement. The NYISO, in consultation with the Connecting Transmission Owner, shall provide a best estimate cost, including overheads, for the purchase and construction of its Interconnection Facilities and provide a detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by agreement of the Interconnection Customer, such other entities, the NYISO, and the Connecting Transmission Owner. 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (1) owning, operating, maintaining, repairing, and replacing its own Interconnection Facilities, and

  • Two-Way Interconnection Trunks 2.4.1 Where the Parties have agreed to use Two-Way Interconnection Trunks for the exchange of traffic between Verizon and PCS, PCS shall order from Verizon, and Verizon shall provide, the Two-Way Interconnection Trunks and the Entrance Facility, on which such Trunks will ride, and transport and multiplexing, in accordance with the rates, terms and conditions set forth in this Agreement and Verizon’s applicable Tariffs. 2.4.2 Prior to ordering any Two-Way Interconnection Trunks from Verizon, PCS shall meet with Verizon to conduct a joint planning meeting (“Joint Planning Meeting”). At that Joint Planning Meeting, each Party shall provide to the other Party originating Centium Call Second (Hundred Call Second) information, and the Parties shall mutually agree on the appropriate initial number of Two-Way End Office and Tandem Interconnection Trunks and the interface specifications at the Point of Interconnection (POI). Where the Parties have agreed to convert existing One-Way Interconnection Trunks to Two-Way Interconnection Trunks, at the Joint Planning Meeting, the Parties shall also mutually agree on the conversion process and project intervals for conversion of such One-Way Interconnection Trunks to Two-Way Interconnection Trunks. 2.4.3 Two-Way Interconnection Trunks shall be from a Verizon End Office or Tandem to a mutually agreed upon POI. 2.4.4 On a semi-annual basis, PCS shall submit a good faith forecast to Verizon of the number of End Office and Tandem Two-Way Interconnection Trunks that PCS anticipates Verizon will need to provide during the ensuing two (2) year period to carry traffic from PCS to Verizon and from Verizon to PCS. PCS’s trunk forecasts shall conform to the Verizon CLEC trunk forecasting guidelines as in effect at that time. 2.4.5 The Parties shall meet (telephonically or in person) from time to time, as needed, to review data on End Office and Tandem Two-Way Interconnection Trunks to determine the need for new trunk groups and to plan any necessary changes in the number of Two-Way Interconnection Trunks. 2.4.6 Two-Way Interconnection Trunks shall have SS7 Common Channel Signaling. The Parties agree to utilize B8ZS and Extended Super Frame (ESF) DS1 facilities, where available. 2.4.7 With respect to End Office Two-Way Interconnection Trunks, both Parties shall use an economic Centium Call Second (Hundred Call Second) equal to five (5). 2.4.8 Two-Way Interconnection Trunk groups that connect to a Verizon access Tandem shall be engineered using a design blocking objective of Xxxx-Xxxxxxxxx B.005 during the average time consistent busy hour. Two-Way Interconnection Trunk groups that connect to a Verizon local Tandem shall be engineered using a design blocking objective of Xxxx-Xxxxxxxxx B.01 during the average time consistent busy hour. Verizon and PCS shall engineer Two-Way Interconnection Trunks using BOC Notes on the LEC Networks SR-TSV-002275. 2.4.9 The performance standard for final Two-Way Interconnection Trunk groups shall be that no such Interconnection Trunk group will exceed its design blocking objective (B.005 or B.01, as applicable) for three

  • Plant The expression ‘Plant’ as used in the tender papers shall mean every temporary accessory necessary or considered necessary by the Engineer to execute, construct, complete and maintain the work and all altered, modified, substituted and additional works ordered in the time and the manner herein provided and all temporary materials and special and other articles and appliance of every sort kind and description whatsoever intended or used therefore.

  • As-Builts Seller shall provide final as-built drawings of the Seller-Owned Interconnection Facilities within 30 Days of the successful completion of the Acceptance Test.

  • Network Interconnection Architecture Each Party will plan, design, construct and maintain the facilities within their respective systems as are necessary and proper for the provision of traffic covered by this Agreement. These facilities include but are not limited to, a sufficient number of trunks to the point of interconnection with the tandem company, and sufficient interoffice and interexchange facilities and trunks between its own central offices to adequately handle traffic between all central offices within the service areas at a P.01 grade of service or better. The provisioning and engineering of such services and facilities will comply with generally accepted industry methods and practices, and will observe the rules and regulations of the lawfully established tariffs applicable to the services provided.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!