CONTROL OF THE WORK. A. SUPERVISION OF WORK BY CONTRACTOR
1. Contractor shall supervise and direct the Work competently and efficiently, devoting such attention thereto and applying such personal skills and expertise as may be required and necessary to perform the Work in accordance with the Contract. Contractor shall be solely responsible for the design and means, methods, techniques, sequences and procedures of construction and for the safety precautions and programs incident thereto. The Contractor shall be responsible to see that the completed Work complies with the Contract.
2. Contractor shall keep on the Site at all times during Work progress a competent resident superintendent who shall not be replaced without the express written consent of the County. The superintendent will be Contractor's representative at the Site and shall have complete authority to act on behalf of Contractor. County recognizes that the superintendent does not have contractual or budget authority. All communications to the superintendent shall be as if given to the Contractor.
3. Contractor shall have and maintain a full-time project manager whose duties shall include certifying to the County that the Work has been reviewed and either found to meet the terms and conditions of the Contract or has been found deficient and corrective action will be taken promptly.
B. OBSERVATION OF WORK BY COUNTY The County may observe and monitor the design and construction through its agents, employees, consultants or others. Contractor in no way is relieved of any responsibility by the activities of County in this regard.
C. ACCESS TO SITE During performance of Work, the County and its respective agents, representatives, consultants, and employees may at any time enter upon the Site, shops or offices where any part of Work may be in preparation, or factories where any materials for use in Work are being or are to be manufactured, and Contractor shall provide proper and safe facilities therefor, and shall make arrangements with manufacturers to facilitate inspection of their processes and products to such extent as the County's interests may require. Other contractors performing work for the County may also, for all purposes required by their respective contracts, enter upon the Site. County and Contractor shall agree on procedures for additional insured requirements for other County contractors on the Site.
D. EXISTING UTILITIES Drawings may indicate above and below grade structures, drainage lines, storm drains,...
CONTROL OF THE WORK. The Construction Manager shall have total control of the Work and shall effectively direct and supervise the Work so as to ensure conformity with the Contract Documents.
CONTROL OF THE WORK. The Contractor shall have complete control of the Work and shall effectively direct and supervise the Work so as to ensure conformance with the Contract Documents including the phasing or sequencing requirements for the Work set out in the Contract Documents. During the progress of the Work the Contractor shall endeavour to submit any request for information to the Consultant in a timely manner having regard for the Construction Schedule and to identify in the request for information the timeframe within which a Supplemental Instruction is needed to ensure there is no impact on the Construction Schedule including whether and how the information requested affects the critical path. The Consultant shall respond to requests for information in accordance with GC 2.
CONTROL OF THE WORK. 2.5.8.1 The CM@Risk shall supervise and direct the Work of its employees and Subcontractors and coordinate the Work with the activities and responsibilities of the Owner and the Design Professional so as to complete the Work in accordance with the Owner’s objectives of cost, time and quality as set forth in the Contract Documents.
2.5.8.2 The CM@Risk shall establish an on-site organization with lines of authority to carry out the overall plans for completion of the Work.
2.5.8.3 The CM@Risk shall schedule, notice, conduct, and take and distribute minutes of weekly progress meetings at which the Owner, Design Professional, and CM@Risk can discuss jointly such matters as procedures, progress, and problems.
CONTROL OF THE WORK. The Contractor shall have total control of the Work and shall effectively direct and supervise the Work so as to ensure conformity with the Contract Documents.
CONTROL OF THE WORK. Contractor shall be solely responsible for construction means, methods, techniques, sequences, procedures, safety and security programs in connection with the performance of the Work.
CONTROL OF THE WORK. 3.6.1 The Construction Manager shall supervise and direct the work of its subcontractors and coordinate the Work with the activities and responsibilities of the Principal Representative and the Architect/Engineer to complete the Project in accordance with the Principal Representative's objectives of cost, time and quality.
3.6.2 The Construction Manger shall establish on-site organization and lines of authority in order to carry out the overall plans of the Construction Team.
3.6.3 The Construction Manager shall schedule and conduct weekly progress meetings at which the Principal Representative, Architect/Engineer, and Construction Manager can discuss jointly such matters as procedures, progress, and problems.
CONTROL OF THE WORK is added as follows:
CONTROL OF THE WORK. Contractor shall be solely responsible, subject to review and consultation with GEC, for construction means, methods, techniques, sequences, procedures, safety and security programs in connection with the performance of the Work. LIMA/GEC/EPC 14 Confidential Business Information
CONTROL OF THE WORK. Refer to paragraph 3.1.2: