Easements and Permits Sample Clauses

Easements and Permits. HPL or its designee shall obtain all clearances, permits, licenses, authorizations, easements and other land rights that may be needed for the construction, installation, maintenance, and operation of the HPL Facilities, HPL Operated Facilities and the TGPL Facilities. The Parties and/or their designees shall have access to each other's facilities at all reasonable times.
AutoNDA by SimpleDocs
Easements and Permits. If necessary, prior to the installation of the Interconnection Facilities, Consumers will acquire required permits and necessary easements for its Interconnection Facilities. These easements / permits may include, but shall not be limited to, rights of ingress and egress, rights to clear trees, and all necessary rights-of-way for installation and maintenance of Interconnection Facilities. The Project Developer shall reimburse Consumers for the costs and expenses Consumers incurs in acquiring such easements / permits.
Easements and Permits. Tetra Tech will assist the City in obtaining the required easements and permits for the project. If any easements are required Tetra Tech will provide legal descriptions for the City’s use in obtaining temporary and permanent easements required for the proposed work. The easement legal descriptions will also be confirmed after construction to make sure they remain accurate and adequate for the completed infrastructure. Tetra Tech will lead the permitting process and will be responsible for preparation, submittal (under East Lansing signature), and successful negotiation of the required permits. The primary agency from whom approvals will be required will be the MDEQ. We recommend reviewing the project with MDEQ during Task I to identify early on what their primary concerns and constraints will be. Once the Basis of Design is available as a draft document, we will review it with the key permitting agencies. This project will likely require two types of permits from MDEQ, including the Part 41 permit for construction of wastewater system improvements, and a Part 31/301/303 permit for work in riverine floodplain/wetland areas. Typically, MDEQ requires either the floodplain or wetland permit for any given project and covers all necessary issues in the single permit. The proposed site for the new facility may impact higher elevations of the 100-year floodplain. This permit should be relatively easy to secure, with estimated fill quantities minimal with some land available at this elevation for potential compensating excavation. No wetlands are documented in the WRRF site area. Any clearing or temporary access construction activities will required documentation examination by MDEQ during application review. In addition, site clearing activities will require an endangered species review. The potential for Indiana Bat habitat will be considered. Selective scheduling of site clearing may be needed to mitigate potential habitat impacts. We will assess the wetland and habitat impacts early in the design process and follow up during permitting and construction. We will be actively engaged during the bidding process and will provide final bidding documents for the project. We will assist City staff with the bidding process including the development of the advertisement for bids. We will distribute bid documents as required to all potential bidders using electronic media for plan distribution. Tetra Tech will lead the pre-bid meeting with contractors to review project r...
Easements and Permits. The Borrower shall submit to the Government, when required by the Administrator, evidence satisfactory to the Administrator that the Borrower has obtained such easements from landowners and releases from lienors and such franchises, authorizations, permits, licenses, certificates of public convenience and necessity, approvals, and orders from public bodies and others, as the Administrator shall deem necessary or advisable in connection with the Project or the Loan. If required so to do by the Administrator, the Borrower shall cause such easements and releases to be recorded in appropriate offices of record. Except with the consent of the Administrator, none of the funds advanced on account of the Loan and none of the equity funds shall be used by the Borrower to pay for easements obtained from landowners, or for releases of liens affecting easements.
Easements and Permits. The Borrower shall submit to the Government, when requested by the Administrator, evidence satisfactory to the Administrator that the Borrower has obtained such easements from landowners and releases from lienor and such franchises, authorizations, permits, licenses, certificates of convenience and necessity, approvals, and orders from public bodies and others, reasonably adequate in form and substance, as may be required by law for the construction of the Project and the operation of the System. If requested so to do by the Administrator, the Borrower shall cause such easements and releases to be recorded in appropriate offices of record. Except with the consent of the Administrator, none of the funds advanced on account of the Loan shall be used by the Borrower to pay for easements obtained from landowners, or for releases of liens affecting easements.
Easements and Permits. BVP shall obtain, at their sole cost and expense all clearances, permits, licenses, authorizations, easements and other land rights that may be needed for the construction, installation, maintenance, and operation of the BVP Facilities, the HPL Operated Facilities and the HPL Facilities. The Parties and/or their designees shall have access to each other's facilities at all reasonable times.
Easements and Permits. Consumers shall prepare an easement agreement for all Consumers’ facilities which will be located on the Customer’s premises. The Customer shall execute such easement agreement prior to the start of construction by Consumers. In the event the Extraordinary Facilities include electric facilities not located on the Customer’s premises, the Customer shall be responsible for Consumers’ cost to obtain the necessary easements and / or permits from third parties for installation of such required facilities.
AutoNDA by SimpleDocs
Easements and Permits. HPL shall obtain, at their sole cost and expense, all clearances, permits, licenses, authorizations, easements and other land rights that may be needed for the construction, installation, maintenance, and operation of the Interconnect.
Easements and Permits. BPE shall obtain, at their sole cost and expense all clearances, permits, licenses, authorizations, easements and other land rights that may be needed for the construction, installation, maintenance, and operation of the BPE Facilities. HPL shall obtain, and BPE shall reimburse HPL for all direct and indirect costs associated with all clearances, permits, licenses, authorizations, easements and other land rights that may be needed for the construction, installation, maintenance, and operation of the HPL Facilities and HPL Operated Facilities. The Parties and/or their designees shall have access to each other's facilities at all reasonable times.
Easements and Permits. 1. The County may provide an additional easement or temporary easement when the City determines that the existing easement is insufficient for requested maintenance work. 2. The County will obtain any necessary permits required to perform Roadway Facility Maintenance