Recovery Plans Sample Clauses

Recovery Plans. In the event of any schedule delays in respect of construction milestones or the substantial completion date, Purchaser shall be advised of (as applicable) any recovery plans and shall be invited to attend meetings between Seller and its suppliers and contractors in respect thereof; provided, however, neither Seller, its suppliers nor its contractors shall be obligated to implement any recommendations of Purchaser in respect of any such recovery plans.
AutoNDA by SimpleDocs
Recovery Plans. For as long as Services are provided hereunder, PICO shall, and shall cause its relevant Affiliates to, maintain backup, business continuation and disaster recovery plans, procedures and policies (collectively, “Recovery Plans”) consistent with past practices as they existed during the twelve (12) months immediately preceding the Offering. PICO shall provide UCP:
Recovery Plans. If the Monthly Progress Report shows that the Substantial Completion is projected to occur ninety (90) days later than the then-current Guaranteed Substantial Completion Date, Contractor will submit a written schedule recovery plan for Concessionaire’s Review concurrent with the next monthly Project Schedule update. Such recovery schedule shall (i) include a list of all activities changed, added or deleted along with all logic changes and an accompanying narrative explaining the nature of the changes as required by Section 1.4.6(A) of the Technical Requirements and (ii) set forth a revised Project Schedule that shall be subject to Concessionaire’s Approval for which projected Substantial Completion shall not, subject to Section 6.6.5, be later than 365 days after the Guaranteed Substantial Completion Date. Contractor shall respond to Concessionaire’s comments in accordance with the process outlined in Section 2.1.1.2 until Concessionaire and the Department have approved the revised Project Schedule. Concessionaire’s Review of a recovery plan and Concessionaire’s Approval of a revised Project Schedule shall not affect any of Concessionaire’s rights or Contractor’s obligations under this Agreement, including Contractor’s obligations to pay Late Completion Payments. Once a revised Project Schedule is reviewed and approved by Concessionaire hereunder and the Department under the Comprehensive Agreement, it shall become the Project Schedule and be used as the basis for subsequent Monthly Progress Reports.
Recovery Plans. The Guaranteed Maximum Price is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Project Schedule requirements. In the event it is necessary for Contractor or any Subcontractor to work additional overtime in order to maintain the Project Schedule, for reasons caused by or attributable to the Contractor, Contractor shall be responsible for all costs relating to such overtime, though Contractor shall have the right to use the Construction Contingency in accordance with Section 3.1.6 hereof. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Interim Milestones by the respective Interim Milestone Dates; or (b) obtain Substantial Completion of the Work in its entirety within the Contract Time.
Recovery Plans. The Guaranteed Maximum Price is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Project Schedule requirements. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Interim Milestones by the respective Interim Milestone Dates; or (b) obtain Substantial Completion within the Contract Time.
Recovery Plans. The Original Project Guaranteed Maximum Price or Expansion Project Guaranteed Maximum Price (as applicable) is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Original Project Schedule and Expansion Project Schedule requirements. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Original Project Interim Milestones or Expansion Project Interim Milestones by the respective Original Project Interim Milestone Dates or Expansion Project Interim Milestone Dates; or (b) obtain Original Project Substantial Completion or Expansion Project Substantial Completion (as applicable) within the applicable Contract Time.
Recovery Plans. If progress of the Redevelopment Work falls materially behind schedule and the Chief Real Estate Officer reasonably determines that Lessee is in jeopardy of not achieving the CO Date on or before the Required Construction Completion Date, then County may issue a written notice (each a “Recovery Plan Notice”) to Lessee identifying areas of concern and requiring that Lessee provide a Recovery Plan detailing the measures to be implemented by Lessee in order to recover any lost time in the Construction Schedule. Lessee shall, within fifteen (15) days after receipt of a Recovery Plan Notice, provide a Recovery Plan to County. Within thirty (30) days after County’s receipt of a Recovery Plan from Lessee, County shall instruct Lessee in writing whether or not to proceed with the Recovery Plan as submitted, or in accordance with reasonable revisions thereto required by County (a “Construction Change Directive”). Upon Lessee’s receipt of the Construction Change Directive, Lessee shall instruct its contractors to implement the Recovery Plan as soon as reasonably possible and any additional costs associated with implementation of the Recovery Plan shall be borne by Lessee. Lessee’s failure (a) to provide a Recovery Plan within the time requirements provided for in this Subsection 5.7.3, or (b) to implement immediately a Recovery Plan upon receipt of a Construction Change Directive to do so, shall each be a material breach of this Agreement.‌
AutoNDA by SimpleDocs
Recovery Plans. (11) 23BIn the event of a Disaster, establish and maintain connectivity for County Locations, from Supplier sites to County Locations, and between County Locations to deliver the Services in accordance with the County’s Disaster Recovery Plans.

Related to Recovery Plans

  • Disaster Recovery Plan Contractor agrees that upon request of System Agency, Contractor shall provide copies of its most recent business continuity and disaster recovery plans.

  • Development Plans 4.3.1 For each Licensed Indication and corresponding Licensed Product in the Field, Licensee will prepare and deliver to Licensor a development plan and budget (each a “Development Plan”). The initial Development Plans for each Licensed Indication will be delivered within […***…] after the Grant Date for such Licensed Indication.

  • Force Majeure and Disaster Recovery Plans A. DST shall not be responsible or liable for its failure or delay in performance of its obligations under this Agreement arising out of or caused, directly or indirectly, by circumstances beyond its reasonable control, including, without limitation: any interruption, loss or malfunction of any utility, transportation, computer (hardware or software) or communication service; inability to obtain labor, material, equipment or transportation, or a delay in mails; governmental or exchange action, statute, ordinance, rulings, regulations or direction; war, strike, riot, emergency, civil disturbance, terrorism, vandalism, explosions, labor disputes, freezes, floods, fires, tornados, acts of God or public enemy, revolutions, or insurrection; or any other cause, contingency, circumstance or delay not subject to DST’s reasonable control which prevents or hinders DST’s performance hereunder.

  • Work Plans Tenant shall prepare and submit to Landlord for approval schematics covering the Tenant Improvements prepared in conformity with the applicable provisions of this Work Letter (the “Draft Schematic Plans”). The Draft Schematic Plans shall contain sufficient information and detail to accurately describe the proposed design to Landlord and such other information as Landlord may reasonably request. Landlord shall notify Tenant in writing within ten (10) business days after receipt of the Draft Schematic Plans whether Landlord approves or objects to the Draft Schematic Plans and of the manner, if any, in which the Draft Schematic Plans are unacceptable. Landlord’s failure to respond within such ten (10) business day period shall be deemed approval by Landlord. If Landlord reasonably objects to the Draft Schematic Plans, then Tenant shall revise the Draft Schematic Plans and cause Landlord’s objections to be remedied in the revised Draft Schematic Plans. Tenant shall then resubmit the revised Draft Schematic Plans to Landlord for approval, such approval not to be unreasonably withheld, conditioned or delayed. Landlord’s approval of or objection to revised Draft Schematic Plans and Tenant’s correction of the same shall be in accordance with this Section until Landlord has approved the Draft Schematic Plans in writing or been deemed to have approved them. The iteration of the Draft Schematic Plans that is approved or deemed approved by Landlord without objection shall be referred to herein as the “Approved Schematic Plans.”

  • Marketing Plans Contractor and the Exchange recognize that Enrollees and other health care consumers benefit from efforts relating to outreach activities designed to increase heath awareness and encourage enrollment. The parties shall share marketing plans on an annual basis and with respect to periodic updates of material changes. The marketing plans of the Exchange and Contractor shall include proposed and actual marketing approaches, messaging and channels and provide samples of any planned marketing materials and related collateral as well as planned, and when completed, expenses for the marketing budget. The Contractor shall include this information for both the Exchange and the outside individual market. The Exchange shall treat all marketing information provided under this Section as confidential information consistent with Section 1.4.1. The obligation of the Exchange to maintain confidentiality of this information shall survive termination or expiration of this Agreement.

  • Disaster Recovery and Business Continuity The Parties shall comply with the provisions of Schedule 5 (Disaster Recovery and Business Continuity).

  • Commercialization Plans As soon as practicable after formation of the JCC (following Acucela’s exercise of an Opt-In Right under Section 3.1), the JCC shall prepare and approve the initial Commercialization Plan for Commercialization of the Licensed Product for the Initial Indication in the Initial Formulation (and, if applicable, any New Formulation or Other Indication Product) in the Territory. The Parties shall use Commercially Reasonable Efforts to ensure that such initial Commercialization Plan for Commercialization of the Licensed Product for the Initial Indication in the Initial Formulation is consistent with the general Commercialization Plan outline set forth in Exhibit C attached hereto and incorporated herein (the “General Commercialization Plan Outline”). The JCC shall prepare and approve a separate Commercialization Plan for Commercialization of Licensed Product for the Initial Indication in the Initial Formulation in the Territory and for Commercialization of each Other Indication Product and New Formulation (if any) in the Territory, and shall update and amend each Commercialization Plan not less than annually or more frequently as needed to take into account changed circumstances or completion, commencement or cessation of Commercialization activities not contemplated by the then-current Commercialization Plan. Amendments and revisions to the Commercialization Plan shall be reviewed and discussed, in advance, by the JCC, and Otsuka agrees to consider proposals and suggestions made by Acucela regarding amendments and revisions to the Commercialization Plan. Any amendment or revision to the Commercialization Plan that provides for an increase or decrease in the number of FTEs for any Phase 3b Clinical Trials or Post-Approval Studies as compared to the previous version of the Commercialization Plan, or that provides for addition or discontinuation of tasks or activities as compared to the previous version of the Commercialization Plan, or that moves forward the timetable for activities reflected in the Commercialization Plan, shall provide for a reasonable ramp-up or wind-down period, as applicable, to accommodate a smooth and orderly transition of Commercialization activities to the amended or revised Commercialization Plan. Each Commercialization Plan shall identify the goals of Commercialization contemplated thereunder and shall address Commercialization (including Co-Promotion) activities related to the Licensed Product (including, if applicable, any Other Indication Product), including:

  • Business Plans The Approved Full-Term Operating Business -------------- Plan and Approved Annual Operating Business Plan, if any, have been prepared in all material respects in accordance with GAAP (except for the treatment of Indebtedness owing to the FCC, which has been reflected in such plans at historical cost).

  • Development Plan document specifying the work program, schedule, and relevant investments required for the Development and the Production of a Discovery or set of Discoveries of Oil and Gas in the Contract Area, including its abandonment.

  • Research Plans The Research Plan for the [***] Designated Target is attached as Schedule 2.2.3-1. Subsequent Research Plans agreed upon in accordance with Section 2.4.2.4 will be attached as additional sequentially numbered schedules (Schedule 2.2.3-2, Schedule 2.2.3-3, etc.).

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!