Start-Up, Commissioning & Supplier Commissioning Work; Access Days Sample Clauses

Start-Up, Commissioning & Supplier Commissioning Work; Access Days. (a) After the Mechanical Completion Date, Owner’s operating personnel shall, under the EPC Contractor’s observation, direction and supervision (along with the technical advice of Supplier), commence the initial operation of the Facility (i.e., the start-up and commissioning of the Facility), and shall, under the EPC Contractor’s observation, direction and supervision (along with the technical advice of Supplier), continue with such operation during the performance of the Performance Test. (b) Supplier shall properly complete the Supplier Commissioning Work within the Access Period. Supplier acknowledges, understands and agrees that the EPC Contractor will be performing those services and activities referenced in Section 5.2(a) at the same time that Supplier will be performing the Supplier Commissioning Work and Supplier shall account for such simultaneous activities in its planning for the performance of the Supplier Commissioning Work. Notwithstanding the foregoing, in the event Supplier is unable to perform the Supplier Commissioning Work on any portion of any Access Day solely by reason of interference caused by the EPC Contractor’s start-up and commissioning of any part of the Facility, including but not limited to steam chemistry cleanup, outages for screen removal, screen cleaning and water wash, testing and setting of relief and safety valves, balance of plant and Facility-wide functional testing, performance testing and reliability testing, then if such inability would invalidate or materially reduce the efficacy of the Supplier Commissioning Work otherwise performed on such Access Day, then such day shall not count as an Access Day (or, if such inability does not invalidate or materially reduce the efficacy of the Supplier Commissioning Work otherwise performed on such Access Day, then only the portion of such day to which the interference relates shall not be credited as an Access Day and Supplier shall be entitled to use such portion on another day within the Access Period) (but only if Supplier notifies Owner in writing of any such interference within twenty-four (24) hours of such occurrence and Owner, acting reasonably, concurs with Supplier’s claim). (c) During the Access Period, Owner shall ensure the following to the extent necessary for Supplier to perform the Supplier Commissioning Work: (i) The continuous availability of all fuels, lubricants, operating supplies and electrical backfeed; (ii) Owner’s operating personnel (provided Supplie...
AutoNDA by SimpleDocs

Related to Start-Up, Commissioning & Supplier Commissioning Work; Access Days

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.

  • 190 Contract Complete This contract is the final expression of the Parties' agreement. There are no understandings, agreements, or representations, expressed or implied, which are not specified in this contract.

  • Milestone Schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.