Approval of Final Payment Sample Clauses

Approval of Final Payment. If, on the basis of its observations and review of the Work during construction, its final inspection and its review of the final Estimate and Requisition for Payment, all as required by the Contract Documents, the AE is satisfied that the Work has been completed and the CM has fulfilled all of his obligations under the Contract Documents, it will, within ten (10) calendar days after receipt of the final Application for Payment, indicate in writing its approval of payment and deliver the application to the Owner. Otherwise, it will return the Application to the CM, indicating in writing its reason for refusing to approve final payment, in which case the CM will make the necessary corrections and resubmit the Application. The Owner will, within fifteen (15) calendar days after receipt of approved application for final payment, either indicate their approval of the estimate and requisition application for payment and within fifteen (15) calendar days pay the CM the amount approved by the Owner and issue a Certificate of Final Completion or return the application through the AE indicating in writing the reason for refusing to approve payment. In the latter case, the CM may make the necessary corrections and resubmit the application to the AE. If, after substantial Completion of the Work, final completion is materially delayed through no fault of the CM, and the AE so confirms, the Owner shall and without terminating the Agreement, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Agreement, and if bonds have been furnished, the written consent of the Surety to the payment of the balance due for that portion of the Work fully completed and accepted, shall be submitted by the CM to the AE, prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. If liquidated damages are to be deducted from the final payment, the Owner shall so notify the CM in writing at least ten (10) calendar days prior to the Owner's submittal to Finance. The CM will be required to submit with his final payment documents a DBE Participation Certification, indicating all DBE subcontractor(s) and amount(s) utilized for the PROJECT. At the final completion of the construction PROJECT the Owner's Project Manager will prepare...
AutoNDA by SimpleDocs
Approval of Final Payment. 14.10.1 If, on the basis of their observation and review of the Work during construction, their final inspection, and review of the Application for Final Payment, and as required by the Contract Documents, CEI or A/E and County are satisfied that the Work has been completed and Contractor has fulfilled all of its obligations under the Contract Documents, CEI or A/E will, within twenty (20) days after receipt of the Application for Final Payment, indicate recommendation for payment and present the Application for Final Payment to County for payment. Thereupon, CEI or A/E will give written notice to County and Contractor that the Work is acceptable subject to the provision of Section 14.11. Otherwise, it will return the application to Contractor, indicating in writing its reasons for refusing to approve Final Payment, in which case Contractor shall make the necessary corrections and resubmit the application. County shall, within ten (10) days of presentation to it of an approved Application for Final Payment, make arrangements to promptly pay Contractor the amount recommended by CEI or A/E.
Approval of Final Payment. RMWD will, within ten (10) work days after the Contractor has fulfilled and satisfied all the requirements of Paragraph 20.8, indicate in writing his approval of payment or will return the application to the Contractor, indicating in writing his reasons for refusing to approve final payment, in which case the Contractor shall make the necessary corrections and resubmit the application. RMWD, within the time period stated in the Supplementary Conditions, Section 00800, will pay the Contractor the amount so approved unless a longer period of time is prescribed by law or required for the lawful filing and publishing of Notices of Completion and the expiration of any lien periods thereof. (See Supplementary Conditions, Section 00800)
Approval of Final Payment. If, on the basis of the County Project Manager’s observation and review of Consultant’s Work or Services performed during the Task Assignment, final inspection and review of the final application for payment and the County Project Manager’s satisfaction that the work has been completed and Consultant has fulfilled all of its obligations under the Contract Documents, County Project Manager, after receipt of the final application for payment, indicate in writing his or her approval of payment and present the application to Accounts Payable for payment. Otherwise, the County Project Manager shall return the application to the Consultant, indicating in writing the reasons for refusing to approve final payment, in which case the Consultant will make the necessary corrections and resubmit the application.
Approval of Final Payment. If, on the basis of its observations and review of the Work during construction, its final inspection and its review of the final application for payment (all as required by the Contract Documents), the Library’s Project Manager is satisfied that the Work has been completed and the XXXX has fulfilled all of his obligations under the Contract Documents, it will, within twenty (20) business days after receipt of the final application for payment, indicate in writing its approval of payment. Otherwise, it will return the Application to the XXXX, indicating in writing its reason for refusing to approve final payment, in which case the XXXX will make the necessary corrections and re-submit the Application. The Library will, in accordance with the Local Government Prompt Payment Act, pay the XXXX the amount approved by the Library and issue a Certificate of Final Completion. If after Substantial Completion of the Work, Final Completion is materially delayed through no fault of the XXXX, and the Library’s Project Manager so confirms, the Library shall, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract, the written consent of the Surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the XXXX to the Library’s Project Manager prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims.
Approval of Final Payment. (a) If, on the basis of its observation and review of the Work during construction, its final inspection and its review of the final application for payment, all as required by the Agreement, City and Program Manager are satisfied that the Work has been completed, and Contractor has fulfilled all of its obligations under the Agreement, the City will, within ten (10) days after receipt of the final application for payment, indicate in writing its approval of payment and process the application for payment. Otherwise, the City will return the application to Contractor, indicating in writing its reasons for refusing to approve final payment, in which case Contractor will make the necessary corrections and resubmit the application. City will, within ten (10) days of presentation to it of an approved final application for payment, pay Contractor the amount approved.
Approval of Final Payment. If, on the basis of its observations and review of the Work during construction, its final inspection and its review of the final Estimate and Requisition for Payment, all as required by the Contract Documents, the AE is satisfied that the Work has been completed and the CM has fulfilled all of his obligations under the Contract Documents, it will, within ten
AutoNDA by SimpleDocs
Approval of Final Payment. A. If, on the basis of their observation and review of the Work during construction, their final inspection and review of the final Application for Payment, all as required by the Contract Documents, Engineer and CITY are satisfied that the Work has been completed and CONTRACTOR has fulfilled all of its obligations under the Contract Documents, Engineer will, within twenty (20) days after receipt of the final Application for Payment, indicate recommendation for payment and present the Application for Final Payment to CITY for payment. Thereupon, Engineer will give written notice to CITY and CONTRACTOR that the Work is acceptable subject to the provisions of Article 12 Paragraph 8. Otherwise, it will return the Application to CONTRACTOR, indicating in writing its reasons for refusing to approve final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application. CITY shall, within ten (10) days of presentation to it of an approved final Application for Payment, make arrangements to promptly pay CONTRACTOR the amount recommended by Engineer.
Approval of Final Payment. Following acceptance of the Work, District shall authorize final payment to Contractor of the undisputed sums found due, subject to retentions for stop notices as provided in Section 21.07 hereof. This final Tenant Improvement Payment shall be made within thirty (30) days after completion, as defined in Section 21.05 hereof, and recordation of the Notice of Completion.

Related to Approval of Final Payment

  • Approval of Plans Landlord will not check Tenant drawings for building code compliance. Approval of the Final Plans by Landlord is not a representation that the drawings are in compliance with the requirements of governing authorities, and it shall be Tenant’s responsibility to meet and comply with all federal, state, and local code requirements. Approval of the Final Plans does not constitute assumption of responsibility by Landlord or its architect for their accuracy, sufficiency or efficiency, and Tenant shall be solely responsible for such matters.

  • Approval of Leave Any leave of absence will be submitted to the Company for approval in writing. No approved leave of absence will affect any employee’s seniority rights when used for the purpose granted and providing the employee returns to work at the expiration of his/her leave.

  • Certification Regarding Prohibition of Boycotting Israel (Tex Gov. Code 2271) If (a) Vendor is not a sole proprietorship; (b) Vendor has ten (10) or more full-time employees; and (c) this Agreement or any agreement with a TIPS Member under this procurement has value of $100,000 or more, the following certification shall apply; otherwise, this certification is not required. Vendor certifies, where applicable, that neither the Vendor, nor any affiliate, subsidiary, or parent company of Vendor, if any, boycotts Israel, and Vendor agrees that Vendor and Vendor Companies will not boycott Israel during the term of this Agreement. For purposes of this Agreement, the term “boycott” shall mean and include refusing to deal with, terminating business activities with, or otherwise taking any action that is intended to penalize, inflict economic harm on, or limit commercial relations with Israel, or with a person or entity doing business in Israel or in an Israeli-controlled territory but does not include an action made for ordinary business purposes. When applicable, does Vendor certify? Yes

  • Approval Process Tenant shall notify Landlord whether it approves of the submitted working drawings within three business days after Landlord’s submission thereof. If Tenant disapproves of such working drawings, then Tenant shall notify Landlord thereof specifying in reasonable detail the reasons for such disapproval, in which case Landlord shall, within five business days after such notice, revise such working drawings in accordance with Tenant’s objections and submit the revised working drawings to Tenant for its review and approval. Tenant shall notify Landlord in writing whether it approves of the resubmitted working drawings within one business day after its receipt thereof. This process shall be repeated until the working drawings have been finally approved by Landlord and Tenant. If Tenant fails to notify Landlord that it disapproves of the initial working drawings within three business days (or, in the case of resubmitted working drawings, within one business day) after the submission thereof, then Tenant shall be deemed to have approved the working drawings in question. Any delay caused by Tenant’s unreasonable withholding of its consent or delay in giving its written approval as to such working drawings shall constitute a Tenant Delay Day (defined below). If the working drawings are not fully approved (or deemed approved) by both Landlord and Tenant by the 15th business day after the delivery of the initial draft thereof to Tenant, then each day after such time period that such working drawings are not fully approved (or deemed approved) by both Landlord and Tenant shall constitute a Tenant Delay Day.