Construction Report. Monthly Project Progress Report APPENDIX 7 TESTING PROTOCOLS INITIAL COMMERCIAL OPERATION and CONTRACT CAPACITY & ANCILLARY SERVICE TESTS
Construction Report. A Construction Report in the form contemplated in Section 8.19 and dated as of the Closing Date.
Construction Report. Devco shall have delivered to Spring Lane a construction report explaining the reason for the cost overruns, including copies of any change orders made under the EPC Agreement, and evidence reasonably satisfactory to Spring Lane that demonstrates that the Project is capable of achieving Completion in accordance with the Project Schedule, the EPC Agreement, and the Financing Documents.
Construction Report. For each and every Recreational Improvement (and material alteration or addition thereto) undertaken by Lessee on the Premises, Lessee shall prepare and deliver a construction report. This report shall contain the following elements: (1) type of Recreational Improvement constructed or altered; (2) floor area or capacity of Recreational Improvement constructed or altered; (3) total cost of construction or alteration; (4) completion date for construction or alteration; and (5) a copy of the certificate of occupancy (as applicable). The construction report shall be delivered to the LAWA Designee at the address provided in Section 15.1 of this Lease not later than sixty (60) days following completion of the Recreational Improvement.
Construction Report. If, as of the last day of each fiscal quarter ending on or prior to the Covenant Changeover Date, the cumulative Capital Expenditures actually made by the Borrower and the Restricted Subsidiaries for the Subject Project through and including such date are less than 70% of the budgeted cumulative Capital Expenditures for the Subject Project as of such date (as set forth in the most recently delivered Budget hereunder), then upon the Administrative Agent’s written request, the Borrower shall deliver, within sixty (60) days of such request, a report of an independent engineering firm or construction consultant reasonably acceptable to the Administrative Agent with respect to the Subject Project, which report shall be in form and substance reasonably satisfactory to the Administrative Agent and shall include a cost and valuation analysis with respect to the construction of the Subject Project.
Construction Report. The Administrative Agent shall have received (i) the most recent monthly Construction Report contemplated by Section 8.19, and (ii) the certificate of an Authorized Officer of the Borrower, both in the form contemplated in Section 8.19 and dated within fifteen (15) days prior to the proposed borrowing date.
Construction Report. Owner shall, upon the written request by Customer, at any time and from time to time prior to the In-Service Date of each Additional Project, provide to Customer a written report setting forth details of the progress of construction and completion of the Additional Projects. Owner shall notify Customer in writing of the projected In-Service Date of each Additional Project sixty (60) calendar days prior thereto. Owner also shall promptly advise Customer of any material developments related to the construction and completion of the Additional Projects, including any delays that may delay the anticipated In-Service Date with respect to any Additional Project. Owner shall use commercially reasonable efforts to comply with any reasonable request made by Customer in connection with the construction of the Additional Projects. 3
Construction Report. The Agent shall have received the Construction Reports contemplated in Section 8.19 substantially in the form of Exhibit G, which are due on or before the date of the Notice of Borrowing.
Construction Report. (a) The Borrower shall deliver to the Agent, the Technical Bank and the Lenders’ Technical Advisor, within thirty (30) days following the end of each month, beginning with the first complete month following the Original Agreement Date until the Project Commercial Operation Date, a Construction Report signed by an authorised signatory summarising the construction and commissioning activities (if applicable) that were carried out in relation to the Project during such period, including a description of:
(i) the construction and other work carried out in relation to the Project during such period;
(ii) a comparison between the actualstate of construction of the Project with the schedule therefor, together with an explanation for any material differences between the progress achieved and the progress forecast in the preceding report in respect of activities, including, but not limited to, engineering and design, procurement and manufacturing, construction, commissioning and start-up and milestone and invoicing status;
(iii) (A) the cumulative Project Costs incurred as at the end of such period and a comparison against the most recent Project Budget; (B) the Borrower’s estimates of the remaining Project Costs (irrespective of whether or not included in the Project Budget) required to achieve the Project Commercial Operation Date; and (C) details of any Available Funds;
(iv) a current forecast of the likely date of each Module Commercial Operation Date and the Project Commercial Operation Date and a confirmation as to the Project’s ability to meet each Expected MCOD;
(v) the performance of the Project during such period (where applicable);
(vi) details of any matters which are likely to materially and adversely affect the construction of the Project;
(vii) details of any event of force majeure under any Project Document which has occurred and details of any mitigation undertaken by the Borrower or the relevant Major Project Party;
(viii) details of any material variations to the design of a Module;
(ix) the amount of any Early Generation Revenues received and transferred on a monthly basis into the Early Generation Debt Account in accordance with clause 11.1 (Payments into the Early Generation Debt Account) of the Cash and Accounts Management Agreement; and
(x) such other information concerning the construction of the Project as may reasonably be requested by the Lenders’ Technical Advisor.
(b) The Borrower shall procure, prior to the Project Commercial Operatio...