Construction Schedule and Construction Operations Phasing Plan Sample Clauses

Construction Schedule and Construction Operations Phasing Plan. If the preceding box is checked, the ESCO will, within days after the Date of Commencement prepare and submit the Construction Schedule and Construction Operations Phasing Plan, prepared in form and substance reasonably acceptable to or as specifically prescribed by the Customer. If the preceding box is checked, the Construction Schedule and Construction Operations Phasing Plan are included as attachments to Schedule A: Project Description. The Construction Schedule shall be updated by the ESCO and submitted to the Customer at least monthly and, if requested by the Customer, in electronic format. The ESCO shall submit a revised Construction Schedule when the ESCO's planned sequence is changed or when Project changes are made that affect the Construction Schedule. Any changes to the Construction Schedule and Construction Operations Phasing Plan are subject to review and approval by the Customer. When performing the Work, the ESCO shall comply with the Construction Operations Phasing Plan and the Construction Schedule.
AutoNDA by SimpleDocs
Construction Schedule and Construction Operations Phasing Plan. The ESCO will, within thirty (30) days after the Date of Commencement prepare and submit the Construction Schedule and Construction Operations Phasing Plan, prepared in form and substance reasonably acceptable to or as specifically prescribed by the Customer. The Construction Schedule shall be updated by the ESCO and submitted to the Customer at least monthly and, if requested by the Customer, in MS Project format. The ESCO shall submit a revised Construction Schedule when the ESCO's planned sequence is changed or when Project changes are made that affect the Construction Schedule. Any changes to the Construction Schedule and Construction Operations Phasing Plan are subject to review and approval by the Customer. When performing the Work, the ESCO shall comply with the Construction Operations Phasing Plan and the Construction Schedule and all Building Rules and Regulations, including any modifications or additions to the Building Rules and Regulations that are generally applicable to all contractors performing work at the Site. If the Customer determines through reasonable evidence that the performance of the Work is behind schedule such that the ESCO will be unable to achieve Substantial Completion in accordance with the Construction Schedule, the Customer shall have the right, but no obligation, to order the ESCO in writing to take corrective measures necessary to expedite the progress of construction, including, without limitation. (i) working additional shifts or overtime, (ii) supplying additional manpower, equipment, and facilities and (iii) other similar measures (collectively "Extraordinary Measures"). The determination of whether the progress of the Work is behind schedule shall take into account any extensions in time to which the ESCO is entitled under Section 9.2 herein. The Customer is hereby permitted to continue use of Extraordinary Measures until the progress of the Work complies with the stage of completion required by the Contract Documents. The Customer's right to require Extraordinary Measures is solely for the purpose of ensuring the ESCO's achievement of Substantial Completion in accordance with the Construction Schedule. In no event shall the Customer have control over, charge of, or any responsibility for construction means, methods, techniques, sequences or procedures or for safety precautions and programs in connection with the Work, notwithstanding the rights and authority granted in this Section or elsewhere in the Contract Docu...

Related to Construction Schedule and Construction Operations Phasing Plan

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Project Construction Budget The project construction cost allowance specifically stated in writing as the ‘revised’ or ‘current’ ‘Project Construction Budget’ by the Trustees at each applicable phase of plan development.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.

  • General Project Description 2. Substation location.

  • Coordination of Design and Construction Contract Documents 5.5.1 Review model(s), Drawings, Specifications and other Construction Documents as they are developed by A/E during the Schematic Design, Design Development, and Construction Documents design phases of the Project.

  • BUILDER’S RISK FOR CONSTRUCTION RENOVATION PROJECTS If the project is CONSTRUCTION RENOVATION of an existing structure, and the State has already determined that Contractor will not be obligated to obtain and maintain Builder’s Risk insurance, then the following provisions apply:

  • ADDITIONAL CONSTRUCTIONS The Promoter undertakes that it has no right to make additions or to put up additional structure(s) anywhere in the Project after the building plan has been approved by the competent authority(ies) except for as provided in the Act.

  • BUILDER’S RISK FOR NEW CONSTRUCTION PROJECTS If the project is NEW CONSTRUCTION, then the following provisions apply:

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!