Construction Timeline. Project Construction is anticipated to start in September 2013 and complete in December 2014. The proposed construction schedule details early completion of the DPAC amenities by September 2014, for use starting with the 2014-15 DPAC Broadway season. Use of the completed DPAC amenities will require partial certificate of occupancy as the construction of the DPAC amenities is part of the construction of the overall project. Project Construction will require close coordination with DPAC to ensure ingress/egress and operations are not impacted. Logistics and communications plans have been developed to address these issues prior and during the project construction. The DPAC amenities will coordinate with the existing DPAC in terms of transitions and appearance. Entry to the DPAC restrooms and the President’s Club will be seamless from the main second floor lobby. An added feature of the President’s Club is the separate entry available from the ground level without first entering DPAC. The flooring, ceiling and wall finishes of the new DPAC amenities will match or complement the existing DPAC finishes. Xxxxxxx Design, architect for the DPAC, is responsible for the complementary architectural design of the proposed development. The DPAC Amenities will cantilever outward on the second level to overlook the Plensa sculpture and DPAC plaza. This cantilever will be constructed of the glass curtainwall system similar to the DPAC, hence reinforcing the connection between the two spaces. On the interior, restroom finishes and fixtures will be the same as within the DPAC. The President’s Club Lounge will have carpet and wood flooring, floor-to-ceiling glass for views, and separate restroom facilities in addition to being constructed to accommodate audio-visual equipment throughout, beverage stations and seating/furnishings.
Construction Timeline. A. Attached as Exhibit E-2 is Xxxxxx’s baseline schedule to commence and complete the demolition of the Existing Improvements and complete the construction of the Project.
Construction Timeline. The Foundation shall provide the City’s Project Manager with a construction timeline prior to commencing construction, for review and approval by the City’s Project Manager. The Foundation will forward, in electronic form, all relevant schedule documents and the City’s Project Manager shall respond as soon as possible, but no later than four (4) business days beginning with the business day following the submission to the City of all relevant materials. Similarly, any additional communications between the City and the Foundation concerning the construction timeline shall be as timely as possible but at the most four (4) business days. Any changes to the construction timeline must be approved, in writing, by the City following the same submittal requirements and review and approval timeline as the original timeline. Full lien waivers must be given to the City prior to the start of any construction. Construction work within the Parks Building cannot exceed four (4) months, measured from the first date construction begins. Construction of the Interpretive Center must be completed within that four (4) month period and no later than June 30, 2023.
Construction Timeline. (a) Within five (5) months of the Effective Date, Redeveloper shall submit its application for site plan approval for the Project to the Planning Board.
Construction Timeline. The completion date of the Project shall occur on or before the date set forth in the Conceptual Review. Contractor shall provide to the Department the construction schedule. Any changes to the completion date may only be made if approved in writing by the Director. Any failure to complete construction of the Project by the Completion Date that is attributed solely to the actions of the County (“County Delay”), such as the unreasonable interference by County or its agents with the substantial completion of the Project, or the County’s failure to meet approval deadlines as contemplated in this Agreement, or any delays in permitting the Project beyond time periods that are typical for permit approval in the County, shall not result in the default of Contractor under the terms of this Agreement, and shall be considered by Director as a basis for modifying the completion date to a later date.
Construction Timeline. Owner acknowledges that Section 24 (Prompt Completion of Structures) of the Covenants requires that all Construction Activity be complete within eighteen (18) months of the Architectural Committee’s approval of the Construction Management Plan. For the purposes of this Agreement, and the Covenants, Owner agrees that “Completion of Construction Activity” means completion of all site work; excavation; grading; construction or remodeling of any structure or improvement, including all punch list items; landscaping and irrigation systems; revegetation, and reclamation of all disturbed areas. Further, Owner understands that issuance of a Certificate of Occupancy by Eagle County does not constitute Completion of Construction Activity.
Construction Timeline. As of the date hereof, to the best of Principal’s knowledge after consultation with the Architect and Contractor, the Construction Timeline attached hereto as Exhibit D (y) is true, correct and complete in all material respects, and (z) is a fair and reasonable timeline for completing the Improvements in accordance with the terms of this Agreement.
Construction Timeline. Planning and construction of the Visp Facility is currently scheduled to commence in [*] and proceed according to the estimated timeline set forth in Appendix F (as amended from time to time). Lonza shall provide Customer with regular updates regarding progress in the planning and construction of the Visp Facility, including prompt notifications of any significant deviations from the estimated timeline. Customer shall also have the right to review construction plans, and conduct a site visit, but shall not have the right to direct or coordinate construction and shall have no obligation with respect to capital expenditures related thereto. If a material delay in construction of the Visp Facility prohibits Lonza from completing delivery of Engineering Batches and Process Validation Batches under the obligations of this Agreement at the Visp Facility, then the provisions of Clause 2.1 shall apply.
Construction Timeline. To the Borrower’s knowledge, the Construction Timeline accurately specifies in summary form the work that the Borrower proposes to complete in each calendar quarter from the Closing Date through the Opening Date, all of which is expected to be achieved.
Construction Timeline. To be added