Reliability Run Sample Clauses

Reliability Run. Contractor guarantees that, in no event later than the occurrence of Final Acceptance of the Facility hereunder, the Facility shall have successfully completed the Reliability Run (the "Reliability Guarantee"). Contractor recognizes and acknowledges that in operating the Facility during the Reliability Run Owner will operate the Facility in accordance with the Power Purchase Agreement.
AutoNDA by SimpleDocs
Reliability Run. Contractor shall carry out a Reliability Run to demonstrate the reliable operation of the Power Plant and its Component Units under normal working conditions and under the dispatch control of the power purchaser and grid operator. The test will be recorded per the attached Test Record of the Reliability Run. The Power Plant will be operated during the Reliability Run Period (defined below) and the Reliability Run will be considered successful if during such period there are: o Not more than 5 (five) Outages (as defined below) o Not more than 16 (sixteen) aggregate Outage Hours (as defined below) o No single Outage with a duration greater than 6 (six) Outage Hours o Not more than 2 (two) Plant Shutdowns (as defined below) o Not more than 8 (eight) aggregate Outage Hours due to Plant Shutdowns o No Plant Shutdowns in the last 48 (forty-eight) hours of the Reliability Run Test Period o No second Outage which was caused by the repetition, after rectification, of a failed item of equipment which had caused a prior Outage (D-6) August 14, 2002 EPC Contract - Mokai II, New Zealand Where: -------------------------------------------------------------------------------- Outage = One or more of the Component Units is not operating under the dispatch control of the power purchaser and grid operator as a result of Equipment failure, Work design or construction defects or an occurrence or circumstance within the reasonable control of Contractor ----------------------------- -------------------------------------------------- Outage Hours = The period of time with respect to a particular Outage commencing upon the time that any or all Component Units are not under the dispatch control of the power purchaser and grid operator as a result of Equipment failure, Work design or construction defects or an occurrence or circumstance within the reasonable control of Contractor and ending upon the resumption of normal dispatch control ----------------------------- -------------------------------------------------- Plant Shutdowns = An Outage in which none of the Component Units are under the dispatch control of the power purchaser and grid operator under normal operating conditions ----------------------------- -------------------------------------------------- Reliability Run Period = 14 (fourteen) days plus the aggregate Outage Hours during the Reliability Run (if any) plus any additional hours necessary (if any) so as to not have a Plant Shutdown during the last 48 (forty-eight...
Reliability Run. As a minimum requirement to demonstrate the reliability of the Facility (, the Company shall carry out a reliability run for a period of one hundred and sixty eight (168) hours during which time the Facility shall operate continuously (without interruption) for seventy-two (72) continuous hours at then demonstrated Dependable Capacity. The output during the remaining ninety six (96) hours of the test will be as requested by BPDB in accordance with the Dispatch provisions outlined in Section 9.2 (excluding Section 9.2(a)(iii)) as if such provisions were applicable during the period prior to the Commercial Operations Date. This test shall have been satisfactorily completed if the reliability run continues without interruption (arising out of factors internal to the Facility) for not less than one hundred and sixty eight (168) hours. In the event that the reliability run is interrupted for reasons external to the Facility, the accumulated testing time prior to such interruption shall be deemed acceptable for testing purposes. The Company shall be required to carry out the reliability run only for such remaining period after such interruption ceases and the reliability runs carried out during the period prior to the interruption and the period after the interruption shall be deemed as one continuous period as if such interruption had not occurred.
Reliability Run. A reliability run for the Early Generation Facility or the Plant as the case may be will be carried out as part of the Commissioning tests. The run will be for a period of thirty (30) days and will include seventy-two (72) continuous hours at one hundred percent (100%) base load (i.
Reliability Run. As a minimum requirement to demonstrate the reliability of the Facility, the Company shall carry out a reliability run for a period of one hundred (100) hours during which time the Facility shall operate continuously for seventy-two (72) continuous hours at the then demonstrated Dependable Capacity. The output during the remaining twenty eight (28) hours of the test will be as requested by BPDB. This test shall have been satisfactorily completed if the reliability run continues without interruption (arising out of factors internal to the Facility) for not less than one hundred (100) hours. In the event that the reliability run is interrupted for reasons external to the Facility, the accumulated testing time prior to such interruption shall be deemed acceptable for testing purposes. The Company shall be required to carry out the reliability run only for such remaining period after such interruption ceases and the reliability runs carried out during the period prior to the interruption and the period after the interruption shall be deemed as one continuous period as if such interruption had not occurred.
Reliability Run. As soon as is practicable after the achievement of Provisional Acceptance and for purposes of determining whether the Turnkey Contractor has satisfied the Reliability Guaranty, the Turnkey Contractor, with the assistance and cooperation of the MEP Participants’ operations personnel, shall operate the Facilities in accordance with the requirements of Section 7.3.1 (the “Reliability Run”) to support the operating demands for the Facilities, while simultaneously operating the Facilities in accordance with the Operating Manuals. The Reliability Run shall be conducted with all systems being operated in the automatic mode in accordance with Appendix A. Without limiting the practices which may void the test, the use of nonpermanent systems and equipment, jumpering out of safety interlocks and use of excess operating personnel shall be prohibited during the Reliability Run.

Related to Reliability Run

  • Reliability Reliability targets (Mean Time Between Failures (MTBF)) are defined in the technical specifications as set out in the Contract. Notwithstanding any possible application of penalties relating to reliability defined in the Contract, Goods shall remain covered by the warranty defined in this Article 16 as long as the reliability commitments have not been reached.

  • Infrastructure Vulnerability Scanning Supplier will scan its internal environments (e.g., servers, network devices, etc.) related to Deliverables monthly and external environments related to Deliverables weekly. Supplier will have a defined process to address any findings but will ensure that any high-risk vulnerabilities are addressed within 30 days.

  • Quality Service Standards Price Services and the Fund may from time to time agree to certain quality service standards, as well as incentives and penalties with respect to Price Services’ Services hereunder.

  • Baseline For purposes of measuring a reduction in net tax revenue, the interim final rule measures actual changes in tax revenue relative to a revenue baseline (baseline). The baseline will be calculated as fiscal year 2019 (FY 2019) tax revenue indexed for inflation in each year of the covered period, with inflation calculated using the Bureau of Economic Analysis’s Implicit Price Deflator.163 FY 2019 was chosen as the starting year for the baseline because it is the last full fiscal year prior to the COVID– 162 See, e.g., Tax Policy Center, How do state earned income tax credits work?, https:// xxx.xxxxxxxxxxxxxxx.xxx/xxxxxxxx-xxxx/xxx-xx- state-earned-income-tax-credits-work/ (last visited May 9, 2021).

  • Quality Assurance/Quality Control Contractor shall establish and maintain a quality assurance/quality control program which shall include procedures for continuous control of all construction and comprehensive inspection and testing of all items of Work, including any Work performed by Subcontractors, so as to ensure complete conformance to the Contract with respect to materials, workmanship, construction, finish, functional performance, and identification. The program established by Contractor shall comply with any quality assurance/quality control requirements incorporated in the Contract.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Money Market Fund Compliance Testing and Reporting Services Subject to the authorization and direction of the Trust and, in each case where appropriate, the review and comment by the Trust’s independent accountants and legal counsel, and in accordance with procedures that may be established from time to time between the Trust and the Administrator, the Administrator will:

  • Data Quality 4.1 Each party ensures that the shared Personal Data is accurate. 4.2 Parties will notify each other with undue delay if they become aware of inaccuracies in shared Personal Data.

  • Registry Performance Specifications Registry Performance Specifications for operation of the TLD will be as set forth in Specification 10 attached hereto (“Specification 10”). Registry Operator shall comply with such Performance Specifications and, for a period of at least one (1) year, shall keep technical and operational records sufficient to evidence compliance with such specifications for each calendar year during the Term.

  • COUNTY’S QUALITY ASSURANCE PLAN The County or its agent will evaluate the Contractor’s performance under this Contract on not less than an annual basis. Such evaluation will include assessing the Contractor’s compliance with all Contract terms and conditions and performance standards. Contractor deficiencies which the County determines are severe or continuing and that may place performance of the Contract in jeopardy if not corrected will be reported to the Board of Supervisors. The report will include improvement/corrective action measures taken by the County and the Contractor. If improvement does not occur consistent with the corrective action measures, the County may terminate this Contract or impose other penalties as specified in this Contract.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!