Testing of the Complex Prior to Commercial Operations Date Sample Clauses

Testing of the Complex Prior to Commercial Operations Date. (a) The Company shall provide the Power Purchaser and NTDC on an on-going basis with relevant information regarding its programme for testing the Complex and the Schedule therefor. Not less than thirty (30) Days prior to the commencement of such test programme, the Company will deliver to the Power Purchaser and NTDC in writing the final programme for testing the Complex, including the expected duration of the Company's start-up testing programme and a tentative schedule for conducting all tests required under Sections 8.2 and 8.3. The Company shall advise the Power Purchaser and NTDC in writing of any changes in its final schedule for the testing programme not less than seven (7) Days prior to the commencement of the tests required under Section 8.2. Such final schedule shall not materially increase or advance the timing of the Power Purchaser’s and NTDC's obligations under this Agreement without the prior written consent of the Power Purchaser and NTDC. If the schedule for any test required under Section 8.2 or 8.3 is adjusted after the Company has provided the Power Purchaser and NTDC with the final testing programme schedule, then the Company shall advise the Power Purchaser and NTDC not less than forty-eight (48) hours prior to the commencement of any such test. On each Day beginning with the Day on which testing commences, the Company shall provide the Power Purchaser and NTDC with a schedule of the tests to be conducted on the following Day or Days (if such test will continue for more than one (1) Day). All testing of the Complex shall satisfy the commissioning and test criteria provided in Schedule 7. (b) If NTDC is unable to accommodate the schedule for such test or tests as provided by the Company in the final schedule for the programme of tests pursuant to Section 8.1(a), NTDC will give the Company notice within forty eight (48) hours of its receipt of the final schedule for testing of its requirements regarding deferral or delay of any Commissioning Tests for the Complex and the Company and NTDC will mutually agree on a date for any deferral test or programme of tests; provided, however, that should NTDC defer or delay any Commissioning Tests beyond fifteen (15) Days from the date on which the tests were finally scheduled in accordance with Section 8.1 and such deferral causes the Scheduled Commercial Operations Date of the Complex, as certified by the Engineer under Section 8.3, to be delayed or deferred, then NTDC shall be liable to the Compa...
AutoNDA by SimpleDocs
Testing of the Complex Prior to Commercial Operations Date. (a) The Contractor shall provide the Employer on an on-going basis with relevant information regarding its programme for testing the Complex and the schedule therefor. Not less than forty-five (45) days prior to the commencement of such test programme, the Contractor will d eliver to the E mployer in writing the f inal pr ogramme f or te sting the C omplex, including t he e xpected du ration of the C ontractor’s start-up t esting pr ogramme a nd a tentative schedule for conducting all tests required by Sections 9.2 and 9.3. The Contractor shall advise the Employer in writing of any changes in its final schedule for the testing programme not less than ten (10) days prior to the commencement of the tests required by Section 9.2. Such final schedule shall not materially increase or advance the timing of the Power P urchaser’s ob ligations unde r the P PA w ithout t he pr ior w xxxxxx c onsent of t he Employer. If the schedule for any test required by Section 9.2 or 9.3 is adjusted after the Contractor has provided the Employer with the final testing programme schedule, then the Contractor shall a dvise the E mployer not l ess t han seventy-two ( 72) hours prior t o t he commencement of any such test. On each day beginning with the day on w hich testing commences, the Contractor shall provide the Employer with a schedule of the tests to be conducted on the following day or days (if such test will continue for more than one (1) day). All testing of the Complex shall satisfy the commissioning and test criteria provided in The Commissioning and Testing Schedule. (b) If the Employer is unable to accommodate the schedule for such test or tests as provided by the Contractor in the final schedule for the programme of tests pursuant to Section 9.1(a), the Employer will give the Contractor notice within seventy-two (72) hours of its receipt of the f inal s chedule f or t esting of i ts r equirements r egarding xx xxxxxx or d elay of a ny Commissioning Tests for the Complex and the Parties will mutually agree on a date for any deferral test or programme of tests; provided, however, that should the Employer defer or delay any Commissioning Tests beyond fifteen (15) days from the date on which the tests were f inally sche duled in accord ance w ith Section 9.1 and s uch de xxxxxx x xxxxx t he Scheduled Commercial O perations D ate of the C omplex, as c ertified by t he E ngineer under S ection 9.3, t o be delayed or de ferred, t hen the C ontractor m ay be e ntitled t o d...

Related to Testing of the Complex Prior to Commercial Operations Date

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Commercial Diligence Pfizer will use Commercially Reasonable Efforts to Commercialize at least [**] in [**], where Pfizer or its designated Affiliates or sublicensees seek and receive Regulatory Approval for such [**]. Pfizer will have no other diligence obligations with respect to the Commercialization of Licensed Products except as otherwise set forth in this Agreement.

  • Service Commencement Date The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.

  • Pre-Commencement Phase Services The services required to be provided by the Contractor for the Pre- Commencement Phase of the Project in accordance with the Contract Documents.

  • Information Systems Acquisition Development and Maintenance a. Client Data – Client Data will only be used by State Street for the purposes specified in this Agreement.

  • Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!