Construction Works. Construction Works on the Project shall be carried out in accordance with the building programme submitted to and approved by the Lender and/or the schedule set out in the Building Contract;
Construction Works. The Concessionaire shall ensure that construction of building structure of the Bus Terminal Facilities is undertaken in accordance with the design approved by the Independent Engineer in consultation with the Punjab Roadways/PRTC/PIDB or any other body of Punjab Governemnt. Entire construction shall be in conformity with the Technical Specifications and Standards set forth in this document. The development works shall include, but be not limited to, the following: · Preparation of master plan for the entire site for development of Bus Terminal Facilities and Commercial Facilities. · Detailed design & detailed engineering with Good for Construction drawings related to the execution of the Bus Terminal Facilities. · Development of Bus Terminal Elements which shall include the bus bays (alighting, boarding and idle parking), bus circulation area, exit & entry for buses and other components described in subsequent paragraphs of this Schedule. · Passenger Amenities shall include, but be not limited to, shops, kiosks, ticketing counters, tourist information centre, toilets, drinking water xxxxxxxx, waiting halls, seating facilities, dustbins, parking areas for public, private and intermediate public transport, etc and other components described.. · Design and construct supporting infrastructure facilities related to internal roads, curb stones, foot paths, Solid Waste Management, Rain Water Harvesting, Water Supply and Sanitation, Electric Sub Station, solar lighting (if needed), Communication System, Facilities for the differentially-abled persons.
Construction Works. (i) The Developer is required to commence Construction Works only on or after the approval of the Development Plan by JTDCL.
(ii) Unless otherwise permitted by JTDCL, no Construction Works shall begin until the Third Party Inspector is in place and has assumed charge. The Developer shall immediately upon commencement of Construction Works notify the Third Party Inspector and JTDCL of the same.
(iii) The Developer shall adhere to the approved Developer Plan, Detailed Project Report, Construction Requirements and achieve COD on or before the Scheduled Project Completion Date. If the Developer fails to achieve COD on or before the Scheduled Project Completion Date for any reason other than conditions constituting Force Majeure or for reasons attributable to JTDCL, the Developer shall pay to JTDCL, damages calculated at the rate of 6% (six percent) of the Performance Security, for every month of delay till COD.
(iv) The Developer shall, before commencement of Construction Works have requisite organisation and designate and appoint suitable officers / representatives as it may deem appropriate to supervise the Project, to deal with the Third Party Inspector/JTDCL and to be responsible for all necessary exchange of information required pursuant to this Agreement;
(v) For the purposes of determining whether the Construction Works are being undertaken in accordance with the Detailed Project Report, Development Plan and Construction Requirements, the Developer shall with due diligence carry out all necessary and periodical Tests at its cost in accordance with the instructions and under the supervision of the Third Party Inspector and the Construction Requirements.
(vi) If, as a result of such tests, JTDCL and/or the Third Party Inspector decides that any plant, materials, consumables, design, process, software or workmanship relating to the Project Facility is defective or otherwise not in compliance with the Detailed Project Report, Development Plan, Construction Requirement and Good Industry Practice, JTDCL and/or the Third Party Inspector may reject such materials, consumables, process or workmanship and shall forthwith notify the Developer with reasons for rejection and require correction of such defects within the stipulated time.
(vii) The Developer shall make good such notified defects within the stipulated time, and undertake re-testing, if any, at its cost that may be required by JTDCL and/or the Third Party Inspector. In the event that the Developer fails...
Construction Works a) Construction all risks, owner-controlled1, for each building under construction, based on full contract value and including:
(i) strike, riot & civil commotion;
(ii) debris removal;
(iii) extra expenses;
(iv) extended maintenance period;
(v) third party liability; and
(vi) designer’s risks.
b) Marine cargo (including war) on transportation of key plant/equipment, unless shipments are on CIF2 project site (or comparable) basis.
c) Advance loss of profits covering debt service (including principal and interest), fixed costs and increased cost of working during indemnity period of twelve (12) months from the anticipated scheduled commercial operations start date.
Construction Works a) Erection and or installation/Construction All Risks, owner-controlled, based on full contract value and including:
i) Strike, Riot & Civil Commotion
ii) Debris Removal
iii) Extra Expenses
iv) Extended Maintenance Period v) Third Party Liability
b) Marine Cargo (including war) on transportation of key plant/equipment, unless shipments are on CIF (or comparable) basis
Construction Works. Construction All Risks, based on full contract value (including in All Risk policy) and including Third Party Liability (included in General Liability policy).
Construction Works. The Concessionaire shall commence the Construction Works on their Commencement Date, after giving a prior notice to the Contracting Authority no later than 7 Business Days before the Construction Works Commencement Date. The Concessionaire shall procure the necessary means and shall execute the Construction Works at own investments and expenses, in full line with the requirements of the Applicable Law, this Agreement, Masterplan, Financing Plan, Implementation Plan, Detailed Technical Project, Environmental Management Plan, Key Performance Indicators and Prudent Industry Practice. The Concessionaire shall admit its obligations and shall be engaged as follows:
Construction Works. Excavation for foundation works and construction of concrete footing for RE Wall were completed. Installation of precast panels is in progress. - Footing and column of staircase were completed and construction of deck is almost completed. - Rock breaking for Bridge No. 2 pier mostly completed. - Backfilling of R/W No. 1 in progress. - Installation of soil nail of slope S2 was completed. - Excavation of slope S3 and construction of temporary soil nail for temporary works for R/W mostly completed. - Preparation for the construction of R/W No. 2. - Construction of cascade No. 2 intake (CH.400) and cascade No. 1 intake (CH.350) in progress. - Construction of Bridge No. 3 was completed. - VO for boulder field between S7 & S8 to remove boulders and stabilize the slope was issued. Erection of temporary rock fall fence and boulder removal were completed. Bulk excavation works and soil nailing works are in progress. - 1st and 2nd Span of Bridge No. 4 were completed. Piling works and pile load tests for bridge 4 were completed. Abutments and wing walls were cast, pile cap and column at pier P4/1 and P4/2 were completed. Construction of 3rd Span of Bridge No. 4 is in progress. Location of Cyberport Development in Telegraph Bay & Northern Access Road is shown in Figure 1.4, and the general layout plans of Northern Access Road are shown in Drawing Nos. T/2146/1003 & W/2146/1004. Two monitoring stations, both for noise and air quality, are located in Pine Court & Magnolia Villa as shown in Figure 1.5 and 1.6 respectively. ASR-NA1 represents the location of air quality monitoring station in Pine Court while ASR-A1 represents the location of air quality monitoring station in Magnolia Villa. NSR-3 represents the location of noise monitoring station in Pine Court while NSR-9 represents the location of noise monitoring station in Magnolia Villa.
Construction Works. (a) If the Tenant, or a contractor engaged by the Tenant, undertakes any construction works at the Property that is a 'construction project' as defined in the WHS Laws (Construction Works), the Landlord hereby appoints the Tenant or the contractor nominated by the Tenant (Tenant's Contractor) as the Principal Contractor in accordance with the WHS Laws for the relevant Construction Works on and from the date the Construction Works commence.
(b) The Tenant hereby acknowledges and accepts its appointment as Principal Contractor, and covenants to discharge the obligations of a Principal Contractor contained in the WHS Laws and accepts all liability in respect thereof.
(c) The Tenant hereby acknowledges that it has the management and control of the Property, to the extent necessary to discharge the duties imposed on a Principal Contractor by the WHS Laws.
(d) The Tenant may authorise the Tenant's Contractor to have the necessary level of management or control of the Property so as to discharge its duties as Principal Contractor for the purposes of the WHS Law so long as the Tenant:
(i) provides the Landlord with evidence to the Landlord's satisfaction that the person is able to fulfil the duties of a Principal Contractor under the WHS Law and that the person accepts the engagement;
(ii) acknowledges that the Landlord has not undertaken any obligation or assumed any duty of care in relation to any approval (implied or otherwise) of the Tenant's engagement of a Principal Contractor; and
(iii) procures that the Tenant's Contractor complies with the obligations under clause 13(e).
(e) The Tenant or the Tenant's Contractor (where engaged as Principal Contractor in accordance with clause 13(d)) acknowledges and agrees that the Tenant or the Tenant's Contractor (as the case may be):
(i) must ensure the health safety and welfare of all other persons performing the Construction Works;
(ii) is the person responsible for the Construction Works for the purposes of the WHS Law at all times until the Construction Works are completed;
(iii) must ensure that in carrying out the Construction Works or causing the Construction Work to be carried out, it complies with its obligations under the WHS Law, including, in respect of the Construction Works, as Principal Contractor;
(iv) must provide to the Landlord all notices and correspondence concerning work health and safety (including, without limitation, in respect of any notifiable incidents) in connection with the Construction Wo...
Construction Works. The Activity involves all the construction works necessary to upgrade the sub-section Brodské (incl.) – State Border SK/CZ in km 72+750 – 74+900 in line with the relevant EU