Pre-commissioning Sample Clauses

Pre-commissioning. On completion the installation of all pumps, piping, valves, pipe connections, electrical wiring, motor control panels and water level controlling devices the Concessionaire shall proceed as follows: Testing of M.C.C.:
AutoNDA by SimpleDocs
Pre-commissioning. The state when the plant/ unit/ system have been erected in accordance with the drawings, specifications, instructions and applicable codes and regulations; all other specific contractual construction activities are completed with respect to the plant/ unit/ system including compliance of check list and all the relevant technical documents are handed over to NRDA. Pretests/ Dry tests for the installed units are completed and certified by the OEM/channel partner. The Plant/ Unit/ system is considered ready for pre-commissioning when all the construction activities (including but not limited to the activities mentioned under “mechanical completion”) are completed, all the check list points are attended and all the relevant technical documents like alignment record/ test reports/ fabrication drawings etc. are handed over to the NRDA. However, with prior agreement with NRDA, construction may continue completion of check list points including residual area grading, paving, clean up, removal of temporary construction facilities, painting, insulation and correction of miscellaneous errors or omissions etc. that do not interfere with pre-commissioning activities. Pre-commissioning activities are operational activities performed in order to make the plant/ unit/ system ready for commissioning.
Pre-commissioning. PathNet shall install an Initial System in such a way that it can be operated and tested without interfering with Texaco's existing system performance. PathNet shall have all equipment in place to allow for a cutover by Texaco of its existing channels. Texaco and PathNet shall mutually agree upon a pre-commission plan and approve it in writing. This System is deemed Pre-Commissioned when fully operational.
Pre-commissioning. Functional verification of Facility utility and auxiliary systems, including electrical power, control systems, firewater, fuel gas system and utilities necessary to support the Units during and after commissioning and reinstatement of Equipment components; preparation of Equipment for commissioning, start-up and testing;
Pre-commissioning. A. Contractor will perform pre-commissioning services. This shall include as a minimum:
Pre-commissioning. TANK CONTRACTOR shall provide all labor, supervision, materials, including required spare parts, equipment and consumables and each and every item required to safely and effectively pre-commission the Phase 2 Tanks. TANK CONTRACTOR is to use this paragraph as a guide to be incorporated into his procedure to be approved by PURCHASER. No later than twelve (12) months before TANK CONTRACTOR is ready for pre-commissioning activities, it shall submit for PURCHASER’s approval, a Pre-commissioning Schedule and Execution Plan, outlining as a minimum the following: • Detailed logic network diagram and bar charts to show the sequence of Work and manpower requirements, including without limitation the following activities, materials and equipment required, and the requirements for interaction with others. • Material, including spare parts, and consumable checklists indicating purchase dates and deliveries. • Equipment checklists including requisitions and expected deliveries. • Recommended De-Commissioning Procedure. Pre-commissioning activities shall include but not be limited to:
Pre-commissioning. 1411 In addition to the tasks defined for pre-commissioning in Section 3, it is also recommended that extensive 1412 quality control checks be completed on all installed components. Pre-commissioning should also include 1413 weight-withhold and vibration tests to ensure mechanical robustness similar to those carried out according to 1414 IEC 61959, Secondary cells and batteries containing alkaline or other non-acid electrolytes - Mechanical tests 1415 for sealed portable secondary cells and batteries. 1416 During pre-commissioning the electrical interconnection to the grid from the Flow Battery should be checked 1417 that the interconnection conforms to the applicable IEEE standard(s) before proceeding to commissioning.
AutoNDA by SimpleDocs
Pre-commissioning. A. Pre-Commissioning – In Contractor fabrication facility, Contractor’s technician shall perform all firmware updates and validate signal switching and routing, IP addressing, and serial communications of all equipment with all transmitters and receivers connected to the system PRIOR to the 1st load of control code.

Related to Pre-commissioning

  • Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Decommissioning The expenditure for Decommissioning will be estimated on the basis of technical studies undertaken by the Contractor, to be agreed by the National Petroleum Agency, as part of each Field Development Program and revised as necessary.

  • Project Completion Part 1 – Material Completion

  • Timeline Contractor must perform the Services and deliver the Deliverables according to the following timeline: • •

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Quality Service Standards Price Services and the Fund may from time to time agree to certain quality service standards, as well as incentives and penalties with respect to Price Services’ Services hereunder.

  • THE WORK The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction.

Time is Money Join Law Insider Premium to draft better contracts faster.