Network Diagram Sample Clauses

Network Diagram. 1. The Contractor shall submit a time-scaled network diagram as part of the Overall Schedule. Draw or print the network diagram on reproducible paper, not larger than 24 inches by 36 inches, and show the sequence and interdependence of activities required for complete performance of all items of work. 2. Produce a legible and accurate diagram. Group activities related to a specific physical area of the project for ease of understanding and simplification. Label each activity with a complete description as well as estimated duration in working days. 3. Activity durations shall be not less than 1 day or more than 30 working days, unless otherwise approved by the Engineer, except for Engineer's submittal review and material and equipment fabrication/delivery. 4. Indicate critical path of activities on the network diagram. 5. Contractor(s) shall not be permitted to sequester shared float through such strategies as extending duration estimates to consume available float time, extensive crew/resource sequencing, etc.
AutoNDA by SimpleDocs
Network Diagram. Activities shown on the WPS shall be categorized and described as follows: a. Each individual construction activity. b. A concise description of the work. c. An activity duration shall not exceed 20 work days. Durations of greater than 20 work days are acceptable for non-construction activities or as required by the type of construction activity. d. Each activity shall be coded with an activity code or hammock that relates that activity to an item on the Schedule of Values. e. Each activity shall be coded with an activity code that relates that activity to a phase or building. This subdivision of the Project shall be mutually agreed upon between the ODR and the Contractor. f. Items requiring fabrication and delivery longer than 180 days. g. Times anticipated for shutdown and tying-in to existing services. Note: This does not serve as an official request to the ODR and each individual request for an outage shall be submitted in writing fourteen (14) calendar days prior to the anticipated outage, as described in Section 01 31 00 Project Management and Coordination. An integrated schedule containing all of the above categories, or individual schedules for each of the above categories, or both, shall be as required by the A/E and/or the ODR. h. After Substantial Completion the Contractor shall show the following activities as a minimum: 1. Completion of pre-final punchlist (Suggested duration 30 days minimum). 2. Final inspection (Suggested duration 5 days). 3. The above activities are to be Finish to Start. i. The WPS shall show the following Major Milestone Target Finish Dates: 1. Completion of main structure foundation piers or footings. 2. First or ground floor slab complete. 3. Structure top out. 4. Building dry-in or enclosed. This is defined as the roof, exterior walls, exterior windows and openings closed in. 5. Start of conditioned air. This is defined as the building is ready to hold environmental conditions. 6. Any Early Occupancy required by the Contract. 7. Project phases as outlined in the Construction Documents.
Network Diagram. ‌ For each response, Offerors must include a physical network diagram displaying the paths to be used to serve each endpoint along with percentages of aerial and underground infrastructure. In addition, each Offeror must provide a detailed network drawing and solution architecture description.
Network Diagram. The network diagram is required for the Preliminary, Initial and Periodic Updates. The network diagram shall depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:
Network Diagram. Below is a high-level diagram of the network topology currently used by IntercontinentalExchange and scheduled to be used for CCX.
Network Diagram. A graphic diagram of a network schedule, showing activities and activity relationships.
Network Diagram. [CJA 2 Abbreviation] is responsible, based on FBI CJIS Security Policy, for providing a network diagram depicting the[CJA 2 Abbreviation] network configuration including the location of all computer equipment, connectivity to [CJA Abbreviation] as well as the data flow/storage within the [CJA 2 Abbreviation] network. This network diagram must be updated whenever substantial changes occur or at least every three (3) years and submitted to the MSHP ISO for review and approval.
AutoNDA by SimpleDocs
Network Diagram. [NCJA Abbreviation] is responsible, based on FBI CJIS Security Policy, for providing a network diagram depicting the[NCJA Abbreviation] network configuration including the location of all computer equipment, connectivity to CJIS and [CJA Abbreviation] as well as the data flow within the [CJA Abbreviation] network. This network diagram must be updated whenever substantial changes occur or at least every three (3) years and submitted to the MSHP ISO for review and approval.
Network Diagram. Unique kind of diagram that represents a cluster or small structure of computers or other networking devices. Generally, is made up of interconnected devices and systems.

Related to Network Diagram

  • Network Upgrades The Transmission Owner shall design, procure, construct, install, and own the Network Upgrades described in Attachment 6 of this Agreement. If the Transmission Owner and the Interconnection Customer agree, the Interconnection Customer may construct Network Upgrades that are located on land owned by the Interconnection Customer. Unless the Transmission Owner elects to pay for Network Upgrades, the actual cost of the Network Upgrades, including overheads, shall be borne initially by the Interconnection Customer.

  • Interface A defined set of transmission facilities that separate Load Zones and that separate the NYCA from adjacent Control Areas. Investor-Owned Transmission Owners. A Transmission Owner that is owned by private investors. At the present time these include: Central Xxxxxx Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New York State Electric & Gas Corporation, Niagara Mohawk Power Corporation, Orange and Rockland Utilities, Inc., and Rochester Gas and Electric Corporation.

  • Configuration Management The Contractor shall maintain a configuration management program, which shall provide for the administrative and functional systems necessary for configuration identification, control, status accounting and reporting, to ensure configuration identity with the UCEU and associated cables produced by the Contractor. The Contractor shall maintain a Contractor approved Configuration Management Plan that complies with ANSI/EIA-649 2011. Notwithstanding ANSI/EIA-649 2011, the Contractor’s configuration management program shall comply with the VLS Configuration Management Plans, TL130-AD-PLN-010-VLS, and shall comply with the following:

  • Network Interconnection Architecture Each Party will plan, design, construct and maintain the facilities within their respective systems as are necessary and proper for the provision of traffic covered by this Agreement. These facilities include but are not limited to, a sufficient number of trunks to the point of interconnection with the tandem company, and sufficient interoffice and interexchange facilities and trunks between its own central offices to adequately handle traffic between all central offices within the service areas at a P.01 grade of service or better. The provisioning and engineering of such services and facilities will comply with generally accepted industry methods and practices, and will observe the rules and regulations of the lawfully established tariffs applicable to the services provided.

  • Network PHARMACY is a retail, mail order or specialty pharmacy that has a contract to accept our pharmacy allowance for prescription drugs and diabetic equipment or supplies covered under this plan. NETWORK PROVIDER is a provider that has entered into a contract with us or other Blue Cross and Blue Shield plans. For pediatric dental care services, network provider is a dentist that has entered into a contract with us or participates in the Dental Coast to Coast Network. For pediatric vision hardware services, a network provider is a provider that has entered into a contract with EyeMed, our vision care service manager.

  • Service Description 2.1 General

  • Network Access TENANT may find it necessary to purchase a network interface card, wireless PC card or other hardware in order to connect to the internet service. LANDLORD is not responsible for the purchase of these items and LANDLORD cannot guarantee compatibility with any device TENANT may have. The computer and network card must have software installed that supports the Internet Protocol commonly referred to as TCP/IP. Any conflicts between the software compatibility of the network and the TENANT’S computer operating system or any other feature will be the responsibility of the TENANT to resolve. LANDLORD will not be responsible for software issues related to the user’s personal computer.

  • Customer Support and Training System Agency will provide support for the CMBHS, including problem tracking and problem resolution. System Agency will provide telephone numbers for Grantees to obtain access to expert assistance for CMBHS-related problem resolution. System Agency will provide initial CMBHS training. Grantee shall provide subsequent ongoing end-user training.

  • SERVICE LEVEL DESCRIPTION The Fund Accounting Agreement is hereby amended by deleting the Service Level Description attached thereto and replacing it in its entirety with the Service Level Description attached hereto.

  • GENERAL SERVICE DESCRIPTION Service Provider currently provides active medical, pharmacy(Rx) and dental administration for coverages provided through Empire and Anthem (medical), Medco(Rx), MetLife(dental) and SHPS (FSA) (Empire, Anthem, Medco, MetLife and SHPS collectively, the “Vendors”) for its U.S. Active, Salaried, Eligible Employees (“Covered Employees”). Service Provider shall keep the current contracts with the Vendors and the ITT CORPORATION SALARIED MEDICAL AND DENTAL PLAN (PLAN NUMBER 502 EIN 00-0000000) and the ITT Salaried Medical Plan and Salaried Dental Plan General Plan Terms (collectively, the “Plans”) and all coverage thereunder in full force through December 31, 2011 for Service Recipient’s Covered Employees. All claims of Service Recipient’s Covered Employees made under the Plans and incurred on or prior to December 31, 2011 the (“2011 Plan Year”) will be adjudicated in accordance with the current contract and Service Provider will continue to take such actions on behalf of Service Recipient’s Covered Employees as if such employees are employees of Service Provider. All medical, dental, pharmacy and FSA claims of Service Recipient’s Covered Employees made under the Plans (the “Claims”) will be paid by the Vendors on behalf of the Service Provider. Service Recipient will pay Service Provider for coverage based on 2011 budget premium rates previously set for the calendar year 2011 and described in the “Pricing” section below. Service Recipient will pay Service Provider monthly premium payments for this service, for any full or partial months, based on actual enrollment for the months covered post-spin using enrollments as of the first (1st) calendar day of the month, commencing on the day after the Distribution Date. Service Recipient will prepare and deliver to Service Provider a monthly self xxxx containing cost breakdown by business unit and plan tier as set forth on Attachment A, within five (5) Business Days after the beginning of each calendar month. The Service Recipient will be required to pay the Service Provider the monthly premium payments within ten (10) Business Days after the beginning of each calendar month. A detailed listing of Service Recipient’s employees covered, including the Plans and enrollment tier in which they are enrolled, will be made available to Service Provider upon its reasonable request. Service Provider will retain responsibility for executing funding of Claim payments and eligibility management with Vendors through December 31, 2013. Service Provider will conduct a Headcount True-Up (as defined below) of the monthly premiums and establish an Incurred But Not Reported (“IBNR”) claims reserve for Claims incurred prior to December 31, 2011 date, but paid after that date, and conduct a reconciliation of such reserve. See “Headcount True-Up” and “IBNR Reconciliation” sections under Additional Pricing for details.