PROGRAMME AND DATES FOR COMPLETION Clause Samples
The 'Programme and Dates for Completion' clause establishes the schedule and key deadlines for completing the work under a contract. It typically requires the contractor to submit a detailed programme outlining the sequence and timing of construction activities, which must be approved by the client or project manager. This clause ensures that all parties have a clear understanding of the expected timeline, helping to coordinate resources and manage expectations, and it provides a basis for monitoring progress and addressing delays.
PROGRAMME AND DATES FOR COMPLETION. Dates for Completion
14.1.1 [satisfy the ICT Handover Requirements by the ICT Handover Date; and]
14.1.2 complete the [Main] Works by the Completion Date [; and]
14.1.3 [complete the Post Completion Works and satisfy the Post Completion Works Requirements by the Post Completion Works Date.] Without prejudice to [Clause 14.9 ([Provision of Temporary Accommodation)], [Clause 14.10 ([Unavailability of Existing Facilities)], [Clause 14.11 ([Post Completion Works Phase)], Clause 19.5 (Liability), Clause 33 (D&B Co Event of Default) and Clause 37 (Consequences of Termination), the Authority shall not be entitled to claim [liquidated or] general damages in respect of any delay which elapses between the ICT Handover Date and the corresponding Actual ICT Handover Date[, or] the Completion Date and the Actual Completion Date [or the Post Completion Works Date and Actual Post Completion Works Date].
PROGRAMME AND DATES FOR COMPLETION. Dates for Completion
14.1 Project Co shall [in respect of each Facility]:
14.1.1 [satisfy the ICT Handover Requirements by the [relevant] ICT Handover Date; and]
14.1.2 complete the [Main] Works and satisfy the Payment Commencement Requirements by the [relevant] Completion Date [; and]
14.1.3 [complete the [relevant] Post Completion Works and satisfy the Post Completion Works Requirements by the [relevant] Post Completion Works Date.] Without prejudice to [Clause 14.9 ([Provision of Temporary Accommodation)], Clause [14.10 ([Unavailability of Existing Facilities)], [Clause 14.11 ([Post Completion Works Phase)], Clause 40 (Project Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination), the Authority shall not be entitled to claim [liquidated or] general damages in respect of any delay which elapses between the [relevant] ICT Handover Date and the corresponding Actual ICT Handover Date[,/or] the [relevant] Completion Date and corresponding Actual Completion Date [and the [relevant] Post Completion Works Date and [relevant] Actual Post Completion Works Date].
14.2 [The Certificate of Practical Completion [in respect of the [relevant] Facility] shall not be issued any less than [twenty (20)] Business Days after the issue of the ICT Handover Acceptance Certificate.]35
14.3 Any Programme submitted in accordance with the provisions set out below shall be prepared in accordance with Good Industry Practice and shall be in sufficient detail so as to enable the Authority's Representative to monitor the progress including all commissioning activities and likely future progress of the Works. 35 To be reviewed in the context of college commissioning needs.
14.4 The initial Programme is set out at Schedule 7 (The Programme). Any change to the Programme shall only be made in accordance with this Clause 14 (Programme and Dates for Completion) and Schedule 8 (Review Procedure). Project Co shall promptly submit to the Authority's Representative a copy of any version of the Programme varied in accordance with this Clause 14 (Programme and Dates for Completion) and Schedule 8 (Review Procedure).
14.5 If it appears to the Authority's Representative at any time that the actual progress of the Works has significantly fallen behind the Programme, then the Authority's Representative shall be entitled to require Project Co to submit to the Authority's Representative a report identifying the reasons for the de...
PROGRAMME AND DATES FOR COMPLETION. Dates for Completion
14.1 Project Co shall complete the Works [relating to a Phase] by the [Completion Date] [relevant Phase Completion Date]. Without prejudice to Clause 40 (Project Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the [Completion Date] [Phase Completion Date] and the [Actual Completion Date] [relevant Phase Actual Completion Date].
14.2 Any Programme submitted in accordance with the provisions set out below shall be prepared in accordance with Good Industry Practice and shall be in sufficient detail so as to enable the Authority's Representative to monitor the progress including all commissioning activities and likely future progress of the Works.
14.3 The initial Programme is set out at Schedule 7 (The Programme). Any change to the Programme shall only be made in accordance with this Clause 14 (Programme and Dates for Completion) and Schedule 8 (Review Procedure). Project Co shall promptly submit to the Authority's Representative a copy of any version of the Programme varied in accordance with this Clause 14 (Programme and dates for Completion) and Schedule 8 (Review Procedure).
14.4 If it appears to the Authority's Representative at any time that the actual progress of the Works has significantly fallen behind the Programme, then the Authority's Representative shall be entitled to require Project Co to submit to the Authority's Representative a report identifying the reasons for the delay and, unless the event causing the delay is still subsisting and it is not possible to predict with any certainty when the delay might come to an end, require Project Co (at the Authority's option):
14.4.1 to produce and submit to the Authority's Representative in accordance with Schedule 8 (Review Procedure) a revised Programme showing the manner and the periods in which the Works will be carried out to ensure completion; and/or
14.4.2 to produce and submit to the Authority's Representative in accordance with Schedule 8 (Review Procedure) a revised Programme showing the steps which are to be taken to eliminate or reduce the delay.
14.5 Notwithstanding that the Works [relating to a Phase] may have been completed in accordance with this Agreement, the [Actual Completion Date] [Phase Actual Completion Date] may only occur on a date on or after the Completio...
PROGRAMME AND DATES FOR COMPLETION. Dates for Completion
14.1 Project Co shall complete the Works [relating to a Phase] by the Completion Date [relevant Phase Completion Date]. Without prejudice to Clause 40 (Project Co Event of Default), 42 (Authority Voluntary Termination), 46 (Compensation on Termination) and 47 (Consequences of Termination) the Authority shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Completion Date [Phase Completion Date] and the Actual Completion Date [relevant Phase Actual Completion Date].
14.2 Any Programme submitted in accordance with the provisions set out below shall be prepared in accordance with Good Industry Practice and shall be in sufficient detail so as to enable the Authority's Representative to monitor the progress including all commissioning activities and likely future progress of the Works.
PROGRAMME AND DATES FOR COMPLETION. 19.1 The Operator shall complete the Works by the Planned Operational Date. Subject to Clauses 44 (Operator Events of Default), 47 (Effect of Termination) and 48 (Compensation on Termination) and Clause 21.6, the Trust shall not be entitled to claim liquidated or general damages in respect of any delay which elapses between the Planned Operational Date and the Operational Date.
PROGRAMME AND DATES FOR COMPLETION. Dates for Completion