PROSECUTION AND PROGRESS OF WORK Sample Clauses

PROSECUTION AND PROGRESS OF WORK. 108.03 - Progress Schedule General Requirements The Contractor shall plan and schedule the Work on the Project so as to complete the work within the time limit and budget established by the Contract and shall submit his plan to accomplish these objectives in the form of a Progress Schedule for the Engineer’s review and acceptance. The Progress Schedule shall be used by the Engineer for planning, coordination and inspection activities, and for evaluation of the Contractor’s rate of progress and the effects of time-related impacts on the Project. Prior to preparing the schedule, the Engineer or the Contractor may request a meeting to discuss any Project specific items required for preparation of the Progress Schedule. The Contractor shall prepare and submit a practicable schedule to reflect a logical progress of the Work. The Progress Schedule shall represent the Contractor’s overall Work plan to accomplish the Work in accordance with the requirements herein and those of the Contract as detailed in the Contract documents. It shall include all time-based tasks required for timely completion of the Work, including as applicable the Work to be performed by sub-contractors, suppliers, the Department, and/or others. When preparing the schedule, the Contractor shall consider all applicable constraints and restrictions such as seasonal, weather, traffic, utility, railroad, right-of-way, environmental, permits, and other limitations to the Work.
AutoNDA by SimpleDocs
PROSECUTION AND PROGRESS OF WORK. The Contractor shall commence on work indicated on the work order no later than the fifth (5th) business day after issuance unless required materials, railroad access, or railroad authorizations are not available. Non-availability of materials shall be verified by at least three (3) different sources. Verification shall be formal and supplied by the Contractor in writing. Issuance of each work order constitutes the notice to proceed with the work described on the work order. Time charges commence from the date of the NTP and continue until substantial completion, as determined by the Engineer, of the individual work order. If there is a verified non-availability of materials, time charges shall commence on the first (1st) working day following the delivery date of materials. The Contractor may have up to six (6) active work orders at any time until all assigned work has been completed. The Contractor is required to have a minimum of two working crews readily available to work on this contract simultaneously, with the ability to provide additional working crews if requested by the Engineer. Each crew is required to have a qualified superintendent as outlined in Section 105.7 of the Standard Specifications. Failure to start assigned work orders in the allowed time constitutes “Failure to Pursue the Work” and subjects the Contractor to Liquidated damages as outlined in Section 108.8 of the Standard Specifications. If work on a specific work order is not completed within the allotted time, Liquidated Damages will be assessed in accordance with Subsection 108.9 and based on the total value of that work order. Each work order shall be considered a separate unit of work. Upon the substantial completion of the work at an individual location, the Engineer will stop time at that location and perform an initial inspection for the work order location in accordance with Subsection 105.16. The Engineer reserves the right to require the Contractor to add work or make repairs to completed locations until such a location has been accepted by the Department. The Contractor must repair all defects in the work caused by poor workmanship or materials at his/her own expense until the Department accepts the Contract after the Primary Inspection. A Primary Inspection will be completed on an annual basis for work orders completed in a calendar year. Upon satisfactory completion of the Final Punchlist, the Department will accept the location and release the Contractor from responsi...
PROSECUTION AND PROGRESS OF WORK. ARTICLE 30, PROSECUTION AND PROGRESS OF WORK, is added as follows: Submission of Working Schedule: The CONTRACTOR shall provide a schedule that shows the various activities of work in sufficient detail to demonstrate a reasonable and workable plan to complete the project within the established Contract Time. The order and interdependence of activities and the sequence for accomplishing the work shall be shown. All activities shall be described in sufficient detail so that the COUNTY can readily identify the planned work and measure the progress of each activity. Each activity will be shown with a beginning work date, duration, and monetary value. Activities for the procurement, fabrication, and/or delivery of materials, batch plants, and equipment shall be included. Activities for the review of shop drawings and submittals shall be included. Activities indicating coordination with utility owners that have facilities within the limits of construction requiring adjustment or relocation shall be included. Milestone activities, when required by the Contract Documents, shall be included. In a project with more than one phase, each phase and its completion date shall be adequately identified. Activities will not be allowed to span more than one phase. The CONTRACTOR shall submit a narrative with the schedule, consisting of a concise written description of the construction plan. An updated Work Progress Schedule shall be submitted monthly to the COUNTY. All changes in the planned order start or finish dates, or duration of an activity will be applied.
PROSECUTION AND PROGRESS OF WORK. Work assignments will be issued to the Contractor in the form of a letter along with all necessary sketches, engineering drawings and any additional special provisions required. At times, depending upon the nature and complexity of the work assignments, field meetings may be necessary at certain site locations. The Contractor shall have sufficient work forces and Bid Item materials in stock to perform any issued assignment.
PROSECUTION AND PROGRESS OF WORK. ARTICLE 30, PROSECUTION AND PROGRESS OF WORK, is added as follows:
PROSECUTION AND PROGRESS OF WORK. Work assignments will be issued to the Contractor in the form of a letter along with all necessary sketches, engineering drawings and any additional special provisions required. At times, depending upon the nature and complexity of the work assignments, field meetings may be necessary at certain site locations. The Contractor shall have sufficient work forces and Bid Item materials in stock to perform any assignment within the times specified. The Contractor shall be actively working on at least one (1) and not more than six (6) active work orders at any one time until all assigned work has been completed statewide, unless otherwise approved by the Engineer. When directed by the Department, out of sequence and/or expedited work sites are not included in the maximum limit noted herein. Failure to begin work as specified on the approved schedule constitutes “Failure to Pursue the Work” and shall result in Liquidated Damages as outlined in subsection 108.09 of the Standard Specifications. No liquidated damages will be charged when items that the Contractor needs in order to start the work are unavailable from at least three (3) independent sources. If work on a specific work order is not completed within the allotted time, Liquidated Damages based on the value of the work order will be assessed in accordance with Subsection 108.09.
PROSECUTION AND PROGRESS OF WORK. UNOFFICIAL Work assignments will be issued to the Contractor in the form of a letter along with all necessary sketches, engineering drawings and any additional special provisions required. At times, depending upon the nature and complexity of the work assignments, field meetings may be necessary at certain site locations. The Contractor shall have sufficient work forces and Bid Item materials in stock to perform any issued assignment. WEBSITE
AutoNDA by SimpleDocs
PROSECUTION AND PROGRESS OF WORK 

Related to PROSECUTION AND PROGRESS OF WORK

  • Prosecution of Work FIRST PARTY will employ a sufficient staff to prosecute the work diligently and continuously and will complete the work in accordance with the schedule of work approved by the CITY. (See Exhibit "A," Scope of Services).

  • REVIEW OF WORK The Consultant shall permit the City, its agents and/or employees to review, at any time, all work performed pursuant to the terms of this Agreement at any stage of the work;

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!