PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
9.1.1 The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and
9.1.2 The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3 The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and
9.1.4 The estimated amount in dollars the Contractor will claim on a monthly basis.
9.2 The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.
9.3 If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
9.4 The Contractor will not receive any payments until the proposed progress schedule is submitted.
PROGRESS SCHEDULES. 42.1. As may be required pursuant to Article 4 or as directed by the Project Manager, to enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work shall submit to the Project Manager a proposed progress schedule in the form specified showing:
42.1.1. The anticipated time of commencement and completion of each of the various operations to be performed under this Contract;
42.1.2. The sequence and interrelation of each of these operations with the others and with those of other related contracts;
42.1.3. The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 43; and
42.1.4. The estimated amount in dollars the Contractor will claim on a monthly basis.
42.2. The proposed schedule shall be revised as directed by the Project Manager, until finally approved by the Project Manager, and after such approval, subject to the provisions of 0, shall be strictly adhered to by the Contractor.
42.3. If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to 0, it shall promptly adopt such other or additional Means and Methods of the Work, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
42.4. The Contractor will not receive any payments until the proposed progress schedule (if required) is submitted.
PROGRESS SCHEDULES. A. Contractor shall develop a progress schedule and submit to the Engineer for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer.
B. The Contractor shall update and submit the progress schedule to the Engineer each month. The Owner may withhold payment if the Contractor fails to submit the schedule.
PROGRESS SCHEDULES. 43.1. As may be required pursuant to Article 4 or as directed by the Project Manager, to enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
PROGRESS SCHEDULES. 28 12.2 Delivery Of Schedules To Company........................................... 28 12.3
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work or issuance of a Work Order, unless otherwise directed by the Director, shall submit to the Director a proposed progress schedule
9.2 The proposed schedule shall be revised as directed by the Director, until finally approved by the Director, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.
9.3 If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the City if the approved progress schedule is not met.
9.4 The Contractor will not receive any payments until the proposed progress schedule is submitted.
PROGRESS SCHEDULES. 9.1 To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within thirty (30) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed milestone schedule based on the Critical Path Method in the form specified in Book 4 Technical Specifications, Section 040.1 Details for Progress Schedule, and milestone cash flow requirements, showing:
9.1.1 The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and
9.1.2 The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3 The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and
9.1.4 The estimated amount in dollars the Contractor will invoice at each completed contract milestone based upon the payment milestones.
PROGRESS SCHEDULES. 9.1. Date by which Party B is to submit the organizational design of the construction (or construction plan) and the progress schedule:
9.2. Date by which Party A's representative is to present its approval: within 5 days of receipt.
PROGRESS SCHEDULES. 9.1. To enable the Work to be performed in an orderly and expeditious manner, the Contractor, within fifteen (15) Days after the Notice to Proceed or Order to Work, unless otherwise directed by the Engineer, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:
9.1.1. The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and
9.1.2. The sequence and interrelation of each of these operations with the others and with those of other related contracts; and
9.1.3. The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and
9.1.4. The estimated amount in dollars the Contractor will claim on a monthly basis.
9.2. The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.
9.3. If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule. The approval by the City of a progress schedule which