Services and other things provided by the Employer Sample Clauses

Services and other things provided by the Employer. Describe what the Employer will provide such as services (including water and electricity) and “free issue” plant and materials and equipment.
AutoNDA by SimpleDocs
Services and other things provided by the Employer. 3.1. Site Services Provided by the Employer
Services and other things provided by the Employer. The employer shall provide power, water, waste disposal areas, lighting and ablution. Any additional lighting requirements around the work area shall be provided by the Contractor. The Contractor shall provide everything else necessary for providing the Works. The Employer will ensure access to the site for personnel qualifying as per the Employers requirements for access control. The Employer will do the induction training for the Contractor. Contractor has submitted the valid Certificate of Compliance. The Contractor adheres to the site services requirements and procedure  The Employer supplies, free of charge, reasonable quantities of potable water required for the purposes of this contract from the existing points. The Contractor provides, at his own cost, all connection fittings, pipe work, temporary plumbing, and pumps necessary to lead the water from the Employer’s points of supply to the various points where it is required.  Power is available at the existing points.  The Contractor provides his own portable 380V electrical distribution boards, and supply cables to and from the boards, for all his power supply requirements to execute the works.  Contractor’s Electrical Distribution Boards complies with OHSA as referred to in the Electrical Installation Regulations and the Electrical Machinery Regulations. Each board brought onto site has a Certificate of Compliance issued by an accredited person.  The Contractor’s electrical distribution boards are installed at the works on a time negotiated with the Supervisor, prior to the possession date.  The Employer connects distribution boards to a 380V three-phase AC power supply, only after the Contractor has submitted the valid Certificate of Compliance. All Contractors' Electrical Distribution Boards are earthed to the steel structure of the plant.  The Employer provides the Contractor access to identified existing toilet facilities.  The Contractor provides a First Aid service to his employees and sub-Contractors. In the case where these prove to be inadequate, like in the event of a serious injury, the Employer’s Medical Centre and facilities will be available.  Outside the Employer’s office hours, the Employer’s First Aid Services are only available for serious injuries and life threatening situations.  The Employer recovers the costs incurred, in the use of the above Employer’s facilities, from the
Services and other things provided by the Employer. Describe what the Employer will provide such as services (including water and electricity) and “free issue” Plant and Materials and equipment. C4: Site Information The bypass is situated in the North East Grid in Mpumalanga near Embalenhle township and the Sasol Secunda Plant. The work area will be within the enclosed area as depicted below. There are three (3) 400kV lines within the enclosure; Camden Sol 1 &2 plus Xxxxx Tutuka – the enclosure was installed owing to the fact that the lines in that section are below the ground clearance as per the SANS10280 and is thus a safey concern due to close proximity of persons and vehicles in the area. GPS Co-ordinates: -26.5503710S, 29.0991190E C4.1: Information about the site at time of tender which may affect the work in this contract 1. Access limitations 2. Ground conditions in areas affected by work in this contract 3. Hidden and other services within the site 4. Details of existing buildings / facilities which Contractor is required to work on
Services and other things provided by the Employer. The Employer’s Representative will arrange the induction Water in a form of Low Pressure Service and Electricity Compressed air Scaffolding Before commencement of the project As and when required at a designated site assigned to the contractor by the employer for establishment As and when required As and when required C4: Site Information Kendal Power Station is situated approximately 40km South West of Witbank in the Mpumalanga province. Construction started in 1982 and took 11 years to complete. Kendal Power Station comprises six generating sets (Units) of 686 MW each, the station capacity is 4116 MW, which is indirectly dry-cooled. The generators produces electricity at a voltage of 22KV, the generator transformers steps up the transmission voltage to 400kV. Kendal Power Station receives its coal supply of over a million tons per month from a neighbouring mine Khutala as well as other sources with varying characteristics. The ash that remains after the combustion of coal has two grading i.e. coarse ash (5% of total ash) and fly ash (95% of total ash). The fly ash together with waste gasses passes through the electrostatic precipitators where 99.9% of the ash is collected. The coal ash is removed by a submerged scraper conveyor to the apron conveyor. The fly ash is moistened and mixed in the ash conditioners. Both grading of ash are transported via the overland conveyors to the ash dump, where it is spread by an ash spreader, levelled and covered with topsoil and finally regressed. The power station is a Zero Liquid Effluent Discharge Station and ISO 14001 compliant. The main access gate to the Power Station is at 26° 5'0.96"S and 28°58'29.01"E. C4.1 Information about the site at time of tender which may affect the work in this contract 1. Access limitations 2. Ground conditions in areas affected by work in this contract 3. Hidden and other services within the site 4. Details of existing buildings / facilities which Contractor is required to work on
Services and other things provided by the Employer. The Employer (Eskom) will supply Galvanized poles; solar panel; brackets and all necessary cables.  Avail staff and measuring and testing equipment to commission the sirens after fitment.  Access to the various sites, with prior arrangement.  Koeberg maintenance team oversight and assistance.  The Koeberg team will be responsible to commission the sirens after installation has been verified.  The Contractor would not be required to be established on site. Hence, there is no requirement for a dedicated computer with LAN access and a telephone. C4: Site Information Work will be done in 31 different siren locations, offsite 16km radius of Koeberg in an outside environment, digging holes while removing and installing siren poles. C4.1: Information about the site at time of tender which may affect the work in this contract
Services and other things provided by the Employer. The employer shall provide power, water, waste disposal areas, lighting and ablution. Any additional lighting requirements around the work area shall be provided by the Contractor. The Contractor shall provide everything else necessary for providing the Works. The Employer will ensure access to the site for personnel qualifying as per the Employers requirements for access control. The Employer will do the induction training for the Contractor. Contractor has submitted the valid Certificate of Compliance. The Contractor adheres to the site services requirements and procedure  The Employer supplies, free of charge, reasonable quantities of potable water required for the purposes of this contract from the existing points. The Contractor provides, at his own cost, all connection fittings, pipe work, temporary plumbing, and pumps necessary to lead the water from the Employer’s points of supply to the various points where it is required.
AutoNDA by SimpleDocs
Services and other things provided by the Employer. The Employer will, at his expense, arrange for, develop and maintain the various facilities and services at or near the Site, as applicable. The services and facilities provided by the Employer are listed below:  Electricity;  Water supply; and  Sanitary Services.  Induction training for the Contractor.  Site for the Contractor’s yard at a location that is indicated to the Contractor. The Contractor provides all the facilities required by him for such a site at his cost C4: Site Information C4.1: Information about the site at time of tender which may affect the work in this contract
Services and other things provided by the Employer. The Contractor shall make himself acquainted with the position of all existing services before any excavation or other work likely to affect the existing services is commenced. The Contractor will be held responsible for any damage to known existing services caused by or arising out of his operations and any damage shall be made good at his own expense. Damage to unknown services shall be repaired as soon as possible and liability shall be determined on site when such damage should occur.
Services and other things provided by the Employer. None. All equipment to be provided the Contractor. C4: Site Information C4.1: Information about the site at time of tender which may affect the work in this contract 1. Access limitations 2. Ground conditions in areas affected by work in this contract
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!