Unanticipated Changes Sample Clauses

Unanticipated Changes. Client agrees that some changes in costs associated with clinical research resulting from, for example, changes to Project Specifications resulting from modifications to the study protocol, delays in receipt of study drugs from Client, changes in amounts charged by third party suppliers or poor subject enrollment due to changes in clinical practices, cannot be reasonably anticipated in advance. Upon identification by either Party of changes to the project assumptions or other unanticipated changes to the Project Specifications, the Parties will negotiate in good faith an Amendment to accommodate increases or decreases to the Project Budget, Project Schedule or Payment Schedule that are reasonably associated with any such adjustments. Amendments will be documented in accordance with the terms of this Section 2.2. Such unanticipated changes may include, but are not limited to, any of the following: i. delays in receiving from Client technical information or Client's acceptance of documents submitted by Aptiv Solutions in the performance of its duties under this Agreement or any Project Agreement, or any other delay on the part of Client; ii. delay in receipt of regulatory approval from a regulatory agency, IRB or Ethics Committee; iii. delay in performance by a Subcontractor not selected by Aptiv Solutions;
AutoNDA by SimpleDocs
Unanticipated Changes. If and as a result of any law, regulation, order or act of a government authority or other competent authority, it becomes necessary, at the Lessor’s discretion, to perform any changes whatsoever in the system for the supply of the Electricity Services to the leased property, the Lessor shall make the aforesaid changes, without the Lessee raising any contention and/or claim whatsoever in respect of making the change as aforesaid and the Lessee shall pay the expenses entailed by the works as aforesaid.
Unanticipated Changes. Sponsor agrees that some changes in costs associated with clinical research resulting from, for example, changes to Project Specifications resulting from modifications to the study protocol, delays in receipt of study drugs from Sponsor, changes in amounts charged by third party suppliers or poor subject enrollment due to changes in clinical practices, cannot be reasonably anticipated in advance. Upon identification by either party of changes to the project assumptions or other unanticipated changes to the Project Specifications, the Parties will negotiate in good faith an Amendment to accommodate increases or decreases to the Project Budget, Project Schedule or Payment Schedule that are reasonably associated with any such adjustments. Amendments will be documented in accordance with the terms of this Section 2.2. Such unanticipated changes may include, but are not limited to, any of the following: i. delays in receiving from Sponsor technical information or Sponsor's acceptance of documents submitted by PRA in the performance of its duties under this Agreement or any Task Order, or any other delay on the part of Sponsor; ii. delay in receipt of regulatory approval from a regulatory agency, IRB or Ethics Committee; iii. delay in performance by a Subcontractor not selected by PRA; iv. delay in shipment of study drug, clinical samples and/or clinical supplies; x. xxxxx due to changes in standard of care imposed by law, regulation or changes in medical practice affecting participating sites; vi. delay by reason of force majeure as defined herein; vii. Sponsor requested changes to the Services or protocol; viii. delays due to questions received by either party from regulatory agencies or ethics committees regarding submission materials that relate to characteristics of the study drug or protocol design; ix. delays due to any changes in applicable law or regulatory environment; or x. changes for any other reason agreed upon in writing by Sponsor.
Unanticipated Changes. If: (a) there are material unanticipated changes in the operating and capital costs of the Project due to circumstances which could not reasonably be foreseen and controlled by the Producer; (b) for reasons beyond the control of the Producer, the cost of constructing or operating the New Project is materially different from the estimates of such costs provided by the Producer to the Utility; or (c) the average production of the Mollejon Project is materially different from 80 Gwh per annum or the combined average production of the Mollejon Project and the New Project is materially different from 160 Gwh per annum, then the Utility and the Producer undertake that they shall use their best efforts to negotiate appropriate amendments to the foregoing prices, subject to the approval of the Public Utilities Commission.
Unanticipated Changes. Where unanticipated changes to previously posted rehearsal schedules occur, as the result of changing circumstances, the Engager shall notify the Artist personally of the correct rehearsal call no later than by the end of daily class on the day preceding the rehearsal. The Artist must inform the Engager forty-eight
Unanticipated Changes. In the event of a significant and unanticipated change in technology or business processes during the Term materially reduces Supplier’s cost of providing the Services, Supplier will reduce the Charges by an amount that reflects such reduction.
Unanticipated Changes. If as a result of any statute, regulation, order or act of a competent authority, the necessity arises, to make any changes whatsoever in the electricity services supply system to the Premises, the Lessor and/or the Lessee shall make the afore-mentioned changes. Insofar as the required changes are to electricity apparatus that was installed by the Lessor outside of the area of the Premises, the Lessor shall perform the changes at its own expense; insofar as the changes necessary will be within the area of the Premises, these changes shall be performed by the Lessee, at its own expense.
AutoNDA by SimpleDocs
Unanticipated Changes. (1) Tesla is entitled to a reasonable adjustment to the Price and Work Schedule, as applicable, if an Unanticipated Change increases Tesla’s costs, or adversely affects Tesla’s ability to meet the Work Schedule. However, for Unanticipated Changes involving Force Majeure Events, Tesla shall be entitled only to a reasonable adjustment to the Work Schedule, and not to the Price. “Unanticipated Change” means a Buyer Caused Delay, a Change in Law, a Differing Site Condition, a Force Majeure Event (each as defined below).
Unanticipated Changes. After the Chief approves an application and a purchase order has been issued for a project, the landowner shall present any unanticipated changes to the contract price to the Division in writing prior to completion of the work. Those unanticipated changes must be changes necessary to properly plug and restore an orphan well. The Chief shall make a decision on whether the change is unanticipated, necessary, and if the costs are reasonable prior to approving or denying the request in writing. Once the Chief approves a change, the Division will issue an additional purchase order to the contractor. The Division has made forms available on its website for this process. A request for form documents can be made by calling (000) 000-0000 or emailing XxxxxxXxxxXxxxxxx@xxx.xxxx.xxx
Unanticipated Changes. The Parties agrees that some changes in costs incurred in the course of performing clinical research cannot be reasonably anticipated in advance. Upon identification by either Party of changes to the project assumptions or other unanticipated changes to the Project Specifications that will result in such material changes in costs, the Parties agree to negotiate in good faith an Amendment to accommodate increases or decreases to the Budget for Services, Project Schedule or Payment Schedule that are reasonably associated with any such adjustments. Amendments will be documented in writing in accordance with the terms of this Section 2.2. Such unanticipated changes may include, but are not limited to, any of the following:  i. delays in receiving from Client technical information or Client's acceptance of documents submitted by Premier in the performance of its duties under this Agreement or any Work Order, or any other delay on the part of Client; ii. delay in receipt of regulatory approval from a regulatory agency, IRB or Ethics Committee; iii. delay in performance by a Subcontractor not selected by Premier;