SCHEDULING OF THE WORK Sample Clauses

SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is 5. These working days shall be consecutive. The Contractor is not required to submit a schedule for this project. Liquidated damages will be assessed beyond the number of working days specified above as well as the completion date as noted in this tender form and agreement. The Contractor must advise the Engineer 48 hours in advance of work starting.
AutoNDA by SimpleDocs
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is 10. These workings days shall be consecutive. Liquidated damages will be assessed beyond the approved schedule.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is fifteen (15) working days. No claims for delays caused by whatever external agencies or factors shall be allowed. The Contractor shall work Saturdays (if he deems necessary to meet deadline) and/or maximize the hours per day on site. Note that construction is not permitted to start on site before 4 November 2019. The bridge/roadway (entire width) complete with asphalt seal, must be opened to traffic no later than 22 November 2019, with no interruption to traffic after this date. The overall project must be completed no later than 22 November 2019. All bidders shall supply a Preliminary Construction Schedule with his Tender Documents for review by the Department. Note that the Department’s evaluation of submitted bids shall include reviewing the Preliminary Schedule including but not limited to the benefit(s) of earlier completion, bridge/roadway open to traffic (entire width), and overall project completion date. Note that the tender deadline dates indicated for bridge/roadway open to traffic (entire width), and/or overall project completion are the latest acceptable dates, with earlier dates acceptable. Prior to Contract award, the selected Bidder shall submit a detailed Final Construction Schedule to the Department for review. The Final Construction Schedule shall identify all primary work activities (eg: excavation, demolition, rock placement, structure installation, earthwork backfill, road work, asphalt paving, guardrails, etc). The Final Schedule shall indicate applicable time lines and milestones for all work activities. Throughout the project the Contractor shall notify the Department of any situations that may negatively affect the project’s Final Construction Schedule. The Contractor shall, upon the Department’s request at any time throughout the project, update and submit to the Department an updated Construction Schedule as deems required to reflect any circumstances that may cause the need for an updated Schedule.
SCHEDULING OF THE WORK. (a) The Contract Schedule shall represent a practical plan to achieve Mechanical Completion and Substantial Completion on or before the Guaranteed Substantial Completion Date. The Guaranteed Substantial Completion Date, not the Contract Schedule, shall control in the determination of any Delay Liquidated Damages. Contractor shall prepare and keep current a schedule of submittals as required by this Agreement and that is coordinated with the Contract Schedule.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is fifteen (15) working days. No claims for delays caused by whatever external agencies or factors shall be allowed. The Contractor shall work Saturdays (if he deems necessary to meet deadline) and/or maximize the hours per day on site. Note that construction must start on site on 26 October 2020. The detour (road closure) shall not be in-place until this date. The bridge/roadway (entire width) must be opened to traffic no later than 27 November 2020, with no interruption to traffic after this date. The overall project must be completed no later than 27 November 2020. All bidders shall supply a Preliminary Construction Schedule with his Tender Documents for review by the Department. Note that the Department’s evaluation of submitted bids shall include reviewing the Preliminary Schedule including but not limited to the benefit(s) of earlier completion, bridge/roadway open to traffic (entire width), and overall project completion date. Note that the tender deadline dates indicated for any Phase(s), bridge/roadway open to traffic (entire width), and/or overall project completion are the latest acceptable dates, with earlier dates acceptable.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is 20. These workings days shall be consecutive. Liquidated damages will be assessed beyond the approved schedule. Utility crews (Aliant, Maritime Electric, etc.) will be carrying out work on site at various stages of the project. The Contractor shall coordinate their work schedules with this work and no additional compensation will be provided for any delays. Regular job site meetings will be held to discuss job progress, environmental concerns, safety, traffic flow etc. The Contractor shall make available for this meeting a representative with the authority to act for the Contractor. The Contractor must advise the Engineer 48 hours in advance of work starting.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is to be determined. These working days shall be consecutive. Due to the COVID-19 pandemic, all schedules and completion dates may be subject to change.
AutoNDA by SimpleDocs
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is 20. These workings days shall be consecutive. Liquidated damages will be assessed beyond the approved schedule. Utility crews (Aliant, Maritime Electric, etc.) will be carrying out work on site at various stages of the project. The Contractor shall coordinate their schedules with this work and no additional compensation will be provided for any delays. Should any utility poles require to be braced during construction, costs associated with this work shall be absorbed by the Contractor. Regular job site meetings will be held to discuss job progress, environmental concerns, safety, traffic flow etc. The Contractor shall make available for this meeting a representative with the authority to act for the Contractor. Driveway accesses must be maintained throughout the project. Contractor shall coordinate culvert removal and replacement with residents and businesses. The Contractor must advise the Engineer 48 hours in advance of work starting. Construction shall not commence until federal funding is approved.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is 30. These workings days shall be consecutive. Liquidated damages will be assessed beyond the approved schedule. The Town of Three Rivers, Maritime Electric, East Link and Bell Aliant may have utilities in the area. It is the responsibility of the Contractor to co-ordinate the work with the utility companies. It may be necessary to brace or hold poles during construction. The method used must meet approval by the owners of the poles, whom are Maritime Electric and/or Bell Aliant.
SCHEDULING OF THE WORK. The number of working days stipulated for this Contract is fifteen (15) working days. No claims for delays caused by whatever external agencies or factors shall be allowed. The Contractor shall work Saturdays (if he deems necessary to meet deadline) and/or maximize the hours per day on site. Note that construction must start on site on 30 May 2022. The bridge/roadway (entire width) complete with asphalt seal and guardrails must be opened to traffic no later than 8 July 2022, with no interruption to traffic after this date. The overall project must be completed no later than 8 July 2022. All bidders shall supply a Preliminary Construction Schedule with his Tender Documents for review by the Department. Note that the Department’s evaluation of submitted bids shall include reviewing the Preliminary Schedule including but not limited to the benefit(s) of earlier completion, bridge/roadway open to traffic (entire width), and overall project completion date. Note that the tender deadline dates indicated for any Phase(s), bridge/roadway open to traffic (entire width), and/or overall project completion are the latest acceptable dates, with earlier dates acceptable.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!